Dear Customer, Thank you very much for buying this appliance. Please read through the manual carefully before using the product, and keep it in a safe place for later reference. In order to ensure continued safe and efficient operation we recommend that the product is serviced regularly.
1 About this manual About this manual General This manual is intended for the installer. Important Some illustrations in this manual show parts that may not be available in your market. Additional documentation The following documentation is available in addition to this manual: Installation manual Symbols used in the manual This manual contains special instructions, marked with specific symbols.
The cascade systems are designed and supplied for specific use with BAXI boilers. Cascade systems link multiple boilers together to provide a desired total heating output. The BAXI cascade system is modular and designed for expansion. A low loss header or plate heat exchanger balances the flow volumes between the cascade and the rest of the heating system.
2 Description of the product Main components Fig.2 Main components of a cascade system AD-3002461-01 Tab.2 Main components Item Description Function Appliance The wall-hung boiler used in cascade. Hydraulic separator A hydraulic separator between the boiler side and system side of an installation maintains a correct water flow and a constant flow temperature.
Wall brackets for 4 boilers See also Choosing a heat exchanger type, page 16 Accessories The available accessories may vary per country or per selected cascade configuration. Contact a BAXI supplier for available flue gas pipe accessories. Tab.4 Accessories Accessory Description Available versions Bend sets Used for positioning the low loss head...
3 Technical specifications Accessory Description Available versions Insulation sets Used to reduce heat loss. Collector pipe assembly insulation Low loss header insulation Elbow set insulation Levelling feet Used to level the collector pipes frame(s) Levelling feet with washers and nuts. when installed on uneven ground.
Page 9
3 Technical specifications Description 2 boilers 3 boilers 4 boilers 5 boilers 6 boilers 7 boilers 8 boilers Gas connection DN50 DN50 DN50 DN50 DN50 DN50 DN50 PN16 PN16 PN16 PN16 PN16 PN16 PN16 Free space required for ex pansion vessel (1) When fitting a blanking flange with an expansion vessel connection, make sure there is enough space for fitting the vessel.
Page 10
3 Technical specifications Fig.4 In-line frame mounted configuration AD-3003380-01 Tab.7 Dimensions in mm with DN65 collector pipes Description 2 boilers 3 boilers 4 boilers 5 boilers 6 boilers 7 boilers 8 boilers Total width 1110 1640 2170 2700 3230 3760 4290 Free space required for mounting the blanking flang...
Page 11
3 Technical specifications Description 2 boilers 3 boilers 4 boilers 5 boilers 6 boilers 7 boilers 8 boilers Total depth For a cascade with Quinta Ace S ≤ 70 kW boiler models Total depth For a cascade with Quinta Ace S ≥ 90 kW boiler models Flow connection DN100 DN100...
1000 1000 1000 mended) Total depth 1170 1170 1170 For a cascade with Quinta Ace S - ≤ 70 kW boiler models Total height 1312 1312 1312 For a cascade with Quinta Ace S ≥ 90 kW boiler models Flow connection...
Page 13
3 Technical specifications Fig.7 Low loss header dimensions - DN65 <350 kW - DN100 AD-3003067-01 Fig.8 Low loss header dimensions Tab.12 Low loss header dimensions Description DN65 DN100 flange size flow, system side DN65 PN6 DN100 PN6 flange size return, system side DN65 PN6 DN100 PN6 body depth...
4 Before installation Fig.11 Sample string 1 EN 14471 or EN 1856–1: The material is UKCA and CE approved according to this standard. For plastic this is EN 14471, For aluminium and stainless steel this is EN 1856-1. 2 T120: The material has temperature class T120. A higher number EN 14471 - T120 P1 W 1 O50 LI E U0 is also allowed, but not lower.
The system heat output in kW at 80/60 °C (P). The available vertical flue gas pipe height (H). AD-3003416-01 Tab.24 Flue gas outlet dimensions for Quinta Ace S (35 – 115 kW) boiler combinations. Number of boil 35 - 60 -...
4 Before installation Newly installed aluminium flue gas pipes with longer lengths can produce relatively larger quantities of corrosion products. Also casting sand and processing metal chips from new boilers can fill the boiler trap on short term after installation. Check and clean the trap more often for these reasons.