Introduction General Description CAUTION/ATTENTION The SHC onDEMAND eliminates the need to have separate Excessive Chlorine, undissolved Chlore excessive, solides non dissous equipment for heating and cooling while saving installation solids and other improper water et les autres impropre conditions de costs thus reducing the physical footprint and overall conditions WILL DAMAGE the l’eau ENDOMMAGERA l’échangeur...
ClimaCool module’s warranty. A factory authorized technician is required to perform the startup of your ClimaCool chiller . Please contact the ClimaCool Customer Service Department at 405-815- 3000 or technicalsupport@climacoolcorp .com to schedule a date for your startup .
Rigging and Lifting Procedures Rigging Each module should be lifted by using lift straps threaded through the steel base cutouts and the use of a spreader bar . Note: If no spreader bar is used, damage to the unit may occur . Figure 1 Figure 2 Lifting Strap...
ClimaCool recommends locking down the chiller to a concrete base or to three (3) 4” base mounting rails using the six (6) bolt holes provided in each base pan . Due to the low vibration of the modules, ClimaCool does not require the application of 4”...
Recommended Service Clearances Service Clearances SHC - Heat Pump Top View 30” 30” Rear Service Access Front Service Access 36” 36” Service Clearances SHC - Heat Recovery Top View Rear Service Access 30” 30” Front Service Access 36” 36” Notes: 1 .
Unit Installation Unit Placement Grooved Couplings Installation ClimaCool modular chillers must be installed in a conditioned Inspect the pipe ends to ensure they are free from any and dehumidified space. The minimum foundation indentations, projections, roll marks, or other harmful...
Page 13
Unit Installation • Remove the rubber gasket from the coupling . • Open the coupling by completely removing one bolt and • Apply a thin layer of silicone or other non-petroleum nut (see Figure 11) . lubricant to both the inner and outer surface of the •...
Page 14
Unit Installation Header Insulation Chilled water piping is pre-insulated on each module at the factory with ¾” closed cell insulation . After bolting all modules together and leak testing, the entire coupling connection needs to be insulated by the installing contractor . Sound Attenuation Panels and Gasket Attenuation panels are enclosures made of 18 gauge galvanized steel with powder coat paint finish and fiberglass...
Proper clockwise rotation for scroll compressor motors dans dommages ou la mort! is important to prevent damage to the compressors . CAUTION/ATTENTION ClimaCool recommends the use of a phase sequence Unit to be serviced by qualified Conifer la maintenance à un indicating instrument following the manufactures personnel only.
. in both the chilled water and condenser water systems . ClimaCool’s warranty does not cover and does not apply to (See Water Piping Configuration Figures 16 and 17 on page products which have defects or damages due to freezing 18).
Page 19
There are system communication delays, polling and network conflicts that strictly prohibit the use of ClimaCool sensors and controls for control of field supplied bypasses or other field supplied items. The recommended method is to control via differential pressure or gpm flow meters across the chilled water/ evaporator, hot water/condenser and source water systems .
5 . For source, hot and chilled water inlet/outlet location dimensions, refer to pages 4-5 Dimension Data Drawings . 6 . The differential flow sensor provided as part of the ClimaCool Bank Package is a required proof of flow safety device on all water loops .
Filling the Water System Cleaning the System It is imperative that the water systems are free from debris prior to initial operation . See Water Treatment for a The following method is recommended to properly clean comprehensive list of precautions on pages 21 and 22 . the water systems: 1.
316 stainless steel, pure copper and carbon steel . Chlorides Less than 2oo mg/l Other materials may exist external to the ClimaCool chiller . Dissolved Solids Less than 1000 mg/l It is the user’s responsibility to ensure these materials are Iron Less than 5.0 mg/l...
Water Temperature Requirements Load Loops Minimum LWT Maximum LWT Water Temperature Chilled Water 20°F 62°F Limits Hot Water 80°F 135°F Source Loop Minimum LWT Maximum LWT Water Temperature Heating Mode 20°F 62°F Limits Cooling Mode 80°F 135°F Notes: 1 . Operating ibelow 40°F requires adequate glycol/antifreeze solution . 2 .
Operating Limits Voltage Limitations The following voltage limitations are absolute and operation beyond these limitations may cause serious damage to the compressor. Nominal Voltage Minimum Voltage Maximum Voltage 208/230/3/60 460/3/60 575/3/60 SHC onDEMAND - Model UCH ® Water Flow Data Minimum Evaporator Water Flow (gpm) Maximum Evaporator Water Flow (gpm) Minimum Condenser Water Flow (gpm)
Glycol Performance Adjustment Factors Charts Note: Correction factors shown above are to be applied to Std. Product Note: Correction factors shown above are to be applied to Std. Product Data @ ARI 550/590 44°F. Leaving Chilled Water / Data @ ARI 550/590 44°F. Leaving Chilled Water / 85°F Entering / 95°F Leaving Conditioned Water.
Pre-Startup Water System All startups must be performed by ClimaCool factory trained personnel. Prior to chiller startup, there are certain 1. Confirm that leak testing has been carried out. essential checks which must be completed . Failure to carry 2. Confirm that the system is clean.
* This form must be completed and submitt ed to ClimaCool Corp. a minimum of three (3) weeks prior to fi nal scheduling of any Start-up. Note: If any of the above items are not complete at � me of start-up, back charges will be assessed for addi� onal costs.
Startup All startups must be performed by ClimaCool factory 10 . Confirm the jumper locations for all master controller trained personnel. and module controllers as shown on the wiring diagrams provided on the inside electrical door panels . 1 . Review all items are complete from the Pre Startup Check •...
Page 32
Startup 18 . Verify proper communications from each module back Verify proper superheat by subtracting the saturated to the master controller using the “STATUS” menu, then evaporative temperature from the suction line temperature . indexing down to the desired compressor data screen . The saturated evaporative temperature is found by •...
Water Testing All startup paperwork and documentation must be Extract three (3) water samples from each water loop, Hot submitted to ClimaCool . Future warranty claims cannot Water/Condenser, Chilled Water/Evaporator, and Source be processed without a completed Startup and Warranty Water using the bottles provided (three (3) bags;...
. As with any mechanical system, it is necessary to * The temperature drop/rise on a fully loaded (both conduct a series of checks to the ClimaCool chiller to confirm compressors) heat exchanger is generally 10°F . If only correct operation .
Heat Exchangers Draining Chemical Clean In Place Washing With When performing standard maintenance procedures such Water Isolation Valves as flushing a heat exchanger, it will be necessary to isolate Chemical Clean in place washing will typically provide either heat exchanger . This can easily be done with the the best debris removal, even from severely clogged provided factory mounted water isolation valves .
Cleaning Arrangement Figure 1 - City Water Cleaning Arrangement Figure 20 - City Water Cleaning Arrangement Service Port (3/4") Connect to City Water To Cooling Tower Header Refrigerant Circuit Pete's Ports Isolation Ball Valves (2, 2 ½ or 3") Header Refrigerant Circuit From Cooling Tower Connect to Drain...
Compressor Information Adding Oil ClimaCool SHC onDemand use scroll compressors . They are highly efficient and extremely reliable. The information The compressor must never be ran in a vacuum . A suitable contained in this manual will be useful for their care .
. It is necessary to use a micron meter equipped with an absolute pressure gauge (or transducer) to take this reading . ClimaCool recommends the triple evacuation process to ensure proper removal of moisture and contaminants from the refrigeration system .
Engineering Guide Specifications General Compressors Factory-assembled and wired water cooled, water chiller . Each module shall contain two scroll compressors Chiller consists of two compressors, one evaporator and independently circuited for redundancy . Each compressor condenser, safety and operational controls . The modular shall be mounted with rubber isolated compressor mounts to the module base and each shall include compressor water cooled package chiller shall incorporate one or more...
Page 43
Engineering Guide Specifications Any module failure condition shall cause a “fault” indication at the Bank Control Panel and shutdown of that compressor circuit with the transfer of the load requirements to the next available compressor circuit . In the case of a system “fault”...
Options and Accessories Pressure Differential Flow Sensor Field installed to prevent operation of chiller without sufficient water flow to evaporator and condenser. Manual Strainers Field installed strainers are external to the chiller bank to increase efficiency and ensure long life of the modules. A minimum 60 mesh stainless steel screen is required to protect both the condenser and evaporator circuit .
. ClimaCool strongly recommends that safety and an adequate seal . you follow these safety precautions and avoid the potential...
Page 46
Stainless Steel Strainer Option Strainer Element Cleaning Table 2 If the strainer assembly is equipped with optional pressure Bolt Size Recommended Torque Strainer gauges, the operator will be able to monitor the pressure (inches) (ft. lbs.) differential between the inlet and outlet sides of the 3 CS 5/16 - 18 60 - 80...
Page 47
Stainless Steel Strainer Option What is Water Hammer? Figure 24 Water hammer is a phenomenon that can occur in fluid RED POINTER systems with long pipes . Water hammer is a rapid change OUTER RING of pressure caused by a rapid change in velocity. If the flow (TIME BETWEEN has been abruptly shut off downstream, the pressure in the FLUSHES)
Page 48
Stainless Steel Strainer Option Operation Instructions Water Resistance Flush valve line must be piped to atmospheric pressure such The valve and controller are water-resistant, but not as an open floor drain. The flush line should not undergo water-proof . Do not install below ground level where the any changes in elevation and should be sloped downward in component can be submerged in water .
Page 49
Stainless Steel Strainer Option When the differential set point is reached both the audible and visual alarms will be triggered and will remain engaged until both the Alarm condition is corrected and the Alarm- Reset button is pressed . (If the Alarm-Reset button is pressed but the differential pressure is beyond the set point, the alarms will re-engage immediately) .
Y and Basket Strainers “Y” Strainer Basket Strainer Before installing the “Y” strainer (refer to Figure 28), be Before installing the simplex basket strainer (refer to Figure sure its pressure rating is correct for the system . If the 29), be sure its pressure rating is correct for the system . end connections are threaded or designed for soldering or If the end connections are threaded, be sure the piping is brazing, be sure the piping is straight and not at an angle or...
2 . The shown Breaker Panel may be purchased through ClimaCool Corp, but is typically provided by the project electrical contractor . 3 . Breaker panel represents field power supply and is to be installed by others. Not provided as part of the ClimaCool modular chiller system.
Troubleshooting Guide WARNING! disconnect all electrical power including remote disconnects The troubleshooting guidelines recommended in this section before servicing . Follow proper lockout-tagout procedures . could result in exposure to electrical safety hazards . Please Only a qualified licensed electrician or persons trained to refer to the safety warnings provided in this manual .
Page 65
Possible Cause Remedy Improper charging Charge per ClimaCool data plate information, located on the chiller, following the Superheat and Subcooling procedure described in IOM (page 29). Improper chilled water circulation Use an ample sized cleanable strainer in the chilled water circuit; make certain the strainer is clean to insure full flow and velocity of chilled water (strainer screen must be 60 mesh minimum).
Page 68
.climacoolcorp .com ClimaCool works continually to improve its products. As a result, the design and specifications of each product at the time for order may be changed without notice and may not be as described herein. Please contact ClimaCool’s Customer Service Department at (405) 815-3000 for specific information on the current design and specifications.