Unloading:
The panels can be unloaded from a lorry using a forklift truck or a crane. When lifting, special care must be taken to ensure that the
panels cannot slip or fall off.
Storage: Never stack more than 30 panels on a pallet.
Storage: Never stack more than 25
panels on a stake rack.
Do not move more than 2 stake racks
at a time using a forklift truck.
Move only one stake rack at a time
using a chain sling.
Distribution Partner: Fomacon Group
Mörsenbroicher Weg 191 | D- 40470 Düsseldorf
General information
Tel.: +49 211 975 323 90
Free call: +49 800 11 00 77 5
produced by:
www.vario-mat.com
E-Mail: info@vario-mat.com

Advertisement

loading

Summary of Contents for OKULEN VARIO mat 1+AS

  • Page 1 produced by: General information Unloading: The panels can be unloaded from a lorry using a forklift truck or a crane. When lifting, special care must be taken to ensure that the panels cannot slip or fall off. Storage: Never stack more than 30 panels on a pallet. Storage: Never stack more than 25 panels on a stake rack.
  • Page 2 produced by: Use of the panels: The upper side is engineered with approx. 5 mm high nubs. Use of the panels: The underside is striated/roughened. Distribution Partner: Fomacon Group Tel.: +49 211 975 323 90 www.vario-mat.com Mörsenbroicher Weg 191 | D- 40470 Düsseldorf Free call: +49 800 11 00 77 5 E-Mail: info@vario-mat.com...
  • Page 3 produced by: Connecting 2 panels: Connect and screw the panels using the 2-way metal connector, 2 washers and 2 hexagonal screws (M10x16mm). All adjacent panels must be connected in this way. Connecting 4 panels: Connect and screw the panels using the 4-way metal connector, 4 washers and 4 hexagonal screws (M10x16mm). All adjacent panels must be connected in this way.