CP 85 / CP 120 Cleaning Unit INTRODUCTION CLEANING UNIT MODELS PRE-INSTALLATION INSTRUCTIONS This guide covers the following cleaning unit The instructions in this Pre-Installation Guide allow types: Cleaning Unit for Chemistry-free Plates. the customer and the Service Technician to prepare the installation of the cleaning unit.
Cleaning Unit CP 85 / CP 120 1. TRANSPORTATION WHEN THE CLEANING UNIT ARRIVES STORING THE CLEANING UNIT BEFORE INSTALLATION CHECKING FOR DAMAGE The crated cleaning unit will usually be delivered Check if the crate is damaged at the time of some time before the arrival of the Service delivery.
CP 85 / CP 120 Cleaning Unit HANDLING THE CRATE The icons on the crate indicate how to handle the crate during transport and storage: Ensure that the side indicated by the arrows is always up. Handle the crate with care.
Cleaning Unit CP 85 / CP 120 TRANSPORTING THE CLEANING UNIT AVAILABLE LIFTING THE CRATE WIDTH FOR TRANSPORT To lift the crate, at least a fork-lift truck or two Depending of the width of the door(s) through which persons and a hand powered pallet mover are the cleaning unit has to be transported to the required.
Cleaning Unit CP 85 / CP 120 2. INSTALLATION REQUIREMENTS GENERAL REQUIREMENTS ENVIRONMENTAL REQUIREMENTS CLEANING FACILITIES Provide a heating and ventilating system capable of It is essential to have easy access to a sink and a maintaining room temperature between 15 and 25°C water tap with hot water where rollers, guides, and (59 and 77°F) and relative humidity on max.
CP 85 / CP 120 Cleaning Unit SPACE REQUIREMENTS FREE SPACE AROUND THE MACHINE Decide where the cleaning unit shall be placed and make sure that the free space around the machine makes servicing possible. The recommended minimum free space around the...
Cleaning Unit CP 85 / CP 120 CLEANING UNIT DIMENSIONS SIDE VIEW 220.6 cm (86.9”) 110.7 cm 69.9 cm 40.0 cm (43.6”) (27.5”) (15.7”) 89.3 - 93.3 cm 90.0 - 94.0 cm (35.2 - 36.7”) (35.4 - 37.0”) 85: 138.5 cm 54.5”...
CP 85 / CP 120 Cleaning Unit SUPPLY AND DRAINS SUPPLIES WARNING! Electrical installation must conform The cable for the main power connection is not to local regulations and guidelines. delivered with the cleaning unit. MAIN POWER CONNECTION DRAINS The main power connection must be made in the cleaning unit's plug located at the back of the right •...
Cleaning Unit CP 85 / CP 120 MAIN POWER OUTLET Provide a main power outlet close to the installation site. The table below indicates the applicable power supply types and to which cleaning unit models they apply. The table also shows recommended power...
Cleaning Unit CP 85 / CP 120 3. PRE-INSTALLATION CHECKLIST Please ask the customer to answer the following questions in order to ensure a trouble-free installation of the cleaning unit: 1. Delivery of the crate and transport to the installation site A.
Page 18
CP 85 / CP 120 Cleaning Unit 3. Water supply and drain A. Capacity of air condition/ventilation adequate with regard to BTU max. 10600? B. Is there a large sink (with hot water) for cleaning the equipment? C. Will the cleaning unit be connected to a local waste treatment system? D.