Huawei SUN2000-600W-P Quick Manual page 4

Smart pv optimizer
Hide thumbs Also See for SUN2000-600W-P:
Table of Contents

Advertisement

2.2
Installing the Optimizer
Properly plan the installation position of optimizers to ensure that the cables between the
optimizer and the PV module and between adjacent optimizers can be properly connected, and the
maximum communication distance between the optimizer and the solar inverter is within 350 m.
1. After determining the installation position of the optimizer, remove the SN label from the
optimizer and attach it to the physical layout template. For details, see instructions on the
back of the physical layout template.
2. Install the optimizer based on the selected installation mode.
Installed on an Extruded Aluminum
Profile – T-shaped Bolt
The optimizer is mounted to an aluminum
profile on the front or rear side with T-
shaped bolt and nut.
The T-shaped bolt and nut need to be
purchased separately from Huawei. The
bolt dimensions are as follows.
Installed on a PV Module
Frame – Bolt Assembly
Before installation, ensure that a
mounting hole has been reserved on
the PV module frame.
The bolt assembly and nut need to be
purchased from a third party. Ensure
that the length meets the installation
requirements of the PV module frame.
M8x20 T-shaped bolt
3
Extruded
aluminum
profile
Flange nut
PV module
M8x20 bolt assembly
Flange nut