english Contents General information ..................... 3 Safety information ......................3 Product description ...................... 4 Installation options ....................4 Dimensions ......................4 Package includes ......................5 Required tools ......................5 Installation ........................6 Drill hole ......................... 6 Preparing the wall duct ..................7 Preparing the media cable ..................
The copyright to these instructions remains with Langmatz GmbH. Safety information The product corresponds to the latest state-of-the-art technology at the time of printing and is delivered in an operationally safe condition.
Product description The wall duct is used for the gas- and water-tight sealing of inserted copper or optical fibre cables in buildings and can be used for wall thicknesses of from 200 mm. Properties: Gas- and water-tight to 1 bar | Water impact class to DIN 18533 W1.1-E / W1.2-E / W2.1-E Waterproof concrete stress class 1 to DAfStb 2017 Waterproof concrete stress class 2 to DAfStb 2017...
Installation Drill hole • The substrate must be clean, largely dry, free of dust and grease, and there should be no standing water. • Drill a ø 25 mm (max. ø 26 mm) hole from the inside to the outside. •...
Preparing the wall duct • Fold the foam pipe (1) together. Fig. 7 • Place the universal seal ø 6-13 mm or 2x ø 7mm (3) on the foam pipe (2). • Insert the foam pipe into the outside flange (1). Fig.
Page 8
• Remove the dust protection (1) from the outside flange (2). Fig. 10...
Preparing the media cable Note: Clean the micropipe before use! • Insert the dust protection (1) into the micropipe ø12 (2). Fig. 11 • Insert the micropipe ø 7 or ø 10 (1) into dust protection (2). Fig. 12 • When fitted with micropipes 2x ø...
Inserting the wall duct Note: For installation close above the base plate, continue with Fig. 16. • Position the guide element (1) at the hole and drive in until the base plate is in contact with the wall. • Drill a hole ø 6 at least 50 mm deep. •...
Page 11
• Position the shortened guide element (1) at the hole and drive in until the base plate is in contact with the wall. • Drill a hole ø 6 at least 50 mm deep. • Drive the dowel nail 6x40 mm (3) into the wall and tighten.
Inserting the media cable Note: Keep the media cable (2) free of grease in the foaming area (1). Fig. 19 • Pull the media cable (2) straight and insert it through the foam pipe (1) from the ground side. Note: Ensure sufficient cable length (on the basement side)! The cable can no longer be pulled further once the L100...
Injecting the sealing foam Note: - Reconfiguration is no longer possible after filling with foam! - Use a suitable cartridge gun or alternatively an adapter (see chapter 6.8) for the cartridge (2). Observe the expiry date! Refer to the cartridge label. •...
Continuing the media cable Note: - Before continuing, remove the dust protection and, if necessary, use a suitable tool to clip off the micropipe. - Only continue the media cable upwards after the fibres have been blown in! • Guide the media cable (1) over the guide element (3) to the wall.
Cover (optional) • Place the cover (1) on the guide element (2). Fig. 26 Accessories Article number Designation Figure Accessories kit with adapter 700732500/012 for cartridge gun Packaging unit: 12 pc. Cover for wall duct 094592020/012 Packaging unit: 12 pc.
In this context, the operator of the products supplied by Langmatz GmbH is expressly obliged to decide, based on their own judgement, whether the products are suitable and appropriate for the application or use being considered.