Four Months before Delivery
• Complete your floor plan.
• Determine cable lengths (see Cable Information in
Chapter 4) and provide this information to your IBM
representative.
• If building alterations (such as painting, plastering, or
expanding electric service or communications
facilities) are needed:
Complete all necessary drawings and specifications
for the alterations.
Schedule getting the areas ready so that
alterations can be made.
Schedule alterations so that they are complete one
week before machine delivery.
One Week before Delivery
• All planned modifications for wiring, temperature
control, and humidity control should be completed
and tested.
• All work station cabling should be installed and
tested.
• Communications facilities should be installed and
tested.
• All building alterations should be completed.