Advertisement

Quick Links

Quick guide PV Point &
PV Point Comfort
Application guide
Information Class: Confidential
,
Fronius International, 29.04.2024

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PV Point and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Fronius PV Point

  • Page 1 Quick guide PV Point & PV Point Comfort Application guide Information Class: Confidential Fronius International, 29.04.2024...
  • Page 2 Business unit or organizational unit Fronius reserves all rights, in particular the right of reproduction, distribution and translation. No part of this work may be reproduced in any form or stored, processed, copied or distributed using electronic systems without the written permission of Fronius.
  • Page 3: Table Of Contents

    Wiring PV Point Comfort ........................... 8 Commissioning ........................... 11 Activation of the PV Point [Comfort] during initial commissioning ..........12 Activation of the PV Point [Comfort] at a later date ................13 Fuse protection of the socket or circuit ................... 14 PV Point..............................14 PV Point Comfort ............................
  • Page 4: Introduction

    The PV Point can be used to supply all important single-phase loads in the household up to 3 kW. The PV Point does not require the installation of a storage unit - but it can also be installed with a storage unit as an option.
  • Page 5: Installation

    The installation of the PV Point [Comfort] requires a modification to the basic shell. Four predefined outputs are marked on the underside of the inverter for this purpose, which can be used for the PV Point [Comfort] installation. The underside of the GEN24 series with the outputs is shown in Figure 2: Figure 2: Inverter underside of the Fronius GEN24 &...
  • Page 6: Pv Point Cabling

    The push-in spring terminals are characterized by their ease of use, which enables quick installation. No special tools are required to install the PV Point and no ferrules need to be fitted to the cables. With regard to cables, Fronius recommends the use of a copper cable with a cable cross-section of min. 1.5 mm²...
  • Page 7 Figure 5: Push-in spring clamp and cable requirements for installing the PV Point The PV Point's push-in spring-loaded terminal can be removed by pressing the catch on the back. For the subsequent cabling, the earthing of the PV Point must be connected to the internal earthing terminal block in the inverter.
  • Page 8: Wiring Pv Point Comfort

    Figure 7: Screw connection of the cable gland 2.3 PV Point Comfort cabling The PV Point Comfort is installed and wired into the GEN24 as follows: 1. First insert the insulation foil. Quick guide PV Point & PV Point Comfort...
  • Page 9 4. Plug the enclosed cables for the connection between the PCB and the inverter into the terminal provided. 5. Connect the two pairs of cables on the PCB to the PV Point terminal and the AC terminal of the inverter (L and N respectively).
  • Page 10 2.2 with the earthing terminal block. 7. For three-phase inverters, L2 and L3 are wired directly past the PV Point Print, while L1 and N are looped via the Print, as this must also provide power in parallel grid operation. As a final step, connect L1 and N coming from the grid directly to the terminal of the Comfort Print.
  • Page 11: Commissioning

    3 Commissioning The PV Point [Comfort] is commissioned via the web interface of the inverter and can be activated both during initial commissioning and at a later stage. Fronius recommends carrying out commissioning with the "Fronius Solar.start" app, which is available free of charge in the Google Play Store and for iOS. The Fronius Solar.start app is identified by the following icon (Figure 8):...
  • Page 12: Activation Of The Pv Point [Comfort] During Initial Commissioning

    "PV Point" mode. This selection applies to both PV Point and PV Point Comfort. Figure 10 shows the photo gallery of the most important steps and settings: Figure 10: Activation of the PV Point [Comfort] in the commissioning wizard during initial commissioning of the GEN24 &...
  • Page 13: Activation Of The Pv Point [Comfort] At A Later Date

    3.2 Activation of the PV Point [Comfort] at a later date The PV Point [Comfort] can also be installed and activated retrospectively at any time. In this case, it is also necessary to connect to the web interface of the inverter after installation. To activate, navigate away from the start page via the "Device configuration"...
  • Page 14: Fuse Protection Of The Socket Or Circuit

    4.1 PV Point With regard to the PV Point socket outlet, it is important that it is protected with an RCD (type A 30 mA) in order to guarantee personal protection and ensure compliance with standards. RCD sockets with an...
  • Page 15: Pv Point Comfort

    PV Point Comfort As the PV Point Comfort also supplies the phase in mains parallel operation, the circuit or socket must also be protected with a 13A miniature circuit breaker in addition to the RCD (type A 30 mA). There is a space-saving solution for this from ABB with the article designation "ABB DS301CC13A30".

This manual is also suitable for:

Pv point comfort

Table of Contents