  • Page 1 Modular Micro Data Centre Solutions Installation Manual zelladc.com...
  • Page 2: Table Of Contents

    Table of Contents 1. Introduction 2. Safety Instructions 3. Power Connection 4. Access Control 5. Single & Dual Cooling System Commissioning Steps 6. PDView Access 7. Pyrorack Commissioning & User Guide 8. Start-up & Ready for Population...
  • Page 3: Introduction

    1. Introduction A Micro Data Centre is a stand-alone housing unit that replicates all of the cooling, security and power capabilities of a traditional data centre on a much smaller, lower cost scale. It miniaturizes the data centre into the size of an average refrigerator, offering its own cooling and power capabilities, significantly reducing operational and energy costs by 30-60%, and on-premise IT footprint.
  • Page 4: Safety Instructions

    2. Safety Instructions 2.1 Overview This manual contains instructions relating to safety, installation, operation, maintenance and warranty of this product and its Important safety note components. Caution needs to be taken when removing the Please keep this manual in a safe place for future references. side panels of the Micro Data Centre, in particular Handling Safety when dealing with the 38U as they are heavy.
  • Page 5: Power Connection

    3. Power Connection 3.1 Power Supply Requirements 3.2 Switchboard Operation Important note Following the connection to mains power DEPENDING ON SIZE AND MODEL. Power consumption can vary DEPENDING ON MODEL THE SWITCHBOARD LAYOUT AND from less than 10 amps and up to 60 amps depending on load. CONFIGURATION IS DIFFERENT.
  • Page 6 3. Power Connection 3.3 Power Supply diagram to PDU switchboard Non-monitored sockets UPS Power Cooling system Cooling system Mains power...
  • Page 7 3. Power Connection 3.4 Switchboard layout Front View Rear View...
  • Page 8: Access Control

    4. Access Control 4.1 Metal Key Pad Operation 4.2 Biometric / Card Reader 4.3 L.E.D. Key Pad Operation The default code for the doors are pre-set in the factory The Zella Pro is supplied with a default card which will The default code for the doors are pre-set in the factory as follows: open the front door.
  • Page 9: Single & Dual Cooling System Commissioning Steps

    5. Single & Dual Cooling System Commissioning Steps Important Safety Warning 5.3 Wiring BEFORE PLUGGING THE EXTERNAL CONDENSER POWER CABLES The Zella Pro is supplied with all the cables (orange and grey) (ORANGE AND GREY) TO THE BACK OF THE ZELLA PRO. ENSURE which is pre-coiled and ready to be run with the copper piping THE COOLING SYSTEM RCD IS OFF ON THE BASE MOUNTED during the commissioning process.
  • Page 10 5. Single & Dual Cooling System Commissioning Steps 5.3 Wiring cont. Electrical Hazard – Ensure cooling system is in the OFF position on Zella Pro base mounted switchboard and orange cooling system plug is unplugged from rear of switchboard Grey cable termination in condenser Orange cable termination in condenser (supplies power back to the Zella Pro) (supplies power to the external condenser)
  • Page 11 5. Single & Dual Cooling System Commissioning Steps 5.3 Wiring cont. PLEASE NOTE: WHEN PLUGGING THE CABLE CONNECTORS, YOU SHOULD HEAR A CLICK TO CONFIRM CONTACT. AFTER INSERTING THE PLUG ENSURE BOTH ORANGE AND GREY CABLES ARE LOCKED BY TURNING THE YELLOW DISK ON THE SIDE OF THE CABLE CONNECTOR WITH A SCREW DRIVER.
  • Page 12 5. Single & Dual Cooling System Commissioning Steps 5.4 Copper Piping (refer to handout in Zella Pro) Cut the pipe ends with a pipe cutter Check that the flaring is properly made Use torque wrenches when tightening the flare nuts Remove burrs with the cut surface facing downwards Never use old or pre-used pipes Protect ends from dust...
  • Page 13 <1+=/">%?;-<@ 7-*5%,>139,*-.#*$+''#0-*,#--%0:,6 5. Single & Dual Cooling System Commissioning Steps J70*-.%,*%11+,-'3-%)02*#3$.*,#$-%)0*%,* ,.)=0*=%-.*311*%-,*5%,>139,*)0*8)'*-.#* >+'>),#*)8*#@>1303-%)06K ,#*-.#*'#/)-#*$)0-')11#'2*3%/*-.#* 0,/%--#'*3-*-.#*%05))'*+0%-6*78*-.#'#* 309-.%0:*-)*;1)$<*,%:031,*;#-=##0* +0%-*305*-.#*'#/)-#*$)0-')11#'2* <1+=/">%?;-<@ .*3,*3*$+'-3%02*-.#*+0%-*=%11*0)-* 5.5 Start up Procedure – Single Cooling A9B(9,4A:,9% 7-*5%,>139,*-.#*$+''#0-*,#--%0:,6 0)-*5')>*-.#*'#/)-#*$)0-')11#'6*?)* "CD6+*#$.*%56**&.+ J70*-.%,*%11+,-'3-%)02*#3$.*,#$-%)0*%,* ONLY once the condenser has been hardwired and copper piping connected can the 7-*$.30:#,*-.#*-#/>#'3-+'#*,#--%0:6 /3@%/+/*5%,-30$#*8)'* ,.)=0*=%-.*311*%-,*5%,>139,*)0*8)'*-.#*...
  • Page 14 5. Single & Dual Cooling System Commissioning Steps <1+=/">%?;-<@ 5.6 Start up Procedure – Dual Cooling 7-*5%,>139,*-.#*$+''#0-*,#--%0:,6 <1+=/">%?;-<@ J70*-.%,*%11+,-'3-%)02*#3$.*,#$-%)0*%,* 7-*5%,>139,*-.#*$+''#0-*,#--%0:,6 ONLY once the condensers have been hardwired and copper piping been ,.)=0*=%-.*311*%-,*5%,>139,*)0*8)'*-.#* J70*-.%,*%11+,-'3-%)02*#3$.*,#$-%)0*%,* >+'>),#*)8*#@>1303-%)06K ,.)=0*=%-.*311*%-,*5%,>139,*)0*8)'*-.#* connected can the cooling system be turned on. ()*+,#*-.#*'#/)-#*$)0-')11#'2*3%/*-.#* >+'>),#*)8*#@>1303-%)06K +,#*-.#*'#/)-#*$)0-')11#'2*3%/*-.#*...
  • Page 15: Pdview Access

    6. PDView Access Default IP address is 192.168.0.192 Zella Pro PDU Configuration Guide OPTION 1: To access the Zella Pro PDU using an smart device (iPhone, iPod, iPad, andriod devise etc.) follow these steps: Download the following App (Raritan PDView) from the Apple App Store, Connect the Apple device with the app installed into the Zella Pro PDU/door access portal, Use the following to access:...
  • Page 16 6. PDView Access OPTION 2: To access the Zella Pro PDU using LAN connections follow these steps: Plug a CAT cable directly into the PDU and your computer, Access a web browser, Type the IP address allocated to the PDU into the web browser. At this stage if you do not know the IP address go back to ‘OPTION 1’.
  • Page 17 ‘OPTION 1’ above, Plug network cable / switch directly into the PDU, Access the PDU through local Display, If you have any questions please contact Zella DC: Australia: 1300 117 644 International: + 61 8 6311 2814 ONCE YOU HAVE ACCESSED THE PDU VIA WEB BROWSER...
  • Page 18: Pyrorack Commissioning & User Guide

    7. Pyrorack Commissioning & User Guide IMPORTANT For effective and safe installation follow the steps in the next few slides. Please note: Accidental discharge will occur if this guide is not followed step by step. For effective and safe installation follow the steps below See cannister connection quick guide. Please note: Accidental discharge will occur if this guide is not followed step by step Please print, laminate &...
  • Page 19 7. Pyrorack Commissioning & User Guide IMPORTANT 10. 7.3 Commissioning Steps Fit the Mains fuse F5 (far right hand side) For effective and safe installation follow the steps in the next few slides. Insert mains supply cable (C13) Please note: Accidental discharge will occur if this guide is not followed Wait 5 seconds step by step.
  • Page 20 Warning Fire Suppression System Information Before working within the Zella Pro ALWAYS ensure you follow these steps: Turn key switch to manual Isolate both zones 1 and 2 by pressing the isolate zones buttons located on the front panel A beeping sound will continue intermittently as a reminder Once you have completed work within the MDC and you are ready to close the doors press the isolate buttons 1 and 2 once more Turn the key switch back to the automatic position...
  • Page 21 7. Pyrorack Commissioning & User Guide 7.6 Pyrorack Canister Replacement 7.7 Important tips. IMPORTANT Before working within the Zella Pro ALWAYS ensure you follow these steps: Decommission Pyroack first Turn key switch to manual Isolate both zones 1 and 2 by pressing the isolate zones buttons located on the Remove Mag fuse F3 from the rear of the Pyrorack (far left) front panel Wait 5 seconds...
  • Page 22: Start-Up & Ready For Population

    8. Start-up & Ready for Population NOTE: Ensure adequate gaps are left between the equipment housed within The Zella Pro Micro Data Centre is a PLUG N PLAY unit therefore once it has been installed by a qualified contractor the Micro Data Centre is ready for use! the Micro Data Centre to ensure an effective air-flow is maintained.
  • Page 23 Meet the uptime experts Over a decade ago Zella DC pioneered the micro data centre. Since then, our next- generation server rooms have been proven to work in the harshest environments on earth. The result is a vendor-agnostic approach to software, hardware manufactured to global standards, and partners across five continents.