  • Page 1 Engineering progress Enhancing lives REHAU EDGE ™ Technical Information...
  • Page 2: Table Of Contents

    Contents 01 Information and safety advice 02 Component overview 03 Pipes and fittings 04 Installation tools 05 Making the EDGE connection 06 Installation guidelines - General 07 System Protection 08 Water quality - Specific guidelines for water application 09 Pressure testing and commissioning...
  • Page 3 This Technical Information REHAU EDGE ™ - is valid from October 2022. The latest version of this Technical Information can be found at https://www.myrehau.com/buildingsolutions/library This documentation is copyright protected. The rights of translation, reproduction, drawing of illustrations, broadcasting, and rendering on photomechanical or by similar means as well as the storage in data processing systems, are reserved.
  • Page 4: Information And Safety Advice

    • EDGE fitting – means REHAU EDGE fittings made of void the REHAU warranty. engineered polymer or DZR brass with at least one EDGE connection (e.g. coupler, elbow, T-piece, adapter, union Piping network calculation connector etc) In addition to the information contained in this technical •...
  • Page 5 • The REHAU pipe cutters have a sharp blade. Store and piping system that have been generally approved by handle them in such a way that the REHAU pipe cutters will REHAU. Using components which are not part of not create any risk of injury.
  • Page 6: Component Overview

    02. Component overview 2.1 System components Size 16 – 25 Size 32 Pipes EDGE silver (hot and cold water) EDGE red (hot water) EDGE green (rain water) EDGE lilac (recycled water) Compression sleeves Material: PVDF, Colour: Black, Characteristics: Identical ends, protruding ribs...
  • Page 7 The print lines on EDGE pipes are black, whereas RAUTITAN pipes print lines are white. In addition, compared to the REHAU RAUTITAN Pipes, the standard EDGE hot and cold water pipe is silver as opposed to platinum.
  • Page 8: Pipes And Fittings

    Corrosion resistance of the pipes: No pitting No tendency for deposits Polymer pipe material reduces sound transmission along the pipe Good resistance to abrasion All EDGE pipes with WaterMark registration comply with AS/NZS 4020 (Components in contact with potable water) Peroxide-crosslinked polyethylene Peroxide-crosslinked polyethylene is designated PE-Xa.
  • Page 9 EDGE fitting components - All fittings and compression sleeves for EDGE can be used for water services. - Do not combine EDGE fittings or compression sleeves with components from other ranges. - Please note the dimensions of the fittings and compression sleeves.
  • Page 10: Installation Tools

    Able to compress sizes 16-32mm When using A-Light2 tool, use only compression When using L1 tool, use only compression jaws that jaws that are specifically approved for EDGE are specifically approved for EDGE Sleeves and Sleeves and Fittings (black colour).
  • Page 11 When cutting EDGE pipes, observe the following: • Cut the pipe square and without burrs. • Pipe cutters must be in good working condition. Approved pipe cutters for EDGE pipe: EDGE Silver Hot and cold water pipe Pipe Dimensions Hot water pipe...
  • Page 12: Making The Edge Tm Connection

    05 Making the EDGE connection EDGE Installation Steps – General overview Push the sleeve over the pipe Fully compressed joint EDGE compression sleeves can be fitted from both sides • Permanently sealed joint • Without O-ring (self-sealing pipe material) • Easy visual inspection •...
  • Page 13 1. Prior to cutting the pipe ensure the cut length accounts necessary, re-insert the loose inner sleeve onto the clip. for the insertion depth of the pipe into the EDGE Fitting (Approximately 1 sleeve length). • Note the direction of insertion: Inner sleeve groove facing 2.
  • Page 14 After insertion, check the correct insertion depth via the Place the tool jaws over the pipe, so that it is in firm inspection windows.
  • Page 15: Installation Guidelines - General

    • Do not extend the leverage of installation tools, e.g with pipes Compatibility of different thread types • Only the following thread types may be used with the REHAU EDGE system: Sealing threads in accordance with ISO 7-1 (AS 1722.1) and EN 10226-1:...
  • Page 16 B Arc • After bending, ensure that there are no kinks, wrinkles d Pipe diameter or bulges. Only cold bending of EDGE pipes is allowed. Fig. 6-2 Pipe bend bracket for plumbing 90 degrees, for size 16– 32 and pipe bend bracket for plumbing/heating 5 x d 90...
  • Page 17 When installing a joint on a bent pipe: • The distance measured perpendicularly from the bottom of the outer edge of the sleeve to the outer edge of the bent pipe must be at least 2.5 sleeve lengths (approx. 35mm for EDGE 16 / approx.
  • Page 18 R ½ the guideline values (see Table 6-2) for installation with or without pipe support channels. AS NZS 3500 guidelines Tab. 6-2 Guideline values for fixing parameters of anchor points for bracket and clip spacing are also approved for EDGE pipes.
  • Page 19 Max. recommended spacing of brackets and clips (m) and clips (m) EDGE Red EDGE Green 0.60 0.30 1.20 1.20 EDGE Lilac 0.70 0.40 1.40 1.40 0.75 0.50 1.50 1.50 0.85 0.70 1.70 1.50 Tab. 6-3 Recommended spacings of pipe bracket/clip for EDGE PE-Xa pipes...
  • Page 20 EDGE PE-Xa pipes. Pipe cover REHAU pipe support channel is clipped onto and firmly holds on the pipe. It stabilizes the pipe against sagging and improves the visual appeal in exposed areas. When using pipe support channel, bracket spacing can be increased to 2m regardless of the pipe size.
  • Page 21 6.6.3 Fitting cover 3. Deburr the ends of the pipe support channel. Clipping over the fitting is not possible with EDGE Fittings. Fig. 6-9 Deburring of pipe support channel 4. Clip the pipe support channel onto the pipe Fig. 6-7...
  • Page 22 6.7.1 Calculating thermal length changes the system. The effects of this stress can be mitigated by using deflection legs. EDGE PE-Xa pipes are particularly Due to the changing operational temperatures, especially suitable for this due to their flexibility.
  • Page 23 6.7.2 Deflection legs Do not fit pipe support channels or pipe brackets A deflection leg is the freely moveable pipe length, which on deflection legs as this would restrict their can take up the required thermal length changes. The flexibility. length of the deflection leg is influenced mainly by the material (material constant C).
  • Page 24 6.7.3 Calculation of deflection leg length Calculation of deflection leg length with EDGE pipe ΔL = α • L • ΔT The minimum length of deflection length (DL) is calculated by the following formula: ΔL = 0.04 • 7m • 50ºC = C •...
  • Page 25 The rating (e.g. wood fire heaters, etc.). of the temperature and pressure relief valve must be • If a heat storage tank is used, EDGE determined by the storage water heater manufacturer in pipes can be used after the tempering valve.
  • Page 26: System Protection

    • Prior to any installation, ensure all components cause corrosion. Where a contact with such being used are REHAU EDGE components only substances is foreseeable, protect fittings • Do not use dirty or damaged system components, pipes, and compression sleeves from contact, e.g...
  • Page 27 Protect EDGE pipe and fittings from contact with: When installing EDGE components and in aggressive environments (e.g. exposed to cleaning agents, aggressive gases, chloride mediums), protect pipes and fittings against Substance* Examples* corrosion adequately and in such a way that they are sealed against vapours.
  • Page 28 • The number of joints shall be kept to a minimum Fig. 7-5 Installation of EDGE system within concrete/screed floor with corrosion protection system Installation of EDGE systems within concrete/...
  • Page 29 • The length of pipe installed above ground shall be kept Inadequate corrosion protection of joints may to an absolute minimum not exceeding 2 metres. cause corrosion of EDGE brass fittings and lead Below ground installation should always be preferred.
  • Page 30 • Protect piping from UV rays in areas where UV radiation can occur (e.g. sunlight, neon light) i.e by installing in black conduit. • EDGE PE-Xa pipes shall be installed in dark areas or protected in conduit to avoid biofilm growth.
  • Page 31 Observe the installation manual of the auxiliary heating manufacturer and ensure that any tape used to fix the heat trace to the pipe is suitable for contact with EDGE components.
  • Page 32: Water Quality - Specific Guidelines For Water Application

    / Time T 70ºC / 49 years the suitability of EDGE pipe system must be checked with REHAU. In some cases, the available water quality may void the REHAU warranty unless appropriate water Short-term maximum / Time T + 80ºC / 1 year treatment is provided.
  • Page 33 KIWA that PEX pipes for water services specifications of DVGW worksheet W 291 can be done and heating installation do not cause any multiplication without impairing the functionality of REHAU drinking of micro-organisms and thus do not support microbial water installation if the active ingredients, concentrations, contamination or legionella growth.
  • Page 34 Chemical postrinse disinfections, active ingredients and concentrations according to DVGW W 291 The corresponding notes in the safety data sheets of the manufacturer must be adhered to. REHAU approval: this value may not be exceeded at any stage of the entire application duration of the installation. 8.6.4...
  • Page 35 Australian Guidelines for Drinking System limitations and water quality Water. Conduct a careful check on the local requirements before contacting REHAU with regard to the suitability of The main application for EDGE lilac plumbing systems EDGE green for this application.
  • Page 36: Pressure Testing And Commissioning

    Flushing and pressure testing may be conducted in (constant, decreasing, increasing) alone. accordance with AS/NZS 3500, or by following the REHAU • Subdividing the piping system into smaller test sections recommendations below.
  • Page 37 Pressure test for installations with EDGE PE-Xa pipes 9.1.3 REHAU Pressure test with air The REHAU recommended pressure test procedure is an alternative solution to the requirements as described in AS/ p [bar] NZS 3500. Important information on tests with pressurised air and...
  • Page 38 5. Pressure test is complete once the visual inspection confirms no leaks. 6. Test protocol is found in Appendix A8. 7. Securely drain the air out of the pipe system. Completion of REHAU pressure test with air 10 – 30 min ≥ 120 min 10 min 1.
  • Page 39: Fire Safety

    REHAU recommends to only use the fire protection methods which have been specifically tested with the EDGE pipe system.
  • Page 40 Darwin REHAU Pty Ltd – National Customer Service Centre Suite 1.02, Level 1, Quad 1, 8 Parkview Drive, Sydney Olympic Park, NSW 2127 AUSTRALIA Tel: 1300 768 033 Brisbane Fax: 1300 760 665 Email: sales.au@rehau.com Perth www.rehau.com.au Sydney Adelaide Melbourne...