Advertisement

Quick Links

Black Marble 5
User Manual
Version: 1.7
Update Date: 2023-02-10

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Black Marble 5 and is the answer not in the manual?

Questions and answers

Summary of Contents for ROE Black Marble 5

  • Page 1 Black Marble 5 User Manual Version: 1.7 Update Date: 2023-02-10...
  • Page 2: Copyright

    ROE. Warranty Policy The standard warranty period for the Products is 2 years after shipment from ROE Visual for rental applications and 3 years for fixed install applications. The contract will specify the application. This warranty includes all accessories, spare parts, and components shipped at the time of the original purchase.
  • Page 3: Contact Information

    (12) Software or accessory malfunction. (13) Any other cause not related to a defect in materials or workmanship. Contact Information If you have any questions about this document, please feel free to contact with ROE technical service team. ROE CHINA...
  • Page 4: Table Of Contents

    Do’s and Don’ts ............................. 12 Components .......................... 13 Overview ................................13 Module ................................14 Power Box................................ 14 Accessories ..........................15 Sub Framing System ........................... 15 Cables ................................16 V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 4 / 32...
  • Page 5 Control System ........................27 Service Manual ........................28 11.1 Cleaning Tiles ..............................28 11.1.1 Needed Tools ............................28 11.2 Swapping Modules ............................29 Revision History ........................ 32 V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 5 / 32...
  • Page 6: Safety

    All components should be kept dry, clean, lubricated (only of recommended), coated properly, and otherwise maintained in a manner consistent with the part design. ROE products must be used in a manner consistent with their design and inspected on a routine basis for security, wear, deformation, corrosion, and any other circumstances that may affect the loading capacity.
  • Page 7: Safety Instructions

    (11) The waterproof rating of the Product is IP65, so need to pay attention to drainage in rainy days. The water surface should not exceed the bottom of the power box, otherwise, the product will be damaged. Pay attention to ponding V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 7 / 32...
  • Page 8: Consignes De Sécurité

    Les produits ROE doivent être utilisés conformément à leur conception et inspectés régulièrement pour vérifier leur sécurité, leur usure, leur déformation, leur corrosion et toute autre circonstance pouvant affecter leur capacité...
  • Page 9: Consignes De Sécurité

    électrique, sinon le produit sera endommagé. Attention à l'eau stagnante V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 9 / 32...
  • Page 10: General Introduction

    2.1.3 Magnet-assisted Assembly Magnets are integrated into the module, enabling a quick module swapping on-site. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 10 / 32...
  • Page 11: Specifications

    -40 ° C to 60 ° C / -40 ° F to 140 ° F Operating / Storage Humidity 10 – 90% RH Certification CE, ETL, FCC CE, ETL Max BTU AVG BTU 3D Ready V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 11 / 32...
  • Page 12: Installation Requirements

    3.1.1 Weight Do not underestimate the weight of tiles and frames. Please make sure the floor or truss on which ROE tiles and frames will be installed is capable of handling the complete weight of tiles and frames. 3.1.2 Levelling The surface on which tiles and frames will be installed must be levelled.
  • Page 13: Components

    Figure 4-1. BM5 Components Test button M10 threaded hole Data Port Stacking Hole Data Port Power In Power Out Figure 4-2. BM5 Parts Information V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 13 / 32...
  • Page 14: Module

    A BM5 tile consists of 4 pcs modules. Dimensions: 300 x 300 mm Figure 4-3. Module Dimensions Power Box Dimensions: 443 x 170 x 54 mm Figure 4-4. Power Box Dimensions V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 14 / 32...
  • Page 15: Accessories

    Dimensions: 1228.8 x 619.2 x 90mm Base frame for BM5, 1x1, V2.0 SAP: 315001-00019 Weight: / kg Dimensions: 619.2x619.2x90mm Floor Laser Leveler SAP: 219001S0001 V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 15 / 32...
  • Page 16: Cables

    Weight: 160±5 g Neutrik_Neutrik Connectors Connect neighboring tiles (vertical). Data cable, 30m, etherCON-etherCON, V2.0 SAP: 208004S0675 Weight: 7±3% kg Neutrik_Neutrik Connectors Connect the processor and tiles. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 16 / 32...
  • Page 17: Power Cable

    “click”. Pull back the button on the plug, turn the power cable anti-clockwise and plug it out. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 17 / 32...
  • Page 18: Data Cable

    Data Cable Plug in the data cable and you feel a “click”. Press the button on the socket and plug the data cable out. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 18 / 32...
  • Page 19: Package

    SAP: 309003-01136 Dimensions: 1500 x 760 x 880 mm Capacity: One flight case can load 8 pcs tiles. 1500 1474 Figure 6-1. BM Flight Case V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 19 / 32...
  • Page 20: Dolly For Sub Frames

    1) BM Dolly supports both horizontal and vertical placement; 2) No need side plates, frames are tied by two side belts; 3) The empty dolly is stackable; V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 20 / 32...
  • Page 21: Installation Overview

    BM5 User Manual www.roevisual.com Installation Overview Figure 7-1. System Overview V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 21 / 32...
  • Page 22: Quick-Start Guide

    (it can be rotated by an electric screw driver) A Floor Leveler can be used, see the attached separate user manual for more information. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 22 / 32...
  • Page 23 Faster Dowel Pin (5) Build the floor while cabling and finish the whole floor screen. 4. Finish. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 23 / 32...
  • Page 24 Note:Please make sure all the tiles have a same direction after they are placed on the sub frames.The tile direction can be seen at the side of the cabinet. User Manual V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 24 / 32...
  • Page 25: Cabling

    If the voltage is 110V, one power cable can load 5 pcs BM5 tiles. NOTES: 1. Power Cable_10m_Neutrik-Neutrik/Weipu-Neutrik 2. Power Cable_1m_Neutrik-Neutrik 3. Power Cable_4m_Neutrik-Neutrik V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 25 / 32...
  • Page 26: Data Cabling

    1 0 0 ~ 2 4 0 V A C Back View Port 3 Port 2 Port 1 Front View NOTES: 4. Main Data Cable_30m_Neutrik_Neutrik 5. Data Cable_0.93m_Neutrik_Neutrik 6. Data Cable_2m_Neutrik_Neutrik V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 26 / 32...
  • Page 27: Control System

    BM5 User Manual www.roevisual.com 10 Control System ROE provides three different control systems: Megapixel VR Helios, Brompton Tessera and ROE Evision. For more information about system operation, please check the corresponding control system user manual. 1. ROE Evision Control System User Manual 2.
  • Page 28: Service Manual

    Use lukewarm water with mild detergent or any glass cleaning product. ⚫ A mop can be used for a quick cleaning. ⚫ Remove stubborn stains: V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 28 / 32...
  • Page 29: Regular Cleaning

    Eraser can be used to clean some marks. ⚫ Caution: The surface of mat floor has texture, be very careful when cleaning. 11.2 Swapping Modules Tools needed: Suction Cup, Anti-static gloves V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 29 / 32...
  • Page 30 4) Place the module at a safe place and release the module by pressing the button. Tips: 1) The handle must be perpendicular to the tile direction; 2) Don’t put the cups at the places of module connectors. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 30 / 32...
  • Page 31 The seat for installing the magnets back are left on the modules. If the glass masks are changed to smaller matte masks, the four magnets need to be reinstalled. V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 31 / 32...
  • Page 32: Revision History

    Update specification and SAP number Lance 2021.09.24 Update control system Zary Update description of waterproof, SAP number and 2022.11.02 Bruce control system 2023.02.10 Update Specification Bruce V1.7, 2023-02-10 | Copyright © 2023 ROE Visual Co., Ltd. All Rights Reserved. 32 / 32...