Download Print this page

Advertisement

Quick Links

MuteClip
Wall
02 - To Stud Wall
04 - Direct to Wall
06 - Windows, Doors, Openings and Pitched Ceilings
Ceiling
08 - Direct to Concrete Ceiling
10 - To Battened Concrete Ceiling
12 - To Wooden Joist Ceiling
15 - MuteClip XP
17 - MuteClip LP
www.iKoustic.com
01937 588226
Sales@ikoustic.com
Creating Quieter Spaces Together
Installation Guides
®
iKoustic Limited,
Units 4 & 5, Erivan Park, Sandbeck Way,
Wetherby, West Yorkshire, LS22 7DN
Creating Quieter Spaces Together

Advertisement

loading

Summary of Contents for iKoustic MuteClip

  • Page 1 06 - Windows, Doors, Openings and Pitched Ceilings Ceiling 08 - Direct to Concrete Ceiling 10 - To Battened Concrete Ceiling 12 - To Wooden Joist Ceiling 15 - MuteClip XP 17 - MuteClip LP www.iKoustic.com iKoustic Limited, 01937 588226 Units 4 &...
  • Page 2 Acoustic Mineral Wool can be friction-held between the joists/battens, if required use thin wiring to keep it suspended. • Measure up and mark out the appropriate locations for the MuteClips (See configurations or contact iKoustic for appropriate dimensions). The perimeter MuteClips must be no further than 100mm from the adjacent surfaces.
  • Page 3 MuteClip centres to vary betwen 600 and 1200m centres creating a Diamond configuration. • Attach MuteClip Channels into MuteClips, channels should run horizontally. MuteClip Channels must overlap by 200mm, fix 4 self-tapping screws into the shoulders of the MuteClip Channels to give a secure join. •...
  • Page 4 Drill hole in the wall, plug this hole and fix the screw through the Clip into the hole. • MuteClips to be spaced a maximum of 600mm apart vertically MuteClip centres to vary betwen 600 and 1200m centres creating a Diamond configuration (See configurations or contact iKoustic for appropriate dimensions). •...
  • Page 5 MuteClip Channels must overlap by 200mm, fix 4 self-tapping screws into the shoulders of the MuteClip Channels to give a secure join. • MuteClip Channels should not overlap on a MuteClip. • Insert Acoustic Mineral Wool between/behind the MuteClip Channels.
  • Page 6 Windows, Doors, Openings and Pitched Ceilings Windows and Doors When installing a MuteClip system around a Door or Window, a piece of channel should be installed above each door and window to ensure the plasterboard is supported along the edge.
  • Page 7 Vents and Openings MuteClip Channel must not be installed over any opening or vent in your wall or ceiling system. To overcome this, install a MuteClip and MuteClip Channel section above the opening or vent. This will help support the weight of the system.
  • Page 8 • Attach MuteClip Channels into MuteClips. MuteClip Channels should overlap by 200mm, fix 4 self-tapping screws into the shoulders of the channels to give a secure join. • MuteClip Channels should not overlap on a MuteClip.
  • Page 9 • Fix your first layer of Acoustic Plasterboard to the MuteClip Channels. Acoustic Plasterboard must not be in direct contact with any adjacent surfaces. There must be a 2-5mm gap around the perimeter of the room. • Seal the perimeter and any other gaps with Acoustic Sealant.
  • Page 10 Screw MuteClips into the appropriate joists. • Attach MuteClip Channels into MuteClips, channels must run perpendicular to the joists/battens. MuteClip Channels must overlap by 200mm, fix 4 self-tapping screws into the shoulders of the MuteClip Channels to give a secure join. www.iKoustic.com...
  • Page 11 Acoustic Mineral Wool can be friction-held between the joists/battens, if required use thin wiring to keep it suspended. • Fix your first layer of Acoustic Plasterboard to the MuteClip Channels. Acoustic Plasterboard must not be in direct contact with any adjacent surfaces. There must be a 2-5mm gap around the perimeter of the room.
  • Page 12 Screw Clips into all the appropriate joists. • Attach MuteClip Channels into MuteClips, channels must run perpendicular to the joists. MuteClip Channels must overlap by 200mm, fix 4 self-tapping screws into the shoulders of the MuteClip Channels to give a secure join. www.iKoustic.com...
  • Page 13 MuteClip Channels must not overlap on a MuteClip. • Fix your first layer of Acoustic Plasterboard to the MuteClip Channels. Acoustic Plasterboard must not be in direct contact with any adjacent surfaces. There must be a 2-5mm gap around the perimeter of the room.
  • Page 14 4/6 Square Please contact iKoustic to confirm correct configurations appropriate for your system. If you need any assistance, please call us on 01937 588 226. www.iKoustic.com iKoustic Limited, 01937 588226 Units 4 & 5, Erivan Park, Sandbeck Way, Sales@ikoustic.com Wetherby, West Yorkshire, LS22 7DN...
  • Page 15 Acoustic Mineral Wool can be friction-held between the joists/ battens, if required use thin wiring to keep it suspended. • Mark out the locations for the MuteClip XP’s (See configurations or contact iKoustic for appropriate dimensions). The perimeter MuteClip XP’s must be no further than 100mm from the adjacent walls.
  • Page 16 • If using MuteClip XP to level uneven joists, take some time to measure the placement of the MuteClip XP’s and Channels. A laser level should be used when calculating the placement of MuteClip XP. • Attach MuteClip Channels into MuteClip XP’s, channels must run perpendicular to the joists.
  • Page 17 Acoustic Mineral Wool can be friction-held between the joists/battens, if required use thin wiring to keep it suspended. • Mark out the locations on the side of the joists for the MuteClip LP’s (See configurations or contact iKoustic for appropriate dimensions). MuteClip LP’s attach to the side of the joists.
  • Page 18 • Take a lot of time to measure when fixing the first MuteClip LP’s and MuteClip Channel, as you only want a few mm of the MuteClip Channel sitting proud of the bottom of the joists. • Attach MuteClip Channels into MuteClip LP’s, channels must run parallel to the joists.