BioCycle 8200 Ecolution Installation Manual

Advertisement

BioCycle Ltd
15 Mexted Place, Hamilton 3216
0800 246 292
enquiry@biocycle.nz
www.biocycle.nz
BioCycle
8200 Ecolution
INSTALLATION
GUIDE
th
Published 5
December 2019

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 8200 Ecolution and is the answer not in the manual?

Questions and answers

Summary of Contents for BioCycle 8200 Ecolution

  • Page 1 BioCycle Ltd 15 Mexted Place, Hamilton 3216 0800 246 292 enquiry@biocycle.nz www.biocycle.nz BioCycle 8200 Ecolution INSTALLATION GUIDE Published 5 December 2019...
  • Page 2 Assurance prior to dispatch, it is inevitable that sometimes a component may get overlooked or even receive damage during transit. You should check over your new BioCycle tank thoroughly upon receipt and if you find anything not as it should be, please notify us immediately and we’ll ensure it gets remedied without delay.
  • Page 3 2310mm High. There are 4 x Reid Swiftlift points on the BioCycle tank. At the time of publication these are each 2.5tonne rated. They are clearly marked as lifting points. A spreader bar should be used by the crane operator when lifting the tank.
  • Page 4 (sand, pea metal or GAP7) should be evenly spread as a settlement platform for the tank. Sewer pipe from the dwelling should be 100mm DWV type and fall at least 1:60 from the dwelling to BioCycle tank. Care should be taken to communicate with the subfloor plumbing contractor for each property prior to them laying their pipes.
  • Page 5 During backfilling, shaping of topsoil should be undertaken to make certain that stormwater cannot gravitate and collect on top of or around the BioCycle tank. It may be necessary to cut swale drains nearby to ensure surface water runoff away from tank location. Backfill soil should be free of large rocks and air voids should also be avoided.