Page 1
Monitor Service Manual Model: BE279QSK Version no.: 0 Release date: 2024/11/22...
Page 2
ASUS will only be responsible for or indemnify you for loss, damages or claims based in contract, tort or infringement under this Warranty Statement. This limit also applies to ASUS’ suppliers and its reseller. It is the maximum for which ASUS, its suppliers, and your reseller are collectively responsible.
1. Safety Precautions FOR PRODUCTS CONTAINING LASER: DANGER- Invisible laser radiation when open. AVOID DIRECT EXPOSURE TO BEAM. CAUTION- Use of controls or adjustments or performance of procedures other than those specified herein may result in hazardous radiation exposure. CAUTION- The use of optical instruments with this product will increase eye hazard. TO ENSURE THE CONTINUED RELIABILITY OF THIS PRODUCT, USE ONLY ORIGINAL MANUFACTURER'S REPLACEMENT PARTS, WHICH ARE LISTED WITH THEIR PART NUMBERS IN THE PARTS LIST SECTION OF THIS SERVICE MANUAL...
ASSY SHIELDING #SCRW MACH STEEL HEX #4-40 NI SCRW TAP CAP M3*6L B-ZN MAIN BOARD 10 WEB CAM MODULE POWER BOARD 11 REAR CASE SPEAKER 12 SCRW FPHM4*10L(7.7/1.6)B-ZN NY MYLAR POWER BE279QSK 13 ASSY STAND #SCRW PH INT/TOO M3*9TP-S C-ZN...
3. Disassembly and Assembly Procedures Disassembly SOP Preparation before disassemble 1. Clean the room for disassemble 2. Identify the area for monitor 3. Check the position that the monitors be placed and the quantity of the monitor; prepare the area for material flow; according to the actual condition plan the disassemble layout 4.
Page 7
5. Unlock 2 screws and disassemble camera from Rear Case. Screw: (SCRW TAP CAP M3*6L B- Torque : 4.5±0.5 Kg-cm 1. Unlock 2 screws and Torque : disassemble camera 4.5±0.5 Kg-cm cover. Screw: (SCREW M3*4 B) 2. Unlock 2 screws and Torque : disassemble camera 4.0±0.5...
Page 8
1. Disinsert Key Board cable from Shielding and unlock 9 Middle Torque : Frame screws. 7.0±0.5 Kg-cm Screw: (#SCRW MACH FLATM3*0.5P*4.5L ZN) 2. Disassemble Camera cable and Speaker cable from Main Board. Screw driver 3. Pull out LVDS cable from panel. 4.
Page 9
6. Disassemble Mylar from Shielding. Main Board 7. Unlock 2 screws Bottom of Main Board to disassemble Main Board Screw:#SCRW MACH Torque : STEEL HEX #4-40 NI 5.0±0.6 Kg-cm 8. Unlock 5 PCBA screws and disassemble Main Power Board and Power Main Board Board Board.
3.2 Assembly SOP Preparation before assemble 1. Clean the room for work 2. Identify the area for material 3. Prepare the implement, equipment and materials as bellow: 1) Working table 2) Screw-driver 3) Glove 4) Cleaning cloth 5) ESD protection After unplugging the power cord, the power board still have power energe.
Page 11
4. Lock 2 screws. Screw:#SCRW MACH Torque : STEEL HEX #4-40 NI 5.0±0.6 Kg-cm 5. Assemble Mylar to Shielding. Main Board 1. Insert camera cable into Camera Board. 2. Assemble Camera Board to camera Shielding. Screw Driver 3. Stick 1 tape to fix camera cable.
Page 12
4. Assemble camera Shielding to front camera cover and lock 2 screws Torque : Screw: SCRW TAP FPH 4.5±0.5 M2.5*4.5L B-NI Kg-cm 5. Assemble camera cover 6. Lock 2 screws. Screw: Torque : (SCREW M3*4 B) 4.5±0.5 Kg-cm 7. Assemble camera to Rear Case and lock 2 screws.
Page 13
1. Assemble Key Board to Middle Frame then lock Torque : 3 screws to fix Key 2.0±0.5 Board. Kg-cm Screw:#SCRW TP-B FPH M2*2.4L B-ZN 2. Assemble Middle Frame to monitor. 3. Insert the LVDS FFC wire to panel. Screw Driver 4.
Page 14
1. Assemble Speaker to Shielding. 2. Insert camera cable to Main Board. 3. Stick 2 tapes to fix Screw camera cable. drive 4. Assemble Rear Case to monitor and lock 4 screws. Torque : Screw:#SCRW 8~10 Kg-cm FPHM4*10L(7.7/1.6)B- ZNNY...
Page 15
1. Assemble Stand to Rear Case. 2. Finish...