Commissioning
3.2

Inspection procedures

3.2.1
Introduction
Inspection procedures include preventative visual controls, monitoring and measuring work
before and during commissioning. Inspection procedures enable changes to the turbocharger
to be detected. Engine damage can be prevented.
3.2.2
Checks before commissioning
Air filter mat (if present)
Check for damage and contamination.
Lubricating system
Contaminated oil
Serious damage to engine or property can be caused by dirt and solid mate-
rial particles in the oil.
CAUTION
At initial commissioning and after all service work, the complete lubricating
system must be thoroughly flushed with warm oil.
Use special running-in filters when running in the engine and after all ser-
vice work on the lubricating system.
Check that the oil filter is clean before commissioning.
Check the oil pressure in the oil supply pipes.
Warning plates
Check whether warning plates are present and legible.
Check whether the protective sheets have been removed.
Air/water cooling
Version with compressor wheel cooling:
Failure of compressor wheel cooling
Any prolonged failure of the compressor wheel cooling will shorten the re-
placement interval of the compressor wheel.
CAUTION
Make sure there is an uninterrupted supply of cooling air during operation.
© Copyright 2016 ABB. All rights reserved.
HZTL4031_EN
Page 25 / 117
Revision D
June 2016

Advertisement

Table of Contents
loading

This manual is also suitable for:

A130-m67

Table of Contents