All electrical work is to be carried out by a qualified electrician using suitable materials for the application. Do not open the Tricel Vitae’s electrical unit cover without first isolating the mains power. Electrical work must be carried out strictly to the manufacturer’s instructions and to the relevant national rules for electrical installations.
Use appropriate lifting equipment. Take care around groundwork machinery. Always keep proper footing and balance. It is necessary to vent the Tricel Vitae at the inlet and the outlet of the plant. ...
The remaining treated wastewater now meets the required standard and is safely passed out of the Tricel Vitae plant. The treated effluent is now ready for discharge to a suitably designed discharge area as required by the relevant local authority.
However, do not desludge the reactor/aeration chamber as this will affect the treatment efficiency of the plant. WARNING: care must be taken not to damage pipework when desludging the tank TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Minimum length of the sling Ensure sufficient lifting height can be achieved and is available on site. If not a lifting bar, as per option two below, is required. Option 1 Option 2 TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Are static or rolling loads present on this site? Only suitably qualified personnel should install the Tricel Vitae. Suitably sized equipment will be required to excavate the hole and to lift the Tricel Vitae into place. 5.2 Inspection on reception of tanks ...
2. Concrete installation It is essential to consider two factors when determining which installation must be implemented: 1. Is the Tricel Vitae being installed in a ‘dry site’ or a ‘wet site’? A ‘dry site’ is a site in which the water table never rises higher than the base of the tank.
Excavation (dry & wet sites): 5.5.1.1 Excavation: length & width Length and width of the excavation must exceed the dimensions of the Tricel Vitae by at least 500mm to maintain a minimum space of 250mm all around the tank. Tricel Vitae...
The fabric must be chosen to allow the flow of water in and out of the excavation but to prevent the movement of fine soil particles into the gravel backfill. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Upon screening analysis, the backfill material shall have no more than 5% by weight passing a 2.36 mm sieve. Pea Gravel Crushed Stone TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Electrical installations must be carried out by a qualified and certified electrician. Please note different electrical requirements are dependent on the size of the Tricel Vitae system, read the following sections carefully. The customers’ minimum responsibility shall consist of: ...
5.10 Risers If a Tricel Vitae requires a deeper than standard installation to align with the wastewater outlet from the premises, manhole risers are available. These are to avoid the access cover being positioning in a depression, as shown in the following diagram: ...
(or its concrete surround). If this slab is constructed immediately above the tank, separate it from the surrounding concrete by a compressible material. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
For the grease trap to continue to perform effectively, it must be monitored/maintained on a regular basis and emptied when required. Warning If high levels of grease/oil are present within the Tricel Vitae, the plant will not achieve the required treatment quality and it will reduce the lifespan of plant components.
7 Disposal of treated water The treated wastewater from the Tricel Vitae should get disposed of as per guidelines from the planning regulations issued by your local authority. ...
8.2 Annual maintenance The Tricel Vitae will require a full service (available from your supplier) once a year to guarantee the efficiency of the plant gets maintained. Accommodating service personnel with clear access to the tanks is essential.
3.1 ‘Dimensions,’ these periods depend on the occupancy of the dwelling. The Tricel Vitae has a separate desludging access point. Desludging is carried out with a vacuum tanker (Tricel recommend the use of a licensed company).
Desludging is a critical part of the successful operation of the Tricel Vitae and is the responsibility of the customer. Only competent and approved personnel should carry out desludging. Desludging must get carried out when required as specified, and the plant should be regularly inspected to check the depth of sludge in the primary chamber.
Page 23
Service personnel must be provided with clear access to the plant. If others size the plant, Tricel will supply to these specifications. In this case, the responsibility lies with others in relation to the maximum flow/litres per day, the plant capacity and retention times.
Stormwater flooding Redirect stormwater drains. Stormwater must level never enter the plant Discharge hose/pipe blocked Find blockage and remove or replace the damaged hose/pipe TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Before taking any corrective action, always positively identify the real source of the odour. Check if the odour is coming from another outside source such as a storm drain. All Tricel Vitae’s plants vent gases back through soil pipes and out roof vents. Improperly installed roof vents can cause odour problems.
1. Classification of Product: Small wastewater treatment system for up to 50PT – Packaged and/or Site Assembled Domestic Wastewater Treatment Plant as set out in EN12566 Part3 2. Name of Product: Tricel Vitae T3 3. Product Characteristics: Material Glass Reinforced Plastic (GRP)
Page 27
Point 8. This declaration of performance is issued under the sole responsibility of the manufacturer identified in point 4. Signed for and on behalf of the manufacturer by: TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 28
Centervej Syd 5, DK – 4733 Tappernoje, Denmark 16 DOP02SAFUK11202306 EN 12566-3 Packaged wastewater treatment plants for treatment of domestic wastewater Product: Tricel Vitae T3 Material: GRP Notified Body: Certipro Certification and Testing department of Vito Boeretang 200, B-2400 Mol,Belgium Number.:...
Subject to our standard terms and conditions, which are available on request. In accordance with our standard policy of product development, this specification is subject to change without notice. (July 2018) TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 30
NOTES This page is intentionally left blank. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 31
NOTES This page is intentionally left blank. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 32
NOTES This page is intentionally left blank. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 33
NOTES TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 34
NOTES This page is intentionally left blank. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 35
NOTES This page is intentionally left blank. TRICEL VITEA T3 UK 6‐14 TRICEL.CO.UK ...
Page 36
Vitae T3 UK 14 0.84 2100 Tricel (Killarney) Unlimited Company Trading as Tricel Ballyspillane Ind. Est. Killarney, Co. Kerry, Ireland Tel: +353 (0)64 663 2421 I Email: sales@tricel.ie I www.tricel.ie In accordance with Tricel normal policy of product development these specifications are subject to change without notice.
Need help?
Do you have a question about the Vitae T3 UK5-14 and is the answer not in the manual?
Questions and answers