GENERAL INSTALLATION GUIDELINES
Inspection / Install Ceiling Cassette
Unpack and Inspect for Freight Damage, continued.
1. Before opening the shipping container, verify the correct unit is included as described in the note on the previous page.
2. Place the box on a solid surface right side up.
3. Cut the white reinforced nylon straps.
4. Open the box.
5. Remove any protective cardboard / Styrofoam
6. The walls and top panels are not attached to the bottom of the box. Lift the cardboard carton by the flaps and remove the box walls and
top and place it to the side.
7. Remove the moisture barrier plastic bonnet.
8. Check the unit nameplate data and model number. Verify the unit voltage, and capacities are correct before proceeding.
9. Locate and retain all included accessories.
10. Using two people, carefully lift the unit and inspect for freight damage.
the frame only. If damage is found, repack the unit as it was received in the original container.
11. If the unit is undamaged, remove and retain the installation manual.
Preparing the Installation Area and Hanging the Indoor Unit Frame
Preparing the Installation Area
1. Installation guide (template) depicts the exact dimensions necessary for the ceiling opening.
2. Choose the location for the indoor unit, and then mark where the suspension bolts, refrigerant piping, and drain hose should be. Suspen-
sion bolt angle should account for drain direction.
3. Drill holes for the bolts. Use either a W 3/8 inch or a M10 size bolt.
Note:
For easier installation, attach the accessories (except for the decoration panel) before hanging the indoor unit.
Figure 6: Using the Level.
Ceiling
Figure 7: Drilling Holes Using Template.
20
top sheets and place to the side.
®
Level
Ceiling
Due to our policy of continuous product innovation, some specifications may change without notification.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. "LG" is a registered trademark of LG Corp.
DO NOT lift by the refrigerant piping or drain pipe stub. Lift by
Figure 8: Ceiling Opening Dimensions and Bolt Locations.
23-1/16 inches ~ 26 inches (Ceiling Opening)
20-3/8 inches
22-15/32 i n ches
Uni t Si z e
18-5/32 inches
F
MULTI
F
MULTI
MAX

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Multi f maxLmcn077hvMulti fLcn127hv4Lmcn185hvLuu097hv ... Show all

Table of Contents