5. Commissioning
5
Commissioning
5.1
Check points before commissioning
27
CAUTION
If the temperature in the solar collectors is higher than
130°C, the control system operates in safety mode. Wait
until the evening before start-up or cool down (cover) the
solar collectors.
5.1.1.
Domestic hot water calorifer
1. Before start-up, the heating installation must be completely
emptied and rinsed.
2. Make sure that all valves on the circuit are opened.
3. Fill the installation with water and check hydraulic tightness.
5.1.2.
Primary solar circuit
¼See installation and commissioning instructions for the solar
station.
5.1.3.
Primary heating circuit
¼See installation and service manual for the boiler or heat pump
5.1.4.
Electrical connection
Check the electrical connections, particularly the earth.
UBVT 200...400 SC UBVT 200...500 DC