Page 2
HVAC technicians are individuals who have suffi- cient professional or technical training in the field they are working in to enable them to carry out their assigned duties at the level of responsibility allocated to them and in compliance with the rel- Chilled ceilings WK-D-GK...
Load suspension systems only with the weight of the device. Adjacent components and con- necting ducts must be supported separately. Use only approved and adequately sized fixing material (fixing material is not included in the supply package). Chilled ceilings WK-D-GK...
Page 5
Chilled ceilings are used indoors only. To avoid hazards and damage due to frost, rooms with filled cooling circuits must be frost-free. If there is a risk of frost, especially on construc- tion sites, we recommend completely draining the water-bearing system. Chilled ceilings WK-D-GK...
Page 6
Stand clear of suspended loads, unless prop- erly secured. Check secure fixing after installation! During installation, a distance from the raw ceiling and the substructure to the water-side connection option must be taken into account. Chilled ceilings WK-D-GK...
Page 7
Assembly Installation types Fig. 8: WK-D-GK ceiling cooling element for combination with gypsum plasterboards Nonius hanger ceiling construction (on-site) Carrier sheet cooling panel Support profile / base profile (on-site) Heat conducting rail Bracket suspension element Copper tube meanders NOTICE! Do not fix any attachments, screws, nails or other pointed bodies in/on the cooling ele- ments.
Page 8
The cooling elements are lifted during the final installation of the plasterboard. In this process, jamming to the support profile must be avoided Fig. 9: WK-D-GK suitable for mounting on plaster- board ceilings Mounting bracket Cooling panel WK-D-GK Gypsum plasterboard (on-site)
Page 10
This is to be checked. Fig. 11: Deburring Cooling elements, except for the connection point of the copper tubes 12x0.35mm with support sleeve, must not be thermally processed. Fig. 13: Pipe connection 180° Chilled ceilings WK-D-GK...
Page 11
Before working on the water-side connec- tions, shut down, depressurise, and, if pos- sible, cool down the system. Cooling/heating capacities depending on Δt. For the heating function, surface temperatures > 35 °C should not be selected for reasons of comfort. Chilled ceilings WK-D-GK...
Page 12
Assembly Make connections to the cooling elements in such a way that external effects on the cooling ele- ments due to, e.g. thermal expansion, weight of the piping, vibrations, condensation and tensions are prevented. Chilled ceilings WK-D-GK...
Filling and supplemental must be filled into the system with the appropriate water quality in order to ensure the long-term operation of the system. Chilled ceilings WK-D-GK...
The water quality may change during operation. The water quality must be monitored and docu- mented at regular intervals to prevent corrosion. Cleaning During cleaning, the following points must be Fig. 17: Schematic illustration of WK-D-GK observed: Clean surfaces with a damp cloth. Pos. Component...