Accessories: one encoder connecting cable (which is integrated with the standard
encoder ERN487-2048).
●
One copy of user's manual for traction machine and one copy of user's manual for
encoder.
●
Parts optional by customers: bed plate, diversion sheave (deflection sheave), etc. as per
the order contract.
●
User's special requirements should be specified in the appendix attached to the
contract when the contract is made.
●
In order to avoid increasing the manufacturer's cost and affecting delivery time, it will
be better if users can make selection within the specified scope of supply
3 Handling and Storage of Product
3.1 Storage
●
The traction machine should be stored in an enclosed place which is dry, dustless,
well ventilated and without apparent vibrations.
●
If the machine has been stored for more than 3 months, it should be operated on two
opposite directions for more than 10 minutes at the speed of 20r/min to distribute the
lubricating grease evenly in the bearing in order to avoid the bearing being rusted
3.2 Lifting
●
The lifting hook is only used for lifting the traction machine and its bed plate; any other
weights must not be added
4 Installation
4.1 Preparations prior to the machine installation
●
When the boxes are opened, check the goods by visual to see if they are intact. If
there is damage, and even if it is urgently needed, do not install and operate the
damaged machine
●
Before installation of the machine, calculate permissible load of the base and
foundation to see if they are satisfied.
●
The base and foundation must be firm and hard enough to ensure the machine can be
operated under all permissible load range.
●
The planeness of the ground where the machine will be installed should not exceed
0.2mm.
●
The machine must be installed in a closed room where relative safety protection
measures can be observed. If the machine needs to be installed in a pit, the pit should
Picture 2 product lifting sketch