QuickNet Heating Cable Continuity Monitor
Installation Instructions
Description
The QuickNet-Check monitor is used to verify the continuity of the
QuickNet heating cable and the integrity of its outer jacket during the
installation process. The monitor connects to the cold leads of the cable
and, if the heating cable is damaged, the alarm on the monitor will
sound. The monitor can also be re-used for subsequent installations and
to help troubleshoot any problems that may arise.
Tools Required
• Phillips (No. 1) screwdriver
Other Materials Required
• QuickNet System Installation Manual (H57704)
• QuickStat
• Two (2) AAA batteries
• Use of the QuickNet-Check monitor does not
replace performing the three commissioning
tests as outlined in the QuickNet System
Installation Manual (H57704). The Insulation,
-Check
®
Thermostat Installation and Operation Manual (H57725)
®
A
Front
Heating Cable and Sensor Resistance
tests must be performed as stated in the
Installation Manual and the readings must be
recorded for the warranty to apply.
Back

Advertisement

loading

Summary of Contents for Raychem QuickNet-Check

  • Page 1 QuickNet Heating Cable Continuity Monitor Installation Instructions Description The QuickNet-Check monitor is used to verify the continuity of the QuickNet heating cable and the integrity of its outer jacket during the installation process. The monitor connects to the cold leads of the cable and, if the heating cable is damaged, the alarm on the monitor will sound.
  • Page 2 Detecting a fault in the heating cable before setting it in mortar can help to save both time and rework cost. QuickNet QuickNet Connecting the QuickNet heating mat to the QuickNet-Check monitor to troubleshoot issues after installation • Turn off the power to the QuickNet floor heating system at the circuit • Connect the cold leads to the QuickNet-Check monitor as shown in breaker before starting any work.