LG LT-E1860RJ Service Manual page 28

Ceiling cassette air conditioner
Table of Contents

Advertisement

CAUTION
Install certainly the decorative panel.
Cool air leakage causes sweating.
Good example
Fit the insulator (this part) and
be careful for cool air leakage
8. Indoor Unit Drain Piping
• Drain piping must have down-slope (1/50 to 1/100):
be sure not to provide up-and-down slope to prevent
reversal flow.
• During drain piping connection, be careful not to
exert extra force on the drain port on the indoor unit.
• The outside diameter of the drain connection on the
indoor unit is 32mm.
Piping material: Polyvinyl chloride pipe VP-25
and pipe fittings
• Be sure to install heat insulation on the drain piping.
Heat insulation material: Polyethylene foam with
thickness more than 8 mm.
Drain test
The air conditioner uses a drain pump to drain water.
Use the following procedure to test the drain pump operation:
Feed water
Drain Pump
Drain pan
Water drops fall.
Bad example
Air conditioner
unit
Ceiling
board
Decorative panel
Pipe clamp
Maintenance
drain port
Flexible drain hose
(accessory)
Main
drain pipe
Drain
port
Glue the joint
Drain hose connection
Use the clip (accessory)
–28–
Air
Indoor unit
• Connect the main drain pipe to the exterior
and leave it provisionally until the test comes
to an end.
• Feed water to the flexible drain hose and
check the piping for leakage.
• Be sure to check the drain pump for normal
operating and noise when electrical wiring is
complete.
• When the test is complete, connect the flexi-
ble drain hose to the drain port on the indoor
unit.
Air conditioner unit
Cool air leakage
(no good)
Ceiling
board
Decorative
panel
Upward
routing
not allowed
1/50~1/100
MAX 700mm