OTC Series Air Cooled Chiller
Operation and Installation Manual
Manual # O002639AC
Date Effective: 08/01/2013

Advertisement

Table of Contents
loading

Summary of Contents for OPTI TEMP OTC Series

  • Page 1 OTC Series Air Cooled Chiller Operation and Installation Manual Manual # O002639AC Date Effective: 08/01/2013...
  • Page 3: Table Of Contents

    OTC Series Air Cooled Chiller Operation and Installation Manual Page Section 1 – Preface ......................... 2 Section 2 – About this Manual ......................2 2.1 General ..........................2 2.2 Warnings and Safety Symbols ....................2 Section 3 – General Information ...................... 3 3.1 Safety Precautions ........................
  • Page 4: Section 1 - Preface

    NOTE: The written information contained in this manual, as well as various drawings, are intended to be general in nature. OPTI TEMP strives to maintain an accurate record of all equipment produced for the course of its useful life. While every effort is made to standardize the design features of these chillers, the various options may make it necessary to re-arrange some of the components;...
  • Page 5: Section 3 - General Information

    Section 3 – General Information 3.1 Safety Precautions Make sure you read and understand all instructions and safety precautions listed in this manual before installing or operating your unit. If you have any questions concerning the operation of your unit or the information in this manual, please contact our Sales Department at 231-946-2931 or information@optitemp.com.
  • Page 6: Compliance

    Section 12.8 Specification of this manual. 3.3 Service and Support OPTI TEMP is committed to customer service both during and after the sale. If you have questions concerning the unit operation, please contact our Service Department at 231.946.2931.
  • Page 7: Section 4 - Unpacking

    During the winter months (between October 1 hazardous Propylene Glycol solution may be added to protect critical components from freeze damage. This solution can be flushed from the system prior to connecting to your process. Contact OPTI TEMP at 231-946-2931 or information@optitemp.com with any questions or disposal concerns.
  • Page 8: Section 5 - Description

    OPTI TEMP systems. A wide range of pumps, flow controls, monitoring devices, and filtration options are provided making the OTC Series chillers a flexible solution for a range of applications. *Standard OTC-.25A, .33A and .50A Chiller...
  • Page 9 (5) Special construction for certain engineered heat transfer fluids may be available. Contact "applications engineering" for more information. Note: "Stainless Steel" (S) or "High Purity" (D) wetted construction required with certain water quality options. 5/6/2013 \\OPTISERVER\Server\Opti Temp PRODUCTS\OTC\Air Cooled-Portable\D003680AK OTC Series Air Cooled Chiller Configuration, Option & Pricing Matrix...
  • Page 10 Consult applications engineering for lead time. (1) Equipped with transformer. (2) Extended lead time. (3) Brass Turbine pump R3 upgrade is required on these models in OTC-.5AL-P1-116 Select Voltage 460V configurations. 5/6/2013 \\OPTISERVER\Server\Opti Temp PRODUCTS\OTC\Air Cooled-Portable\D003680AK OTC Series Air Cooled Chiller Configuration, Option & Pricing Matrix...
  • Page 11 (1) Certain options not available on OTC-.25A, .33A, & .5A when equipped with active DI Control System. Contact applications for details. (2) Deionization control options D02 & D01 limit maximum operating temperature to 104 F (40C). 5/6/2013 \\OPTISERVER\Server\Opti Temp PRODUCTS\OTC\Air Cooled-Portable\D003680AK OTC Series Air Cooled Chiller Configuration, Option & Pricing Matrix...
  • Page 12 (1) UV System option includes a circulation pump upgrade for the De-ionization package. (2) Contact factory for amp draws on units with heaters. (3) Available on three phase units only. (4) Fluid circuit insulation standard for high temperature (Extended Range) package. Select Options OTC-.5AL-P1-116-SC1-LW1 5/6/2013 \\OPTISERVER\Server\Opti Temp PRODUCTS\OTC\Air Cooled-Portable\D003680AK OTC Series Air Cooled Chiller Configuration, Option & Pricing Matrix...
  • Page 13 Contains 50 ft. of Clearbraid® hose, 50 ft. of Armaflex® insulation, Male NPT to barb fittings, & hose clamps. Condenser Air Filter (Cleanable) (1) Contact factory for installation instructions. 5/6/2013 \\OPTISERVER\Server\Opti Temp PRODUCTS\OTC\Air Cooled-Portable\D003680AK OTC Series Air Cooled Chiller Configuration, Option & Pricing Matrix...
  • Page 14 Compressor The OTC Series Chillers are equipped with a hermetic reciprocating or hermetic scroll compressor, depending on model. Both the compressor and the motor are encased together and solidly mounted in the cabinet. The compressor is unidirectional and will only pump refrigerant when properly phased.
  • Page 15 not capable of drawing air in through ductwork on the intake or discharging air through ductwork on the exhaust. The discharge air will be significantly warmer than the intake air. Evaporator The standard evaporator is constructed of stainless steel plates and copper brazing. (An optional “nickel brazed”...
  • Page 16 For installations with overhead piping special precautions will have to be made during installation. Contact OPTI TEMP customer service department for details at 231-946-2931 or information@optitemp.com.
  • Page 17 OPERATION AND INSTALLATION MANUAL REMOTE CONDENSER # M002359AB FOR OTC and OTM SERIES ALL Models CAUTION (REFER TO ACCOMPANYING DOCUMENTS) CAUTION: RISK OF ELECTRICAL SHOCK. DISCONNECT SWITCH REQUIRED TO DE-ENERGIZE THE EQUIPMENT BEFORE SERVICING. CONNECTING THE (OPTIONAL) REMOTE CONDENSER THE CHILLER CONTAINS REFRIGERANT. Be sure that all mechanical piping and wiring conform to federal, state and local codes.
  • Page 18: System Construction Standards

    It is suggested that valves be installed on the “TO PROCESS” line and “FROM PROCESS” line at the OPTI TEMP unit to be used as balancing valves and to isolate the chiller should maintenance be required on the unit.
  • Page 19: Chilled Water Lines

    Recommended Hose Selection Table Standard Minimum Hose Length Standard Flow Rating Model OTC Hose Size from Machine .25A, .33A, ≥ ¾” ID 2.3 GPM @ 65 PSI < 10’ .5A, .75A, ≥ 1” ID 4 GPM @ 65 PSI >10’ 1.0A, 1.5A ≥...
  • Page 20: Overhead Piping And Drain Back Prevention

    Contact OPTI TEMP for further information at 231-946-2931 or information@optitemp.com. CAUTION: The OPTI TEMP system is designed as an “open system” with the top of the reservoir at atmospheric pressure. Do not connect any fittings to the cover of the reservoir or pressurize the reservoir in any way or damage to the system and/or personal injury could result.
  • Page 21: Section 7 - Operation And Start Up

    NOTE: Due to variation in required plug configurations OPTI TEMP units are shipped without a plug on the power cord. Electrical Voltage Range Table Nominal Operating Range 100V, 1 φ, 50 ΗΖ 95 -110V 115V, 1 φ, 60 ΗΖ 109-126V 110V, 1 φ, 50 ΗΖ...
  • Page 22: Operating Temperature Range Limits

    7.2 Operating Temperature Range Limits OPTI TEMP systems are designed to operate at fluid temperatures within a certain specified temperature range. All systems are not designed to operate over the same range. It is important that you do not operate the system outside of this intended range. Please refer to the specifications in section 5.2 Specifications and Available Options for details on the...
  • Page 23: Fluid Fill

    7.7 Temperature Setting and Adjustment OPTI TEMP systems are designed to operate within a certain specified temperature range. All systems are not designed to operate under or over the range. It is important that you do not operate the system outside of this intended fluid operating range.
  • Page 24 16B Love Controller – Guide 1. In addition to the Home Screen, there are three menu's in the 16B-XX Love Control a. Home Screen i. Used for setting the parameter to be controlled. Typically it is the temperature, water purity level, pressure or flow. b.
  • Page 25 Secure menu determines which items are displayed in the Secondary menu and how the Primary menu is displayed. 3. Typically the controls are shipped from Opti Temp in a locked state. They can be unlocked by entering a code found in the controller user manual.
  • Page 26: Fluid Bypass Valve Setting And Adjustment

    NOTE: Couplings and clamps are preferred to quick connect fittings because they have the potential for restricting the flow rate. CAUTION: Please contact OPTI TEMP if your process is equipped with a valve, which may periodically interrupt flow to the process. Bypass settings may be critical to protect the...
  • Page 27: Section 8 - Maintenance

    4. Turn the unit on for approximately 30 seconds to ensure the propylene glycol has had a chance to contact all of the wetted internal components. 5. Turn off the chiller and remove power from the unit. 6. Open the system drain connection (if applicable). Drain as much fluid as possible. 7.
  • Page 28: Section 9 - Troubleshooting

    If the chiller’s process fluid temperature is 5 degrees colder than the controller’s fluid set point, the Opti Temp chillers are programmed to shut off the compressor until the process fluid temperature warms up to the desired process fluid set point. In addition, a “freeze alarm”...
  • Page 29: Low Refrigerant Check

    9.1 Low Refrigerant Check Unfortunately, leaks happen. Opti Temp Inc. ships chillers all over the world and even with the best testing and packaging a large shock is all it takes to create a leak. So if you think maybe your chiller has lost its refrigerant, this guide will help you determine if it has or has not.
  • Page 30 arrangement with one controller on the unit and a second located remotely. In this case, set the Local/Remote switch to Local to make it easier to diagnose. 2. The second item is the refrigerant sight glass (Figure 1). This is a window into one of the refrigerant lines.
  • Page 31: Section 10 - Replacement Parts

    Section 10 – Replacement Parts OPTI TEMP recommends that our customers running critical applications have a stock of replacement parts available, in case of malfunction due to regular wear and tear of the chiller. The following list has been complied to assist the customer to differentiate which items are desired when considering replacement parts.
  • Page 32: Section 11 - Warranty And Service

    Section 11 – Warranty and Service OPTI TEMP is committed to customer service both during and after the sale. If you have questions concerning the unit operation, please contact our customer service department at 231-946-2931 or information@optitemp.com. OPTI TEMP systems are built to provide years of trouble free service. All systems are tested prior to shipping to insure you receive the highest quality product.
  • Page 33 OPTI TEMP can not be responsible for any damage occurring during shipment to the factory. OPTI TEMP ordinarily will evaluate the unit within 3 to 5 business days of receipt and will use reasonable effort to repair the unit promptly, in most cases within one week of receiving all the required parts.
  • Page 34 Field Service/Installation Charges The terms of OPTI TEMP’s standard warranty DO NOT provide for “in the field” or “on-site” repair service under any circumstances. However, OPTI TEMP can arrange “on-site” service, at customer expense, for chiller installation or repair in most areas. Service is generally available throughout the continental US, Canada, and parts of Mexico, Europe, Israel, Asia, Africa, South America, and mainland China.
  • Page 35 Please call 231-946-2931 to request an RMA number or an RMA form and fax to 231-946- 0128. All items returned to OPTI TEMP must be clean and dry. All liquids must be drained from the system. Systems returned with coolant present are subject to a minimum hazardous material disposal fee.
  • Page 36: Section 12 - Appendix

    Section 12 – Appendix 12.1 Dew Point / Temperature Chart Outside Relative Temperature to Laser Outside Temp Degrees Dewpoint Temp Degrees Humidity Degrees °F °C °F °C °F °C °F °C...
  • Page 37 002359AB Addendu Other Options CCR02 - 2 with BLYGOLD Remote Condenser Cab Other Options Custom 36" Cabinet Other Options #N/A #N/A Other Options Formula Qty. Size Description Part Number OptiShield #N/A Options-Notes (Sales) F003285AP Opti Temp Job MASTER Workbook -19845...
  • Page 41 12.6 Installation Diagram...
  • Page 42: Water Quality Guidelines

    12.7 Water Quality Guidelines Permissible (PPM) Desirable (PPM) Microbiologicals (algae, bacteria, fungi) Inorganic Chemicals Calcium <40 Chloride <25 Copper Iron <0.1 Lead 0.015 Magnesium <12 Manganese 0.05 <0.03 Nitrates/Nitrites 10 as N Potassium <20 Silicate <1.0 Sodium <20 Sulfate <50 Hardness <0.05 Total Dissolved Solids...
  • Page 43: Pump Curves

    12.8 Pump Curves Standard Pumps Positive Displacement Pump(s) Flow (LPM) P3&4 P1 &2 60 Hz 60 Hz P5&6 Pressure Pressure 60 Hz (PSI) (BAR) P1 &2 P3&4 P5&6 50 Hz 50 Hz 50 Hz Flow (GPM) Centrifugal Pump(s) Flow (LPM) Pressure Pressure C4 60 Hz...
  • Page 44 Optional Pumps Continued Regenerative Turbine Pump(s) Flow (LPM) R5&6 50 Hz R5&6 60 Hz Pressure Pressure (PSI) (BAR) R1&2 R1&2 R3&4 R3&4 50 Hz 60 Hz 50 Hz 60 Hz Flow (GPM) Regerative Turbine Pum p(s) Flow (LPM) R7&8 R7&8 50 Hz 60 Hz Pressure...
  • Page 45: Rohs Material Table

    12.9 RoHS Material Table PROPRIETARY - OPTI TEMP, Inc. OTC Series Material Compliance Summary Table - ROHS Standard Model(s) Used for Analysis: OTC-.25, .33, .5, .75, 1.0 and 1.5A Date Effective: 6/29/2007; Last Updated: 10/1/2007 Toxic or Hazardous Substances and Elements...
  • Page 46: Electrical Interfacing

    1) "Normally Open" or "Normally Closed" contacts should be specified at time of order. 2) Consult OTM or OTC Series Chiller Configuration & Option Matrix for additional information regarding available options. 3) Contact OPTI TEMP applications engineering at 231-946-2931 for assistance.
  • Page 49 Fig # 4: 1 fan...
  • Page 50 Initial Setting InPt tPUn tP-H tP-L 45.0 CtrL S-HC COOL COOL ALA1 ALA2 HEAT ALA3 TOLERANCE SALA CoSH C-SL ASCII ASCII C-no 9600 9600 Prty EvEn EvEn StoP Parameters (Sales & Shop) F003285AP Opti Temp Job MASTER Workbook -19845...
  • Page 51: Glycol Tables

    12.13 Glycol Tables Table 1 Increased Flow Requirements for 50% Glycol as Compared with Water Fluid Temp (°F) Flow Increase Need for 50% Glycol as Compared with Water 1.22 1.16 1.15 1.14 1.14 Example: A water cooled condenser requires 11 GPM of 100°F water for condensing. If 50% glycol / water mixture is used the flow rate will increase by a factor of 1.16.
  • Page 52 X004690AA PID Flow Meter Menu Value Operation Mode OUT1 OUT2 Regulation Mode Pid0 IoF0 CLPD CoeF dEAd tPoF Initial Setting InPt tPUn tP-H tP-L CtrL S-HC HEAT ALA1 ALA2 ALA3 SALA CoSH C-SL ASCII C-no 9600 Prty EvEn StoP Page 1...
  • Page 53: Notes

    12.14 Notes...
  • Page 54 X004691AA Pressure Transducer Menu Value Operation Mode OUT1 OUT2 Regulation Mode Pid0 dEAd tPoF Initial Setting InPt tPUn tP-H tP-L CtrL Onof S-HC HEAT ALA1 ALA2 ALA3 SALA CoSH C-SL ASCII C-no 9600 Prty EvEn StoP Page 1...