Table of contents Technical data ..................... 4 Safety requirement ..................5 Installation ......................6 Description of connection ................7 Installation Examples ..................8 Commissioning ....................9 Inspection & maintenance ................10 We reserve the right to change designs and technical specifications of our products.
1. Technical data Flextherm PS-H: Steel vessels to reduce the on/of cycling of the heat pump as buffer vessel or to protect Flexcon expansion vessels on elevated temperature systems. Flextherm PS-H+: Buffer vessels for use in smaller closed heating installations. If a heat pump produces more heat than the heat requirement at a certain time, it’s recommended to buffer this excess heat and meanwhile reducing the on/off cycling of the heat pump to increase the product life time.
Flextherm PS-H 2. Safety requirement Read these instructions carefully before commencing installation. For any additional questions, please consult our customer service department (see contact details). WARNING: Do not expose the insulation to open fire! > Safety requirement...
3. Installation Installation, commissioning and maintenance must be carried out by specialists according to the applicable regulations (including EN 12828 and VDI 2035, the relevant regulations for local distributors, national legislation and other regulations). Suitable measures must be taken to protect the vessels from damage caused by under pressure.
Flextherm PS-H 4. Description of connection Flextherm PS-H Ø A [mm] [mm] [mm] [mm] 24 L G¾"M ….. > Description of connection...
Page 8
Flextherm PS-H+ Size Ø A [mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm] 50 L 100 L Size ["] ["] 50 L G½"F G1"F 100 L G½"F G1"F We reserve the right to change designs and technical specifications of our products.
6. Commissioning The entire system must be thoroughly flushed before commissioning. The system may only be set up in frost-free rooms and a surface that is sufficiently able to bear the load of the completely filled tank. Any unused connections must be professionally sealed. We reserve the right to change designs and technical specifications of our products.
Flextherm PS-H 7. Inspection & maintenance No liability shall be accepted for damage that is caused by failure to follow the installation and operating instructions. The vessel must be installed to allow easy access for maintenance, operation, repairs or replacement. Site preparation and suitability for installation of the vessel are not the responsibility of the manufacturer or the responsible distributor.
Page 12
We supply products for the installation industry in more than 70 countries. This is done from Flamco sales offices and via distributors who know the local market, and can give you the right advice at all times. Aalberts hydronic flow control The Netherlands Fort Blauwkapel 1 1358 DB...
Need help?
Do you have a question about the Flamco Flextherm PS-H and is the answer not in the manual?
Questions and answers