STEP 1
Set the Armor-Edge
All Steel joint assembly to the correct line of the
®
construction joint and hold in place with nail stakes through the holes
in the setting brackets.
STEP 2
Insert 2 x 4 x 5 inch (50 x 100 x 125 mm) wooden nailing blocks into the
setting bracket behind the nail stakes. For long runs, join joint assembly
at overlap using provided nylon nuts and bolts.
STEP 3
Adjust the assembly to the specified elevation and hold in place with
duplex nails through the nail stakes. Adjust to correct level and elevation
using wedges if needed.
STEP 4
If the Armor-Edge
All Steel joint assembly will butt up to a saw-cut
®
contraction joint, cut through the full depth of the side of the joint
assembly that abuts the saw-cut to allow activation of the joint.
STEP 5
Place Diamond Dowel
®
plates on the opposite side of the form to the nail stakes. Ensure
pocket formers completely cover the plate that will protrude into the
first placement.
STEP 6
Place and finish the first slab. Use internal vibration to consolidate
concrete around the assembly per industry guides for embedments.
Remove concrete paste from the top of the Armor-Edge
during finishing.
STEP 7
Remove nail stakes, wooden nailing blocks and wedges (if used) taking
care not to disturb the form.
STEP 8
Place and finish the second slab. Use internal vibration to consolidate
concrete around the assembly per industry guides for embedments.
STEP 9
Remove concrete paste from the top of the Armor-Edge
during finishing.
STEP 10
Threads of nylon nut will strip when concrete contracts.
STEP 11
Fill joints as outlined in the project specification.
ARMOR-EDGE
ALL STEEL JOINT ASSEMBLY - INSTALLATION GUIDE
pocket formers over the Diamond Dowel
®
setting bracket
®
steel bars
®
steels bars
®
nail stake
place Diamond Dowel
®
pocket formers over the
Diamond Dowel
plates
®

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ARMOR-EDGE and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for RNA ARMOR-EDGE

  • Page 1 ® STEP 6 Place and finish the first slab. Use internal vibration to consolidate concrete around the assembly per industry guides for embedments. Remove concrete paste from the top of the Armor-Edge steel bars ® during finishing. STEP 7 Remove nail stakes, wooden nailing blocks and wedges (if used) taking care not to disturb the form.
  • Page 2 If your project involves intersections, please follow the below guides: For price quotes, email inquires to csr@pna-inc.com. To place an order, email your purchase order (PO) to orderspna@pna-inc.com. To speak with a Customer Service Representative, call 1 (800) 542-0214. www.pna-inc.com ©2022.

Table of Contents