INSTALLATION & OPERATION GUIDELINES FOR SINGLE PIECE UNITS ® BIODISC BH – BL & NH – NL Klargester Environmental College Road North, Aston Clinton, Buckinghamshire, HP22 5EW Tel: +44 (0)1296 633033 Fax: +44 (0)1296 633001 Website: www.klargester.com Email: uksales@klargester.co.uk Important O n c e i n s t a ll e d , t h e m o t o r s h o u l d b e l e f t o n a n d r u n n i n g .
Covers must be kept locked. Observe all hazard labels and take appropriate action to avoid exposure to the risks indicated. The correct ongoing maintenance is essential for the proper operation of the equipment. Klargester offer a range of maintenance contracts, details on request.
PD0351 – Installation & Operation Guidelines for BH – BL & NH - NL Introduction Thank you for choosing a Klargester product. This manual will help you to keep it operating efficiently over a long service life. Please read this manual thoroughly, preferably before installation.
4.1.1 Care must be taken to ensure that the unit is not damaged during delivery and handling on site. If there is any damage it should be reported to Klargester After-Sales within 48 hours of delivery. 4.1.2 The design requirements of Klargester products will frequently mean that the centre of gravity of the unit is “offset”.
PD0351 – Installation & Operation Guidelines for BH – BL & NH - NL Site Planning The following points should be considered before installation of the equipment: 5.1.1 The discharge must have the consent of the relevant Environmental Regulator. 5.1.2 The installation should have Planning and Building Control approval.
PD0351 – Installation & Operation Guidelines for BH – BL & NH - NL 6.1.2 In situations where the excavation will not maintain a vertical wall, it will be necessary to support sidewalls of the excavation (E.g. with suitable trench sheets and bracing systems) to maintain a vertical wall from the bottom to the top of the excavation.
However, subsequent handling during transportation and installation may result in the movement of components and a subsequent need to re-adjust prior to starting the unit. If, on inspection, you consider that any components require adjustment, please contact Klargester. Page 8 of 13...
If the unit has been installed with no operational power supply, then remove the motor/gearbox unit and store it in a dry or heated environment until such time as the unit is ready for permanent operation. Klargester or an experienced contractor should then replace the motor gearbox unit.
These are generally all right to use in the normal concentrations and usage found in domestic housing applications. All commercial applications are individually assessed before installation for their laundry load. Please contact Klargester for advice if any changes are contemplated e.g. addition of extra laundry facilities.
This will cause the alarm to activate when power is re-established after power cuts, check that the rotor is turning correctly. In the event of any difficulties, contact Klargester. 9 Running Checks 9.1.1...
10.1.4 Klargester offer various levels of contract maintenance of all BioDisc Systems through our service company Tekserv who can be contacted on 0845 3550555 or by e-mail at info@tekserv.co.uk.
PD0351 – Installation & Operation Guidelines for BH – BL & NH - NL 10.2.4 Remove any surface scum from the Final Settlement Tank [A]. The steel mesh may be removed for access if required. Lower the hose to the bottom of the tank and remove any settled sludge. Replace the steel mesh.