ACC2 IoT gateway • Installation About this manual This manual describes the IoT gateway ACC2. This user manual is part of the product. • You may only use the product if you have read and understood the user manual fully.
DESCRIPTION Critical warning, risk of personal injury Warning risk of damage to equipment or person Attention is required Note ! Regulations regarding ACC2 SYMBOL DESCRIPTION Note ! Read instructions before installation Installation may only be carried out by a qualified installer...
IoT gateway • Installation Product description ACC2 is an IoT gateway that consists of an electronic device that you can plug in 4 digital (0/1) and 2 analog sensors that communicate via the 4G network to AfrisoCloud, which is a cloud service solution for the presentation of measurement values on internet connected devices.
ACC2 Installation • IoT gateway Assembly Assembly of electronics unit Note ! Read instructions for installation Installation may only be carried out by a qualified installer • Mount the electronics unit on a even wall at eye level. • Check that the electronics unit is easily accessible and easy to monitor.
ACC2 Installation • IoT gateway Installation of sensors Cables should be installed mechanically protected Sensors are mounted according to the description in their manual. Record as many measurements as possible to facilitate continued set-up in the cloud service portal. See 7.1.
ACC2 IoT gateway • Installation 5.3.3 Separator alarm OSA3 OSA3 - Relay input R1 = programmable function (sensor-specific or total alarm) Common (C) is connected to terminal J6/1 (DIG_IO-1) and NC is connected to terminal J4/3 (GND) In the event of an alarm, the relay switches and in the Sitevisual portal the value changes from 1 to 0.
ACC2 Installation • IoT gateway Commissioning Note ! Make sure that the electronics unit and sensor are installed according to instructions in previous points. Handling at startup 1 = Status LED 2 = Status LED for mobile connection Checks at start-up of electronics unit Check that all connections and assembly are correctly performed before voltage connection.
ACC2 IoT gateway • Installation Operation After commissioning and if no status LEDs are red, the ACC2 is ready for use. Cloud service portal When everything is installed according to instructions, Afriso needs to be contacted to complete the set-up. Prepare the following information:...
ACC2 Installation • IoT gateway Maintenance ACC2 does not need any actual maintenance. Check that the enclosure and wiring are complete and clean. Open the lid and check that the LEDs are green. Maintenance of sensors For sensor maintenance, consult the sensor’s own manual.
Page 12
ETSI EN 301 908-1 v.13.1.1 (2019-11) (Parts of) ETSI EN 301 908-13 v.13.2.1 (2022-02) (Parts of) ETSI EN 303 413 v.1.2.1 (2021-04) (Parts of) Signed for and on behalf of Afriso Ema AB Date of issue: 2024-01-30 Signature of authorized person:...
Need help?
Do you have a question about the ACC2 and is the answer not in the manual?
Questions and answers