OZPCS-RS40 Installation and Commissioning Checklist
Unit Model Number
____________________________
Unit Serial Number
____________________________
Installation Date
____________________________
This checklist is intended as a quick reference guide to assist installation and commissioning of OZPCS-RS40 power conversion systems. It
is not a substitute for thorough user's manual review and system-level engineering. If in doubt at any step, consult the user's manual. If the
user's manual does not fully address your concern, please contact Oztek Corp Applications Engineering at
603. 546. 0090 for assistance.
PCS INSTALLATION
(individual unit)
Step
Name
1 Installation
Environment
2 DC and AC Voltages
3 Unpacking
4 PCS Installation
DR-0158 OZPCS-RS40 Installation and Commissioning Checklist
Rev. A
Description
Ensure installation site meets environmental
and physical constraints specified in user's
manual.
Verify that battery voltage range and nominal
AC grid voltage are within PCS operating voltage
range specified in user's manual.
Verify that packaging is not damaged and verify
the PCS's condition after unpacking.
Install the PCS into the equipment rack. Be sure
to only use Oztek supplied/authorized fasteners
for securing mounting ears or brackets to the
PCS. Verify adequate unit support for the
application (rack shelf and/or rear mounting
brackets) and ensure mounting bolts are
properly tightened.
TechSupport@oztekcorp.com
Notes
OztekCorp.com
or

Advertisement

loading
Need help?

Need help?

Do you have a question about the OZPCS-RS40 and is the answer not in the manual?

Questions and answers

Summary of Contents for OZTEK OZPCS-RS40

  • Page 1 ____________________________ This checklist is intended as a quick reference guide to assist installation and commissioning of OZPCS-RS40 power conversion systems. It is not a substitute for thorough user’s manual review and system-level engineering. If in doubt at any step, consult the user’s manual. If the user’s manual does not fully address your concern, please contact Oztek Corp Applications Engineering at...
  • Page 2: Over Current Protection

    Record unit model and serial numbers, and installation date in space provided above. ☐ 11 Photograph Installation Take photographs of unit installation, being sure to capture mounting and cabling details. OztekCorp.com DR-0158 OZPCS-RS40 Installation and Commissioning Checklist Rev. A Page 2 of 7...
  • Page 3 Verify no unexpected warnings are displayed. ☐ 9 Full Discharge Power Command rated system discharge power. Verify that the reported power matches the expected value. Verify no unexpected warnings are displayed. OztekCorp.com DR-0158 OZPCS-RS40 Installation and Commissioning Checklist Rev. A Page 3 of 7...
  • Page 4 Enable AC and DC power to unit. ☐ 14 Verify Operation Under Verify communication and operation through EMS Control system-level energy management system (EMS) using documentation provided by EMS supplier. OztekCorp.com DR-0158 OZPCS-RS40 Installation and Commissioning Checklist Rev. A Page 4 of 7...
  • Page 5 ☐ 4 Connect Connect laptop running Oztek Power Studio using Commissioning Laptop a temporary commissioning test cable per PCS and Power Studio user’s manuals. Note, the...
  • Page 6: Verify Communication

    Enable AC and DC power to unit. ☐ 16 Verify Operation Under Verify communication and operation through EMS Control system-level energy management system (EMS) using documentation provided by EMS supplier. OztekCorp.com DR-0158 OZPCS-RS40 Installation and Commissioning Checklist Rev. A Page 6 of 7...
  • Page 7 1. Full charge/discharge operation is readily accommodated in most grid-connected applications. For grid-forming systems, test loads and secondary power sources are needed to fully exercise the system. When possible, Oztek recommends first commissioning the system grid-connected and then verifying grid-forming operation.