Wall hung rsf gas-fired condensing combination boiler for sealed central heating systems and mains fed domestic hot water, natural/liquid petroleum gas (60 pages)
Wall hung rsf gas fired condensing system boiler (60 pages)
Summary of Contents for Bosch WORCESTER GREENSTAR CDi
Page 1
INSTRUCTION MANUAL INSTALLATION, COMMISSIONING & SERVICING WALL HUNG RSF GAS-FIRED CONDENSING COMBINATION BOILER GREENSTAR CDi FOR SEALED CENTRAL HEATING SYSTEMS AND MAINS FED DOMESTIC HOT WATER THE APPLIANCE IS FOR USE WITH NATURAL GAS OR L.P.G. (Cat II 2H3P TYPE C13, C33 & C53) NATURAL GAS: 27CDi GC NUMBER 47-406-12 30CDi GC NUMBER 47-406-14...
THIS APPLIANCE MUST BE INSTALLED BY A CORGI REGISTERED, COMPETENT PERSON. FAILURE TO INSTALL CORRECTLY COULD LEAD TO PROSECUTION. IF YOU ARE IN ANY DOUBT CONTACT WORCESTER, BOSCH GROUP TECHNICAL WATER TREATMENT: HELPLINE. DISTANCE LEARNING AND TRAINING COURSES ARE AVAILABLE FROM WORCESTER FERNOX 01799 550811 BOSCH.
SETTING THE AIR/GAS RATIO SHORT PARTS LIST CONVERSION KITS L.P.G. CONVERSION FAULT FINDING & DIAGNOSIS FAULT FINDING CENTRAL HEATING FUNCTION PREHEAT AND DHW FUNCTION PROTECTION FUNCTION INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi CONTENTS 6 720 614 564b (2008/02)
WRAS. IMPORTANT: ARTIFICIALLY SOFTENED WATER MUST NOT BE USED TO FILL THE CENTRAL HEATING SYSTEM INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi SAFETY PRECAUTIONS 6 720 614 564b (2008/02) & INSTALLATION REGULATIONS...
24 AIR / GAS ADJUSTMENT SCREW 25 TESTING POINT FOR FAN PRESSURE 26 FAN 27 PRIMARY SENSOR 28 EXPANSION VESSEL 29 REMOVABLE TOP CASE PANEL FOR SERVICING INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi LAYOUT & COMPONENTS 6 720 614 564b (2008/02)
Page 8
58 SYSTEM PRESSURE GAUGE 59 POSITION FOR OPTIONAL TEXT DISPLAY WITH INTELLIGENT FUNC- TIONALITY OR TIMER 60 DISPLAY 6 720 614 562-02.1O INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi LAYOUT & COMPONENTS 6 720 614 564b (2008/02)
• Drain and thoroughly flush the system to remove the flushing agent and debris. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi CLEANING PRIMARY SYSTEMS 6 720 614 564b (2008/02)
In such circumstances, the advice of the local water authority should be sought. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi MAINS SUPPLIES 6 720 614 564b (2008/02)
6 720 611 927 - 02.1O • Do not use galvanised pipes or radiators. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi WATER SYSTEMS & PIPEWORK 6 720 614 564b (2008/02)
M & F bend and the drainpipe, outside the property, to avoid flooding during adverse weather conditions. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi CONDENSATE PIPEWORK 6 720 614 564b (2008/02)
Electrical switches, fused spur and socket outlets must not be situated in the 600mm radius bathroom. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi BOILER LOCATION & CLEARANCES 6 720 614 564b (2008/02)
CH flow 22 mm DHW Out 15 mm Mains Gas Supply 22 mm CH return 22 mm Mains Water In 15 mm INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi PLUMBING MANIFOLD 6 720 614 564b (2008/02)
52mm fall 104mm fall or at least 52mm for each metre away from the boiler to ensure condensate flows back into the boiler. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi FLUE TERMINAL POSITIONS 6 720 614 564b (2008/02)
Page 17
2 metres from the ground or if a person could come into contact with the flue terminal. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi FLUE OPTIONS 27CDi 6 720 614 564b (2008/02)
Before installing appliance ensure system 6 720 614 039-04.1O has been cleaned as explained on page 9. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi UNPACKING WALL FRAME AND 6 720 614 564b (2008/02) ANCILLARY ITEMS...
Clear away any debris. FIXING THE PRE-PLUMBING MANIFOLD: Mount the pre-plumbing manifold on the 2 lower screws and secure the screws. Pre-plumbing manifold INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi WALL MOUNTING PLATE 6 720 614 564b (2008/02) FLUE OPENING...
10. Remove the outer case. 11. Remove the protective packaging (G) from the electrode assembly. Do not use the frame as handle INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi UNPACKING THE APPLIANCE 6 720 614 564b (2008/02)
Ø60mm PLUME MANAGEMENT KIT (7-716-191-086) replaces the plume deflector in the Ø60/100mm telescopic flue terminal. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi FLUE INSTALLATION 6 720 614 564b (2008/02)
Page 25
NOTE: The aluminium tape is not required when reducing the terminal. 130mm INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi FLUE INSTALLATION 6 720 614 564b (2008/02)
This is to allow condensate to run back into the boiler for safe disposal. Do not attempt to force the terminal outlet beyond the limit stops. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi FLUE INSTALLATION 6 720 614 564b (2008/02)
It must fall at least 50 mm per metre towards the outlet. • An adaptor (A) in 22 mm pipe is contained in the fitting pack. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi CONDENSATE CONNECTION 6 720 614 564b (2008/02)
9. Refit control panel cover: Refit panel and secure with screws (B). Bring the control panel to its upper position and fix it with screw (A). INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi ELECTRICAL 6 720 614 564b (2008/02)
Open gas cock on the boiler and purge the gas supply to the boiler ensuring that the room is well ventilated. Test gas supply for soundness as described in BS 6891. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi FILLING THE SYSTEM 6 720 614 564b (2008/02)
To reset press and hold the reset button (E) for 2 seconds. The boiler will be reset. CAUTION: DO NOT PRESS POWER INDICATOR (B) TO RESET BOILER. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi STARTING THE APPLIANCE 6 720 614 564b (2008/02)
* compatible with aluminium. The pH value of the system water must be less than 8 or the appliance guarantee will be invalidated. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi WATER TREATMENT 6 720 614 564b (2008/02)
Inlet Test Nipple When the ECO button is illuminated the M - Holiday button boiler will be in Economy mode with pre-heat no longer active. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi COMMISSIONING 6 720 614 564b (2008/02)
If the appliance is unused and exposed to freezing conditions; shut off all the mains supplies and drain the system and boiler. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi FINISHING COMMISSIONING 6 720 614 564b (2008/02)
Call up the last fault stored by the Bosch Heatronic, Service Function .0. Refer to Fault Finding for rectification procedures. 6720611927-07.1O INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
30CDi - 4.1 mbar 37CDi - 3.9 mbar 42CDi - 4.8 mbar Pressures measured below these figures will indicate that the heat exchanger will require cleaning. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
Page 38
• There is a special accessory kit available specifically designed for cleaning the heat exchanger. If required order 7 719 001 996. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
Page 39
2.2 Clean the heat exchanger from top to bottom using the brush. Refit the clean out coverplates in reverse order using a new seal (C) and tighten screws. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
Page 40
Fill the condensate trap with approximately 1/4 litre of water and refit in reverse order. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
Remove expansion vessel from boiler. Set the pressure of the new vessel to that required by the system. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi INSPECTION AND SERVICE 6 720 614 564b (2008/02)
Page 42
Fill the condensate trap with approxi- mately 1/4 litre of water and refit in reverse order. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 43
Transformer / PCB Disconnect all electrical connections from the control. Remove 5 screws (C) retaining the rear panel of the control and remove panel. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 44
Remove spark/flame electrode assembly (G) from heat exchanger. 12.3 12.4 Check CO/CO 2 levels as described on the “setting of the air/gas ratio” section. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 45
Burner Remove the burner (H). Replace new burner in correct position. Ensure that a new seal (K) is used. 14.2 14.3 14.4 INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 46
Unscrew the flow pipe (D). 16.4 Undo flue connection (E) from sump (F). Pull flue pipe up. Remove the heat exchanger. 16.1 16.2 16.3 16.4 INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 47
Disconnect the electrical connection from the sensor. Withdraw the spring clip. Withdraw the sensor (D) from the housing. To refit, follow the above in reverse. 20.1 INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 48
25.2 Withdraw the drain tap from its housing. To refit, follow the above in reverse. Ensure any seals that have been disturbed are renewed. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 49
Withdraw the pressure release valve (A) from its housing. To refit, follow the above in reverse. Ensure any seals that have been disturbed are renewed. 27.1 27.2 INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Page 50
29.2 Remove the heat exchanger. To refit, follow the above in reverse. Ensure any seals that have been disturbed are renewed. 29.2 INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi REPLACEMENT OF PARTS 6 720 614 564b (2008/02)
Remove manometer and re-seal inlet pressure point on gas valve. Fit new plastic seal to outlet adjuster (B). Re-fit brass cap over valve adjuster (C). INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi SETTING THE GAS/AIR RATIO 6 720 614 564b (2008/02)
THE GAS/AIR RATIO MUST BE RESET AFTER CONVERSION. REFER TO THE SERVICE & SPARES - SETTING GAS/AIR RATIO SECTION OF THIS MANUAL. INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi L.P.G. CONVERSION 6 720 614 564b (2008/02)
FAULT FINDING NOTE: This fault finding information is for guidance only. Worcester Bosch cannot be held responsible for costs incurred by persons not deemed to be competent. The electronic control system for this boiler incorporates a blue central indicator. This normally confirms the permanent mains supply but, by flashing during a fault, provides a guide to the cause as listed.
CENTRAL HEATING FUNCTION INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42CDi CENTRAL HEATING FUNCTION 6 720 614 564b (2008/02)
PREHEAT AND DHW FUNCTION INSTALLATION & SERVICING INSTRUCTIONS FOR WORCESTER BOSCH GREENSTAR 27CDi/30CDi/37CDi/42 CDi PREHEAT AND DHW FUNCTION 6 720 614 564b (2008/02)
GAS BOILER COMMISSIONING CHECKLIST This Commissioning Checklist is to be completed in full by the competent person who commissioned the boiler as a means of demonstrating compliance with the appropriate Building Regulations and then handed to the customer to keep for future reference. Failure to install and commission this equipment to the manufacturer’s instructions may invalidate the warranty but does not affect statutory rights.
SERVICE RECORD It is recommended that your heating system is serviced regularly and that the appropriate Service Record is completed. Service Provider Before completing the appropriate Service Record below, please ensure you have carried out the service as described in the manufacturer’s instructions.
Page 60
5. Is the incoming gas pressure at least 18mbar with the boiler at maximum output? Dedicated to heating comfort Worcester, Bosch Group Cotswold Way, Warndon, Worcester WR4 9SW. Tel. 01905 754624 Fax. 01905 754619 Worcester, Bosch Group is a brand name of Bosch Thermotechnology Ltd. worcester-bosch.co.uk 6 720 614 564b (2008/05)
Need help?
Do you have a question about the WORCESTER GREENSTAR CDi and is the answer not in the manual?
Questions and answers