Une ZHERO S10 Installation And User Manual

Table of Contents

Advertisement

Quick Links

INSTALLATION AND USER MANUAL
ZHERO THREE-PHASE
STORAGE SYSTEM INSTALLATION AND OPERATING MANUAL
ZHERO THREE-PHASE S10

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ZHERO S10 and is the answer not in the manual?

Questions and answers

Summary of Contents for Une ZHERO S10

  • Page 1 INSTALLATION AND USER MANUAL ZHERO THREE-PHASE STORAGE SYSTEM INSTALLATION AND OPERATING MANUAL ZHERO THREE-PHASE S10...
  • Page 2 PAG. 2 of 111...
  • Page 3 Throughout the life of the UNE ZHERO S10, please keep this manual in a safe place and ensure that it is available to all technical personnel working on the UNE ZHERO S10.
  • Page 4: Table Of Contents

    1.10. ESIDUAL RISKS - GENERAL PRODUCT OVERVIEW 2.1. ENERAL ESCRIPTION 2.1.1. ON-G RID SYSTEM 2.1.2. ON-GRID OFF-GIRD SYSTEM 2.2. UNE ZHERO S10 AMEPLATE OF 2.3. ECHNICAL 2.4. BOX I NVERTER 2.5. ATTERY 2.6. WITCH PANEL 2.7. INPUT TERMINAL BLOCK 2.8.
  • Page 5 AIN SWITCH DOWNSTREAM OF THE CHANGEOVER COUNTER 3.10. SER ELECTRICAL SYSTEM 3.11. RELIMINARY PERATIONS 3.12. URTHER ESIGN UIDELINES 3.13. UNE ZHERO S10 ONNECTION DIAGRAM OF - INSTALLATION 4.1. ATTERY INSTALLATION 4.2. ONTROLLER SHELF INSTALLATION 4.3. ONNECTING THE PHOTOVOLTAIC SYSTEM 4.4. SIDE CONNECTION 4.4.1.
  • Page 6 10.2. ECURITY CHECKS 10.2.2. BOARD SWITCH TEST 10.3. UPERVISION 10.3.1. & W EBSERVER EBAPP 10.4. “S ” TANDARD FUNCTION 10.5. “C ” YCLIC EQUALISATION FUNCTION 10.6. “C ” HARGE YSTERESIS FUNCTION 10.7. “F ” EED SURPLUS ENERGY INTO THE GRID FUNCTION 10.8.
  • Page 7: General Information

    (the EMPLOYER must carry out a risk assessment). 1.1. Manual recipients This manual contains important safety instructions which must be followed during the use of UNE ZHERO. The original language of this document is Italian, in case of inconsistencies or doubts please request the original document from UNE srl.
  • Page 8 UNE ZHERO. ATTENTION: It is forbidden to use the equipment in a way that does not comply with its field of application. Figure 1 – UNE ZHERO S10, UNE ZHERO S10, battery box left, inverter box right PAG. 8 of 111...
  • Page 9: Scope Of Validity

    This product may only be operated within its intended field of application, i.e., it is permitted for residential, commercial and industrial use, in 400V (three-phase) 50 Hz TT and TN-S networks, not IT or TN-C. For further information and questions, please contact UNE srl via the channels indicated in the contact section. 1.3.
  • Page 10: Symbols Used

    Failure to observe the warning The following usage tips can threatening and cause damage to may hinder an operating phase make it easier for you to use UNE the device. and possibly prevent optimal ZHERO and improve its operation of the device.
  • Page 11 “SYSTEM OPERATING RANGE” " WAITING TIME” “DEGREE OF PROTECTION” This symbol indicates the Wait a certain period of time Indicates the degree of operating range. before taking the indicated protection provided by action. mechanical and electrical enclosures against the intrusion of solid particles and access of liquids.
  • Page 12: Definitions Used

    INSTALLER STAND BY He who, after appropriate training, operates UNE Standby mode is the condition in which ZHERO with competence and expertise. electrical/electronic devices are not operating but are ready to switch from temporary inactivity to operational mode.
  • Page 13 WORKING MODE In electronics, a light-emitting diode or LED is an This means the operating mode of UNE ZHERO, optoelectronic device that exploits the optical depending on how it is programmed it can be Off- properties of certain semiconductor materials to Grid, On-Grid with backup.
  • Page 14: General Information

    ATTENTION: Always keep the safety warnings and manuals supplied with the UNE ZHERO at hand. ATTENTION: UNE srl declines all responsibility in the event of failure to comply with the rules for correct installation and is not liable for the proper execution of the systems upstream or downstream of the equipment supplied by it.
  • Page 15 ATTENTION: Installation under environmental conditions other than those indicated in the chap.3.3. The maintainer of the UNE ZHERO S10 must bear the following warnings in mind: ATTENTION: UNE srl disclaims all liability in the event of failure to comply with the rules for proper maintenance and is not liable for the proper maintenance of systems upstream or downstream of the equipment it supplies.
  • Page 16: Personal Protection

    20 minutes after the power has been removed. ATTENTION: Operations on UNE ZHERO "open external carter" may only be carried out by authorised personnel.
  • Page 17: Storage System

    ATTENTION: UNE ZHERO is NOT designed to supply vital medical equipment. ATTENTION: UNE ZHERO must not be used in installations where a power failure could cause personal injury. ATTENTION: Open external carter operations must be performed with the system switched off.
  • Page 18 The Residual Current Detection O RCD is guaranteed by the isolation control with which UNE ZHERO is equipped and which is visible in the disconnector panel at the top right, in the event of activation of the alarm the inverter can still continue to operate safely;...
  • Page 19: Limits Of The Field Of Application

    It is forbidden to use the equipment without having read and understood the contents of the • manuals; It is forbidden to obstruct the ventilation system; - It is forbidden to use UNE ZHERO as a UPS as it is • not certified for this use;...
  • Page 20: Residual Risks

    If, during the course of the work, the maintenance technician discovers obvious safety deficiencies whose removal is outside his remit (e.g. obstructions to ventilation, changes to external UNE ZHERO installations which could lead to serious risks to people's safety), these must be reported in writing, pointing out the need to eliminate them.
  • Page 21: General Product Overview

    UNE ZHERO, once correctly sized and installed according to your needs provides the energy required to power your electrical consumers. The UNE ZHERO S10 can operate in different modes depending on the needs of the customer and the installation site, some modes are not available in some countries, the external structure remains the...
  • Page 22: On-Grid System

    Being in parallel, the power available to the user is the sum of the power made available by UNE ZHERO (which varies depending on the availability of the photovoltaic and the battery, up to a maximum of 10 kW) and the power made available by the distributor to the user.
  • Page 23: On-Grid Eoff-Gird System

    2.1.2. ON-GRID e OFF-GIRD system UNE ZHERO works independently of any external network, creating its own network and serving the users by relying only on it. As there is no other network with which to work in parallel, the power available to the user is only that made available by UNE ZHERO, which varies according to the availability of the photovoltaic and battery, up to a maximum of 6kVA.
  • Page 24: Nameplate Of Une Zhero S10

    2.2. Nameplate of UNE ZHERO S10 Below is an example of a label that can be detected on the UNE ZHERO S10 system: Figure 2 - UNE ZHERO S10 nameplate 2.3. Technical Data The technical data of UNE ZHERO can be found in the datasheet.
  • Page 25: Box Inverter

    2.4. BOX Inverter Inverter BOX closed Upper carter Rear carter Switches Lamp Left carter Right carter Front carter PV inlet 4-5 Batteries inlet PV inlet 1-2-3 Lower carter Figure 3 - Front view BOX Inverter Figure 4 - Retro view BOX Inverter The following is a legend of the components that make up the exterior of the BOX Inverter: LEGEND DESCRIPTION...
  • Page 26 Inverter BOX open AC Inlet Protection interface Power modules Transformers Battery plugs RJ batteries Controller 4-5 Controller 1-2-3 Figure 5 - Front view BOX Inverter Figure 6 - Retro view BOX Inverter Below is a legend of the components that make up the inside of the Inverter BOX: LEGEND DESCRIPTION AC inlet...
  • Page 27: Battery Box

    2.5. Battery BOX BOX Inverter closed Upper carter Left carter Rear carter Battery carter Right carter Battery output Lower carter Figure 7 - Front view of battery box Figure 8 - Rear view of battery box The following is a legend of the components that make up the outside of the battery box: LEGEND DESCRIPTION Upper carter...
  • Page 28 Open battery BOX Battery 3 Battery plan Battery 2 Battery plan Battery 1 Battery plan 1 Figure 9 – Front view of the open battery Figure 10 – Rear view of the open battery The following is a legend of the components that make up the inside of the battery box: LEGEND DESCRIPTION Battery 3...
  • Page 29: Switch Panel

    The position of the UNE ZHERO S10 switch panel is located where indicated in the figure opposite. Figure 11 - Switch panel position PROTECTION ON-OFF Figure 12 - Front view of the UNE ZHERO S10 Switch Panel LEGEND DESCRIPTION PROTECTION Protection interface for connection to the local distributor network;...
  • Page 30: Ac Input Terminal Block

    Figure 13 - Position of AC input terminal blocks Backup line Cont. GRID side Grid input Cont. INVERTER side Figure 14 - Top view of the UNE ZHERO S10 system showing AC connections LEGEND DESCRIPTION Cont. GRID side Grid-side production meter connection terminal block; Grid input Grid connection terminal block from exchange meter;...
  • Page 31: Communication Connections

    2.8. Communication connections The UNE ZHERO S10 communication connections are shown below. The position of the UNE ZHERO S10 switch panel is located where indicated by the figure opposite. Figure 15 – Signal input position (Empty) Figure 16 – View of the signal connections at the top of the BOX Inverter...
  • Page 32: Photovoltaic Connections

    ATTENTION: In the case of the presence of sunlight irradiating the photovoltaic modules, there will be DC voltage from the photovoltaic system. Below is a legend of the components that the UNE ZHERO S10 photovoltaic input of the ZHERO system.
  • Page 33 BATTERY CONNECTIONS Below is a legend of the UNE ZHERO S10's battery connections. Negative poles Positive poles Figure 19 – View of power and signal connections of the UNE ZHERO S10 system LEGEND DESCRIPTION Negative poles Connection of the NEGATIVE battery poles;...
  • Page 34: Operations Prior To Installation

    3.1. Lifting and transporting UNE ZHERO is a very large and heavy product, so particular caution must be exercised during lifting, transport and handling so as not to cause hazards to property and persons. Transport must be carried out using appropriate means, as UNE ZHERO contains components that could be sensitive to shocks, vibrations, etc.
  • Page 35 ATTENTION: The means used for lifting must be suitable for supporting the weight of the equipment in excess of 350 kg. ATTENTION: Due to the weight and bulk of the UNE ZHERO it is always necessary to call in specialised personnel for transport, handling, loading and unloading.
  • Page 36: Tools Required For Installation

    3.2. Tools required for installation The following is a list of the main tools that an installer must be equipped with in order to properly install the UNE ZHERO S10 system. “FUSES” “SCREWDRIVER” “CURRENT CLAMP” Suitable for the current and...
  • Page 37: Environmental And General Installation Conditions

    However, this function is not to be considered equal to a UPS because UNE ZHERO is not certified as such but as a storage system with a backup function; moreover, it does not filter the public network and does not stabilise it.
  • Page 38: Positioning Of Une Zhero S10

    In floors suitable to support the weight of UNE ZHERO. • ATTENTION: The UNE ZHERO S10 must be anchored to the ground by means of the holes in the base to prevent it from tipping over. ATTENTION: It is essential to assess the suitability of the floor on which UNE ZHERO is placed in order to determine its ability to support the weight of the system (approx.
  • Page 39 MINIMUM DISTANCES BOX INVERTER BOX BATTERIE Frontal distances 1500 mm 1500 mm Rear distances 100 mm 100 mm Distances on the left side * 500 mm 500 mm Right-hand side distances * 500 mm 500 mm Upper distance 500 mm 500 mm * If the battery box is present, it can be placed against the left side of the inverter, not the left side as this is the connection side with the PV array.
  • Page 40: Unpacking

    During the unpacking operation, preliminarily check the integrity of the contents and the presence of all components; if not, suspend all operations and contact UNE srl immediately. ATTENTION: Some elements of the packaging such as cardboard, nails, etc. can be dangerous and lead to personal injury or property damage, so they must be removed by appropriate means.
  • Page 41: Preliminary Work On Electrical Connections

    Preliminary Work on Electrical Connections In order to facilitate installation and maintenance of the UNE ZHERO S10, it is possible to remove all the painted external casings of the UNE ZHERO S10 system with the exception of the rear casing, which provides considerable resistance to diagonal deformation.
  • Page 42 All types of modules can be connected which do not require one of the poles of the electrical system to be earthed. If in fact one pole of the electrical system were to be connected to earth, the UNE ZHERO's internal insulation resistance control would detect an anomaly and block the feeding of energy from the generator.
  • Page 43: Dimensioning The Photovoltaic System

    In addition, the correct polarity must be checked before connecting. ATTENTION: consider variations in module voltage as temperatures vary. Consult the technical data sheet of the photovoltaic modules that you intend to connect to UNE ZHERO. PAG. 43 of 111...
  • Page 44: Main Switch Downstream Of The Changeover Counter

    Before connecting the UNE ZHERO, it is necessary to check the electrical installation serving the customer, the switch fitted at the output of the UNE ZHERO serves to make the connection between the UNE ZHERO and the circuit breakers upstream of the electrical installation's protections, but in no way acts as protection for the user's electrical installation.
  • Page 45: Preliminary Operations

    3.12. Further Design Guidelines The electrical designer and the installer of the installation in which UNE ZHERO is inserted, each for their own tasks in accordance with and in compliance with the regulations in force at the place of installation, must check: Whether it is necessary to include a system to isolate the generator voltage in the perimeter of the •...
  • Page 46: Connection Diagram Of Une Zhero S10

    Below is the general connection diagram of the system, should you require further information please contact UNE srl directly (info@unesrl.com) Below are the connection diagrams of the 4 available types of UNE ZHERO S10 systems: UNE ZHERO S10 Trifase; •...
  • Page 47 BLOCK DIAGRAM - UNE ZHERO S10 THREE-PHASE BLOCK DIAGRAM - UNE ZHERO S10 RETROFIT PAG. 47 of 111...
  • Page 48 BLOCK DIAGRAM - UNE ZHERO S10 HYBRID BLOCK DIAGRAM - UNE ZHERO S10 OFF-GRID PAG. 48 of 111...
  • Page 49: Installation

    4.1. Battery installation UNE ZHERO S10 comes complete with batteries. ATTENTION: A battery can pose a risk of electric shock and high short-circuit current. The following precautions must be observed when working on batteries: Remove watches, rings, or other metal objects;...
  • Page 50 In some states it may still be necessary to transport separately. In this case, installation must be carried out as follows: Remove the 2 front and top panels of the battery BOX To remove them, use a screwdriver or drill to remove the 8 locking screws on the front and top panels.
  • Page 51 c) Fixing batteries Once positioned, screw the batteries onto the retaining lugs, these are already screwed to the base of their corresponding plane, there are 2 for each battery. Use an appropriate spanner to tighten an M6 hexagon head screw. Figure 28 –...
  • Page 52 Connection of power cables The cables exiting the battery poles (Positive, Negative and RJ-45 of Modbus 485) must be routed through the lower slot shown in the figure: In the upper slot RJ-45 signal cables; • In the lower slot the + and - power cables. •...
  • Page 53 Negative poles Positive poles Figure 32 – Detail of power and signal battery plug connection ATTENTION: Power cables can be connected in any pole of the respective connector; • Signal cables must NOT be interchanged. • PAG. 53 of 111...
  • Page 54: Controller Shelf Installation

    4.2. Controller shelf installation UNE ZHERO S10 is supplied complete with controller shelf. In some states it may still be necessary to transport separately. READ CAREFULLY: The MPPT shelf disassembly operation is identical for both MPPT shelfs, however, be careful not to reverse the lower with upper shelfs.
  • Page 55 d) Disconnect the RJ-45 plug and power cables from the front panel On the left, arrows indicate the position of the negative (top) and positive (bottom) power connectors. Be very careful not to reverse the polarities of the plugs: respect both the symbolism on the carpentry and the colour code: Positive pole - Colour red - Symbol + •...
  • Page 56: Connecting The Photovoltaic System

    Once the preliminary checks described in the preceding paragraphs have been carried out, the connection between the UNE ZHERO and the PV generator can be made. The number of strings that can be connected to the system varies depending on the model purchased, from 0 to 5.
  • Page 57 ATTENTION: Do not connect or disconnect the connectors under load and/or with UNE ZHERO switched on. Cables laid outside UNE ZHERO, i.e. not protected by its enclosure, must be protected by firmly anchored ducts with a degree of protection appropriate to the installation site.
  • Page 58 Figure 39 - Ferrites arrangement for photovoltaic strings at the input of the ZHERO system All cables coming from the photovoltaics must make 2 passes through the 6 ferrites in series type 5975003801 or equivalent. The pairs corresponding to the same photovoltaic string, exiting from these windings, must be passed through an additional ferrite type 0431176451 or equivalent.
  • Page 59: Ac-Side Connection

    Before proceeding with the connection, please pay attention to the following: ATTENTION: do not reverse the phases or one of the phases with neutral. ATTENTION: Cables laid outside UNE ZHERO, i.e. not protected by its enclosure, must be protected by conduits, firmly anchored, with a degree of protection appropriate to the installation environment and in compliance with the regulations in force at the place of installation.
  • Page 60: Connection: Distributor Network/ Gen-Set

    Grey Blue Green GNDG If it is an "OFF-GRID" genset system that can be connected to UNE ZHERO it must have the following characteristics: AC frequency between 48.5 and 52.5 Hz to keep the connection active; • AC frequency between 49 and 51 Hz to keep the connection active;...
  • Page 61 AC cables coming from the mains (R, S, T, N and PE), before being connected to the above mentioned connector, must be properly filtered using the following material and carefully following the instructions below: Figure 43 - Ferrite arrangement for the ZHERO system input network The AC cables coming from the user's installation (R, S, T, N and PE) must make 2 passes within the 2 ferrites in series type 04311772081 or equivalent, the 2 ferrites must be spaced 30 cm apart, in addition, the same cable must make a single pass within the ferrite type 0431176451 or equivalent.
  • Page 62: Connection: In-Out Production Counter (If Applicable)

    4.4.2. Connection: in-out production counter (if applicable) In some countries, regulations require the installation of a production meter at the same time as the installation of the photovoltaic system. This meter in many cases cannot be included in the system because it must be managed and supplied by the local distributor.
  • Page 63 T0 – T00 Blue N0 – N00 UNE ZHERO has been prepared for the installation of this external component; the procedure is as follows: Switch off UNE ZHERO by means of the "ON-OFF" disconnecting switch; Set the "INV" disconnecting switch to off;...
  • Page 64: Connection: Backup Line (If Applicable)

    4.4.3. Connection: backup line (if applicable) The backup output is represented by the 1st connection group: Backup BACKUP CONNECTION (LEFT TO RIGHT) Threaded insert Backup: Ground; → First screw Backup: Neutral; → Second screw Backup: Phase T; → Third screw Backup: Phase S;...
  • Page 65 Figure 48 - Ferrite arrangement for UNE ZHERO backup output AC cables coming from the user's installation (R, S, T, N and PE) must make 2 passes within the 2 ferrites in series type 04311772081 or equivalent, the 2 ferrites must be spaced 30 cm apart.
  • Page 66: Connecting The Meters

    THE EXCHANGE METER Present in all ON-GRID systems, this is a meter external to UNE ZHERO S10, which must be installed in series with the household/business exchange meter so that it measures exactly what is measured by the exchange meter.
  • Page 67: Gavazzi Et340

    ATTENTION: Do not install more than one meter in series or in parallel with the same function (both exchange and production). The meter is supplied together with the UNE ZHERO S10 product, the device is already parameterised, configured and tested.
  • Page 68 'WAT': COMMUNICATION CONNECTION - ZHERO STANDARD The communication connection must be made by inserting the RJ-45 cable in the WAT port of the UNE ZHERO S10 to the RJ-45 port of the exchange meter, as shown in the figure below: WAT port Figure 49 –...
  • Page 69 Figure 51 – Meter ET340 communication confirmation detail POWER CONNECTION - ZHERO STANDARD METER SCREW ORIGIN Phase 1 from the exchange counter Fase 2 from the exchange counter Fase 3 from the exchange counter EXCHANGE METER Phase 1 towards users and the ZHERO system Fase 2 towards users and the ZHERO system Fase 3 towards users and the ZHERO system PAG.
  • Page 70 COMMUNICATION CONNECTION - ZHERO RETROFIT & HYBRID: The communication connection must be made by inserting the RJ-45 cable in the WAT port of the UNE ZHERO S10 to the RJ-45 port of the exchange meter, as shown in the figure below: WAT port Figure 52 –...
  • Page 71 Figure 54 – Meter ET340 communication confirmation detail or check with special ZHERO Installer Tool software. POWER CONNECTION - ZHERO RETROFIT & HYBRID METER SCREW ORIGIN Phase 1 from the exchange counter Phase 2 from the exchange counter Phase 3 from the exchange counter EXCHANGE METER Phase 1 towards users and the ZHERO system Phase 2 towards users and the ZHERO system...
  • Page 72: Meter Lovato Dme D330

    PIN number of the RJ-45 connector and inserted into the connector marked 'WAT': COMMUNICATION CONNECTION - ZHERO STANDARD The communication connection must be made by inserting the RJ-45 cable in the WAT port of the UNE ZHERO S10 to the RJ-45 port of the exchange meter, as shown in the figure below:...
  • Page 73 WARNING: the Meters will count and measure what is connected downstream of the device, what happens upstream cannot be managed by UNE ZHERO. To verify correct installation, once the Meter has been powered up and the UNE ZHERO system switched on, check with the appropriate ZHERO Installer Tool software.
  • Page 74 SIGNAL CONNECTION - ZHERO RETROFIT & HYBRID The communication connection must be made by inserting the RJ-45 cable in the WAT port of the UNE ZHERO S10 to the RJ-45 port of the exchange meter, as shown in the figure...
  • Page 75 POWER CONNECTION – ZHERO RETROFIT & HYBRID METER SCREW ORIGIN Phase 1 from the exchange counter Phase 2 from the exchange counter Phase 3 from the exchange counter Neutral from the exchange counter I1 – S1 CT on phase 1 – arrow from the meter to the house EXCHANGE METER I1 –...
  • Page 76: Meter For Off-Grid Application

    4.5.3. Meter for OFF-Grid Application The OFF-Grid configuration does not require the installation of any meters. PAG. 76 of 111...
  • Page 77: Internet Connection

    Internet connection The system, whether for warranty, monitoring or service purposes, must be connected to the Internet; the ETH port on the UNE ZHERO S10 is located where indicated in the figure below. Port ETH Before making the connection, check that the cable connection is working, and if possible, check that the data communication on the webserver is successful.
  • Page 78 b) Connessione - Range extender In the event that such a connection is not possible, a WIFI-REPEATER with an Ethernet port, configured as a range extender for your network, should be used. Figure 61 - Connection via range extender No special features are required of this device; however we recommend purchasing a mid-range product, possibly supporting mesh networking, dual band 2.4 and 5 GHz and with an antenna powerful enough to reach the router.
  • Page 79 The section of RJ-45 cable exiting the ETH port of the UNE ZHERO system, before entering the router, range extender or powerline must be wound inside 4 ferrite rings 0475176451 or equivalent, carefully following the instructions below: The cable must be run 3 times inside each individual ferrite and the ferrites must be approximately 40 cm apart;...
  • Page 80: Start-Up And Shutdown

    - START-UP AND SHUTDOWN 5.1. Switching on the system Preliminary verifications: Verify the electricity grid connection; • Verify that the exchange meter and production meter are enabled; • Verify that the meter power cables are correctly connected; • Verify that the 485 meter terminator is only on the last meter in the series; •...
  • Page 81: Verification With "Zhero Installer Tool

    The programme is necessary in order to be able to verify the correct installation of the UNE ZHERO system, since verification of the correct installation is not provided by the UNE operator, but only has to be contacted in the event of a serious anomaly.
  • Page 82: Shutting Down The System

    If you intend to work on the system, you will also need to: Disable the "INV" circuit breaker by setting it “OFF”; • Disable the differential circuit breaker at the system input (not part of UNE ZHERO S10); • Open the photovoltaic circuit breakers.
  • Page 83: Maintenance

    There is no routine maintenance to be carried out on the system, but it is advisable to check the general state of cleanliness of the system and to visually inspect UNE ZHERO S10 annually to ensure that there are no obvious situations that could affect its proper functioning.
  • Page 84: Product Service

    Indicative date and time of the event encountered; • Description, as complete and detailed as possible, of the event/problem. • Once the email has been sent, UNE will receive the request for assistance and an operator will respond as quickly as possible. PAG. 84 of 111...
  • Page 85: Regulatory Compliance

    - REGULATORY COMPLIANCE SYSTEM - REGULATORY COMPLIANCE Mark Certification EN 62109-2 EN 62109-3 CEI EN 61000-6-1 (2007) CEI EN 61000-6-3 (2007) CEI 0-21: 2019-04 VDE 4105 -0124 06/2020 PAG. 85 of 111...
  • Page 86: Disposal

    UNE srl is registered with COBAT (Consorzio Nazionale Raccolta e Riciclo) for the disposal of electrical waste. UNE ZHERO, at the end of its life cycle, must be stored and disposed of according to the regulations in force in the country of installation.
  • Page 87: Operation Of The System

    Tips for optimal use In this section we will give you useful tips to make the most of your UNE ZHERO. All it takes is a few tricks to be able to consume in a 'smart' way while saving energy and not giving up your comforts.
  • Page 88 These are tips for optimal use, everything will continue to work smoothly even if the battery runs out. Furthermore, the battery available in the UNE ZHERO S10 has a high capacity; it is likely that, no matter how much you consume with heavy appliances (ovens, washing machines, etc.), it will not last overnight to finish its charge.
  • Page 89 With this in mind, you should start using all the electrical appliances in your home (iron, hoover, etc.), making sure that you have chosen the UNE ZHERO model with the appropriate battery capacity for your uses, so that this capacity is sufficient to cover your night-time needs.
  • Page 90: Security Checks

    10.2. Security checks To ensure proper functioning, it is advisable to carry out some checks on the system on a regular basis to avoid possible problems. It is necessary: Monitor whether the system sends notification e-mails; • Check the cleanliness and integrity of the outer casing; •...
  • Page 91 10.2.2. On-board INV switch test In order to verify the correct functioning of the ZHERO on-board life-saving device, it is necessary to: Disconnect as many loads as possible from the house; • Disconnect the photovoltaic system; • Press the test button on the 'INV' module as shown in the figure below. •...
  • Page 92: "Standard" Function

    10.3. Supervision The programme is necessary in order to be able to verify the correct installation of the UNE ZHERO system, since verification of the correct installation is not provided by the UNE operator but must only be contacted in the event of a serious fault.
  • Page 93: "Blackout" Function

    In the case of utilities not connected to the 'backup' line, any disruption cannot in any way be caused by the UNE ZHERO storage system. In the case of utilities connected to the “backup” line (if provided), it can be checked whether: The network is not within the legal limits;...
  • Page 94 10.13. “Retrofit – Hybrid” function UNE ZHERO Retrofit or Hybrid is set up to operate in such a way as to accumulate excess energy during the day and then distribute it to the user. Therefore, the user will first use the energy produced by its internal MPPT controllers (Hybrid configuration), then by the grid inverter, then that stored by the battery pack, and finally, only, if necessary, that from the distributor's grid.
  • Page 95 The battery pack is recharged following its own charging curve, so it is common during the day for overproduction to be released to the grid even though the battery is charging. This means that the optimal way to store the energy produced is on long days with average brightness, rather than short days with high production peaks.
  • Page 96: Fault Signalling

    Alarm or fault signalling is carried out, both for the user and the installer, via these two modes, which require no additional installation, only WEB registration: WARNING LIGHT ON BOARD UNE ZHERO S10 The “RED“ indicator light indicates the presence of an active alarm in the system.
  • Page 97 In the event of adverse environmental conditions (particularly violent storms, etc.), moisture may penetrate the connectors giving a temporary dispersion which disappears once the site has dried. In this case, even if UNE ZHERO is able to restart regularly, a check must be carried out.
  • Page 98: Battery Failure

    Battery failure Event In the event of a critical battery error, UNE ZHERO will attempt a battery reset. The system will disconnect the inverter and the user, if in Off-Grid, will be blacked out for a time of a few minutes.
  • Page 99 Inverter failure Event In the event of a fault in the inverter, UNE ZHERO will no longer be able to supply current from either the generator or the battery. In the most serious cases, it will not even be able to keep you connected to the local distributor's grid (if On-Grid) or to the backup generator (if Off-Grid), along the "backup"...
  • Page 100 IP on port 9090 TCP and UDP to data traffic. The problem could be in one of the following places: a) Switch lockout Connect UNE ZHERO directly RJ of the router (if network switches are present), to • remove any hardware between router and UNE ZHERO.
  • Page 101 Changing the connection network: Connect the UNE ZHERO to another network and see if communication resumes from there (wait at least 30 minutes), at which point the UNE ZHERO hardware problem would be definitively ruled out. (hotspot your mobile phone to a wi-fi repeater with an RJ port connected directly to the UNE ZHERO for example).
  • Page 102 The reasons for the failure could be various and not perfectly determinable. User behaviour If there is no possibility of an immediate reset, UNE ZHERO can be excluded by manually switching to the distributor's mains via an external diverter, which the installer must provide in the event of a backup line being present.
  • Page 103 On-Grid If the system does not connect to the distributor network, it is possible that the voltage or frequency is outside the ranges accepted by UNE ZHERO, see cap. 5.9.3. Off-Grid System If the system does not connect to the genset, it is possible that the voltage or frequency is outside the ranges accepted by UNE ZHERO.
  • Page 104 - APPENDICES 12.1. System Status Tables SUMMARY - STATUSCYCLE - Agen BLOCKING ALARM NAME POSSIBLE CAUSE POSSIBLE SOLUTION ALARM There is no photovoltaic production and the if it does not reset within ten minutes, reset using the "ALL" button, if this ALL_UNDERV_DC battery is off does not work, contact: assistenza@unesrl.com...
  • Page 105 SUMMARY - STATUSCYCLE - Adevice BLOCKING ALARM NAME POSSIBLE CAUSE POSSIBLE SOLUTION ALARM Too many battery reset occurred in a short Reset the alarm using the "ALL" button. If the problem turns out to be ALL_B0_FERMA time. If the problem persists, there may be a frequent, contact: assistenza@unesrl.com.
  • Page 106 SUMMARY - INV0 - alarms BLOCKING ALARM NAME POSSIBLE CAUSE POSSIBLE SOLUTION ALARM Relay stuck or distributor mains voltage too RELE Contact: assistenza@unesrl.com high Check that your backup line does not have loads with spikes greater than PH_OVC Excessive inrush current 50A, intervene to reduce the starting point of the devices connected to the ZHERO backup line.
  • Page 107: Product Data Sheet

    12.2. Product data sheet PAG. 107 of 111...
  • Page 108 PAG. 108 of 111...
  • Page 109 PAG. 109 of 111...
  • Page 110 12.3. Annexes • Battery Manual; • Maintenance certificate; • Datasheet. PAG. 110 of 111...
  • Page 111 PAG. 111 of 111...

Table of Contents