Installation and operating manual Valid for the following Meyer Burger photovoltaic modules: MEYER BURGER BLACK MEYER BURGER WHITE MEYER BURGER GLASS...
Contents 1. Introduction 1.1 General information 1.2 Intended use 2. Electrical planning, design and wiring 2.1 Scope 2.2 Certification and technical data of PV modules 2.3 Electrical design and planning 2.4 Series connection 2.5 Parallel connection 2.6 Combined connection 2.7 Safety during electrical installation 2.8 Electrical installation 2.9 Equipotential bonding, grounding and lightning protection 3.
1. Introduction Observe all required local, regional Congratulations on the purchase of your high-efficiency and national (safety) regulations and photovoltaic module (hereinafter referred to as PV module) ordinances, as well as all technical, from Meyer Burger Industries (hereinafter referred to as MBI). electrical and structural standards when Meyer Burger PV modules offer particularly sustainable and designing and installing the PV system. climate-friendly energy production, as no greenhouse gases Occupational safety regulations must be are produced in the solar cells during power generation. observed and occupational health and MBI strives for sustainable production of PV modules. safety must be guaranteed at all times. This is why MBI focuses from the very start on high-quality materials, resource-conserving production processes, maximum recyclability in the sense of the circular economy, reliable and transparent supply chains and optimised transport A photovoltaic module is an electrical routes. MBI PV modules enable environmentally friendly product. There is a risk of electric shock conversion of solar energy directly into electrical energy in the event of incorrect handling and indefinitely and for several decades.
2.2 Certification and technical data of PV modules Observe all required local, regional The PV modules are tested and approved according to and national (safety) regulations and IEC 61215-2016 and IEC 61730-2016. Please refer to the ordinances as well as all technical and corresponding data sheets for the further list of current electrical standards when designing the available certificates, as well as all technical and electrical data. PV system. These can be found on our website www.meyerburger.com. 2.4 Series connection • T he PV modules can be connected in series to achieve 2.3 Electrical design and planning the desired total voltage. • M eyer Burger PV modules have three pre-installed bypass • T he current (I ) of the PV modules connected in series diodes (non-replaceable) that ensure protection and should be identical, as the maximum current is determined...
• A lways connect the cables with a suitable identical plug, do not trap them and protect them from mechanical stress. • E nsure that the cables are routed so that there are no loops (minimise the risk of induction during thunderstorms). • I t is recommended to place PV modules with the same orientation and inclination in a string to achieve 2.7 Safety during electrical installation maximum yields. The following safety instructions must be observed • C onnect the module string to an inverter suitable at all times: for the layout. • W ork may only be carried out by qualified personnel. • T he applicable safety instructions and regulations 2.9 Equipotential bonding, grounding and lightning protection must be observed.
• I n the immediate vicinity of air conditioning • N o third-party products may be placed or stacked on the and ventilation systems pallets and PV modules. • T he PV modules must not be used as a replacement • F urther transport recommendations can be requested for roof coverings or facades. from Meyer Burger. • F or installations closer than 500 m to the sea, special • T he PV modules may only be touched on the module precautions must be taken with regard to grounding, frame with clean gloves. maintenance and cleaning. • W hen unpacking the PV modules, the front side must be • T he PV modules must not be in direct contact with salt water.
• T he fixing must be stress-free to allow for temperature- related changes in length. • A minimum distance of 5 mm between the PV modules is recommended. Local, country-specific building • T he PV modules can be fastened using clamps or insert regulations must be observed. rails. The MEYER BURGER WHITE and MEYER BURGER BLACK PV modules can also be fastened using a screw connection (point connection) (see table in Section 3.7). 3.4 Freedom from shade • T here must be no components between the profiles of the Optimal solar radiation results in maximum energy yield: substructure and the PV modules. • I nstall the front of the PV modules facing the solar • S harp edges and point loads of the substructure under the radiation. The electrical connection box is located on the PV modules must be avoided.
3.6 Clamping system Clamps that meet the following requirements must be used: • M inimum clamping width 40 mm • C lamping height for 35 mm frame height • C lamping depth 7–11 mm • S tatic requirements of the respective site • L ong-term stable clamps • T he clamps must not touch the front glass. • T he clamps must not cast shade on any cells. End clamp • T he clamps must not damage or deform the frame of the module. • C lamps must be attached to the substructure as specified by the substructure manufacturer, including specific hardware and torque requirements. A maximum torque of 20 Nm must not be exceeded.
3.7 Installation types The overview table shows all permissible installation types and the corresponding maximum pressure and suction loads. including the associated test loads according to IEC 61215. Suitable fastening variants can be developed in consultation The following tables show in detail the different assembly with MBI for assembly with unspecified installation types or variants (sketches), the permissible associated fixing areas with increased loads. Module Installation type Design load Test load (1.5x safety) WHITE BLACK GLASS Name L [mm] W [mm] Pressure [Pa] Suction [Pa] Pressure [Pa] Suction [Pa] 4000 2666 6000 4000...
Page 11
Design load Test load (1.5x safety) Pressure Suction Pressure Suction Module L [mm] [Pa] [Pa] [Pa] [Pa] 4000 2666 6000 4000 WHITE, BLACK, 200 - 450 3600 1600 5400 2400 GLASS 0 - 550 1600 1600 2400 2400 = Clamp point INSTALLATION TYPE CP1a Fastening with 4 module clamps on the long module side,...
Page 12
PERMISSIBLE LOADS (PRESSURE, SUCTION) Design load Test load (1.5x safety) Pressure Suction Pressure Suction Module [mm] [Pa] [Pa] [Pa] [Pa] = Clamp point WHITE, BLACK, 160 - 210 1600 1600 2400 2400 GLASS INSTALLATION TYPE CP2a Fastening with 4 module clamps on the short module side, point mounting without continuous substructure rails PERMISSIBLE LOADS (PRESSURE, SUCTION) CP2a Design load Test load (1.5x safety)
Page 13
Test load (1.5x safety) Pressure Suction Pressure Suction Module [mm] [Pa] [Pa] [Pa] [Pa] = Clamp point 3600 2666 5400 4000 WHITE, BLACK, 200 - 450 3600 1600 5400 2400 GLASS 0 - 550 1600 1600 2400 2400 INSTALLATION TYPE CL2 Fastening with 4 module clamps on the short module side, line mounting along the short module side PERMISSIBLE LOADS (PRESSURE, SUCTION) Design load Test load (1.5x safety)
Page 14
PERMISSIBLE LOADS (PRESSURE, SUCTION) Design load Test load (1.5x safety) Pressure Suction Pressure Suction Module [Pa] [Pa] [Pa] [Pa] WHITE, BLACK, 3600 2666 5400 4000 GLASS INSTALLATION TYPE IP2 Fastening via line mounting with insert profile rails on the short module side PERMISSIBLE LOADS (PRESSURE, SUCTION) Design load Test load (1.5x safety)
Page 15
PERMISSIBLE LOADS (PRESSURE, SUCTION) Design load Test load (1.5x safety) Pressure Suction Pressure Suction Module [mm] [Pa] [Pa] [Pa] [Pa] WHITE, 4000 2666 6000 4000 BLACK = Mounting point INSTALLATION TYPE MP1a Fastening at the mounting points on the long module side, line mounting along the long module side PERMISSIBLE LOADS (PRESSURE, SUCTION) MP1a Design load Test load (1.5x safety)
3.8 Fire protection 4.2 Cleaning • W hen installing on the roof, the PV modules may only • U se sufficient water and a soft cloth to clean the be installed over a fire-resistant roof cover ("hard roof"). PV modules. This excludes the in-roof installation of the PV modules. • T he PV modules must only be cleaned manually. • D o not use high-pressure cleaners for cleaning. • A llow the PV modules to cool down before cleaning. Improper installation can lead to fires/ • N ever touch glass with bare hands as this may leave fire hazards. Observe all necessary local, fingerprints.
6. Dismantling and recycling • W hen disassembling the system, the (dis)assembly/ installation manual for the other installed system components must be observed. The work may only be carried out by qualified personnel. • T he five safety rules of electrical engineering must be observed. • T he inverter must be switched off and its switch-off time interval observed. • T he PV modules must be disconnected from the inverter. It is essential to ensure and check that the inverter is de-energised. • T he plugs must only be disconnected with suitable specialist tools. • C heck the components for damage. Meyer Burger (Industries) GmbH Carl-Schiffner-Strasse 17 09599 Freiberg Germany www.meyerburger.com WEEE reg. no. DE 18170271...