Nice Sole KIT Instructions And Warnings For Installation And Use page 10

Solar power kit

Advertisement

CHAPTER 5
STEP 1 – Assembly of photovoltaic panel support bracket
Assemble all components of the support bracket on the rear of the
panel, as shown in fig. 3.
Caution! – The bracket at the rear of the panel must be positioned
(fig. 3-b) according to the type of position in which the panel is
mounted. To select the position, refer to fig. 6.
STEP 2 – Photovoltaic panel positioning
Caution! – For optimal operation of the panel, it must be
positioned precisely in the selected location. Therefore, after
performing the checks as described in chapter 3, strictly observe
the following instructions: as a general rule, the panel must be posi-
tioned so that it can receive the maximum possible sunlight during
the day and throughout the year. This means that its horizontal posi-
tion and vertical angle must be calculated on the basis of the location
where it is to be installed.
• Ensure the correct position of the panel on the horizontal
plane as follows:
a) In the installation site, determine the cardinal points NORTH and
SOUTH, with the aid of a compass or a geographical map of the
location.
b) Then position the panel in the direction NORTH or SOUTH,
according to the following:
– if the installation site is in a country North of the equator
(United States; Europe; Russia; etc.) the panel must be posi-
tioned exactly SOUTH;
– if the installation site is in a country South of the equator
(Latin America; Australia; Indonesia, etc.) the panel must be posi-
tioned exactly NORTH.
For further information, refer to fig. 4.
• Ensure the correct position of the panel on the vertical plane
as follows:
Considering that it is preferable to ensure maximum efficiency of the
panel during the winter period, when there is less energy available
than in the summer, the panel should be positioned at an angle that
ensures reception of the sun rays perpendicular (from front) to the
sensitive surface.
This angle corresponds to the latitude of the location and can be
read on any commercial geographical map. For example, Madrid
has a latitude of 40°; Venice 45°; or London approx 50° etc. For
further information, refer to fig. 5.
STEP 3 – Fixing the photovoltaic panel in the selected site
After establishing the precise position of the panel, fix to the selected
surface as shown in fig. 6.
STEP 4 – Fixing the battery in the selected site
After performing the checks as described in chapter 3 and establish-
ing the precise position of the battery, fix to the selected surface as
shown in fig. 13. Note – use the 2 lower screws only if you wish to
anchor the battery in a permanent position, i.e. when removal is not
required.
STEP 5 – Cable routing
IMPORTANT! – The cables supplied must be used in
indoor and protected environments. For use outdoors,
the cables must be protected with adequate ducting.
After fixing the panel and battery, route the panel cable through the
tube or protection ducting through to the battery.
With reference to the instruction manual of the automation to be
powered, remove the control unit protection cover. Then pass the
end of the power cable (with wires exposed) through the automation
3 – English
IS0492A00MM_29-11-2016_SOLEKIT.indd 3
COMPONENT ASSEMBLY AND CONNECTIONS
(where the other cables are routed). Then route the cable through
the protection ducting (if present) through to the battery.
Caution! – Do not connect the power cable to the control unit; leave
access to the control unit open.
STEP 6 – Assembly of "L" socket on the photovoltaic pa nel
cable
If the cable is too long, it can be shortened, taking care to strip the
wires so that their length is equal to the values specified in the fig.
20 (caution! – different lengths may impair subsequent assembly of
the socket).
Then proceed with assembly of the GREY "L" type socket on the
end of the panel cable, as follows:
01. Insert the various elements of the socket on the cable, taking
CAUTION! – Do not modify the electric jumper on the connec-
tor (fig. 8).
02. Using a slotted screwdriver, attach the blue wire to terminal
03. After fixing the two wires, insert the connector in its casing
04. Then pull the cable outwards from the socket and insert the
05. After assembling the socket, position the seal supplied on the
STEP 7 – Assembly of "L" socket on the power cable
If the cable is too long, it can be shortened, taking care to strip the
wires so that their length is equal to the values specified in the fig.
20 (Caution! – different lengths may impair subsequent assembly of
the socket).
Then proceed with assembly of the BLACK "L" type socket on the
end of the power cable, as follows:
01. Insert the various elements of the socket on the cable, taking
CAUTION! – Do not modify the electric jumper on the connec-
tor (fig. 8).
02. Using a slotted screwdriver, attach the blue wire to terminal
03. After fixing the two wires, insert the connector in its casing
04. Then pull the cable outwards from the socket and insert the
05. After assembling the socket, position the seal supplied on the
STEP 8 – Connecting the photovoltaic panel to the battery
To connect the panel to the battery, proceed as follows:
01. Connect the GREY "L" type socket to the "IN" connector on
02. To select the most suitable connection configuration for the
care to observe the sequence as shown in fig. 7;
n° 1 on the connector and the brown wire to the earthing
terminal (4) (fig. 9):
Note – The reference numbers and symbols are printed on the
connector below the terminals and on the opposite side.
(fig. 10).
Important – The correct position of the connector is that
with the earthing symbol in the lower position (see fig. 10);
seal and washer (fig. 11-a-b). Lastly, tighten the cable clamp
(fig. 11-c) using a wrench, to guarantee completely sealed clo-
sure.
connection side (fig. 12).
care to observe the sequence as shown in fig. 7;
n° 1 on the connector and the brown wire to the earthing
terminal (4) (fig. 9):
Note – The reference numbers and symbols are printed on the
connector below the terminals and on the opposite side.
(fig. 10).
Important – The correct position of the connector is that
with the earthing symbol in the lower position (see fig. 10);
seal and washer (fig. 11-a-b). Lastly, tighten the cable clamp
(fig. 11-c) using a wrench, to guarantee a completely sealed
closure.
connection side (fig. 12).
the battery (fig. 14);