Table of Contents: Parts List ... 3 Assembly Assembling Frame and Enclosure ... 4-6 Attaching Impact Screen ... 7 Optional Side Netting ... 8 Projector Setup Setting Up Bracket ... 9-12 Pole Mount ... 13 Ceiling Mount ...14 Display Settings ... 15-19 Warranty ...
Parts List: Enclosure Impact Screen Side Netting Projector Projector HDMI Cable Bracket and Mount Hitting Mat Putting Turf Ball Tray Frame Launch Monitor (model will vary)
Assembling Frame and Enclosure: Using the numbered corners, begin partially assembling the frame to match the layout shown below Attach the enclosure to the ceiling of the frame using the hook and loop (please note hook and loop is often confused for the brand that is Velcro). Orient the enclosure such that the singular white wall creates the back wall.
Page 5
Assembling Frame and Enclosure: Attach the (4) C Poles to the upper structure. Build the bottom base of the frame and connect it to #4 feet and #5 connctors. Join the upper and lower frame structures...
Page 6
Assembling Frame and Enclosure: Wrap and secure the remaining perimeter edges to the frame using the hook and loop attachments Please note - On the rear exterior at the bottom you may find this particular position will never meet. Rest assured this area will not jeopardize the integrity of the enclosure - provided the majority of the strip is joined.
Attaching Impact Screen: The top of the impact screen is highlighted with a green tab. With two people, have one person push the outer sidewall inward while the other attaches the impact screen to the left vertical wall. Start with the left or right side, pull the screen tight as you secure it across the top, then complete the other side.
Optional Side Netting: There is a right and left side to the net, so start by identifying the correct side. The corner with the tag is the anchor point. Please note that an anchor is not provided, but you can use any object —...
Projector Setup: Setting Up Bracket (Ceiling Mount) The extension arm is optional. The gimbal can be attached directly to the ceiling bracket if height is limited. Projector Setup: Projector Placement The projector will need to be positioned about 9.5 feet back or further from the screen when using a computer, or 10.5 feet back when using a tablet—this is farther than the projector pole allows.
Page 15
Projector Setup: Power and Input Source & Mirroring/Extending Display Power and Input Source To fully access projector settings, the projector must be connected to both a power and display source. There’s an included HDMI cable but an HDMI adapter may be required for Apple products and will need to be purchased separately.
Projector Setup: Display Settings Click Display > Projection Orientation Select orientation where the projector is on Be sure to enter yes to apply the projection the ceiling and in front of the impact screen...
Page 17
Projector Setup: Display Settings Screen Type and Aspect Ratio Display > Screen Type > and choose a size 4:3 is recommended for both Screen Type and Aspect Ratio if using 4:3 for PC, however iPad and other tablets are likely better with 16:9 Similar to the projector not having to be in one exact position, there are different combinations of settings that can be used to adjust the size of the screen.
Page 18
Projector Setup: Display Settings Keystone VIDEO Keystone is adjustment of the trapezoid effect when the projector is off axis (tilted up or down) to create a square image. There is a separate Vertical and Horizontal adjustment within the Geometric Correction menu Display >...
Page 19
Projector Setup: Display Settings Four Corners VIDEO Display > Geometric Correction > Four Corners Hit Enter to select corner. The image will turn white and highlight which is corner is selected. Use the remote arrows to adjust the corners direction as needed. Deselect a corner by hitting Enter and repeat for each corner.
Need help?