1
Cast 100mm concrete base with central drainage hole
for soak away.
3
Place access section onto wet concrete and insert
ducting.
2a
Using the appropriate hole cutter drill holes into a
STAKKAbox section as required for incoming ducts OR
2b
Use factory pre-drilled duct access sections.
4
Add sections by stacking them vertically, with external
ribs positioned at the bottom.
www.nal.ltd.uk

Advertisement

loading

Summary of Contents for NAL STAKKABOX

  • Page 1 IMPORTANT READ THIS www.nal.ltd.uk CIVILS INSTALLATION OF STAKKABOX Using the appropriate hole cutter drill holes into a STAKKAbox section as required for incoming ducts OR Cast 100mm concrete base with central drainage hole Use factory pre-drilled duct access sections. for soak away.
  • Page 2 IMPORTANT READ THIS www.nal.ltd.uk CIVILS INSTALLATION OF STAKKABOX Remove the marked section and cut with hand saw Mark the top section in line with finished surface along the pre-marked line and refit back onto the level, allowing for depth of cover & frame.