INTELLIQUILTER INSTALLATION ON HQ-AVANTE W. PROFESSIONAL TABLE
Version 03.25.16
1. SWITCH CABLE
Unplug the flat cable from the connector on the side of the head.
Plug in the IQ switch cable's in-line adapter.
Reinsert the flat cable.
Fig. 1
Remove the front control box from the handle assembly, and place it on the top of
the handle, so the cable does not get stretched.
Mount the extender brackets as Fig. 2 shows.
Mount the control box on the bottom of the extender brackets.
1

Advertisement

loading
Need help?

Need help?

Do you have a question about the HQ-AVANTE 03.25.16 and is the answer not in the manual?

Questions and answers

Summary of Contents for IntelliQuilter HQ-AVANTE 03.25.16

  • Page 1 INTELLIQUILTER INSTALLATION ON HQ-AVANTE W. PROFESSIONAL TABLE Version 03.25.16 1. SWITCH CABLE Unplug the flat cable from the connector on the side of the head. Plug in the IQ switch cable’s in-line adapter. Reinsert the flat cable. Fig. 1 Remove the front control box from the handle assembly, and place it on the top of the handle, so the cable does not get stretched.
  • Page 2 Fig. 2 Remove the two front screws from the handle. Mount the computer support plate on the top of the handle, using 2 pcs M6 X 60 mm bolts and serrated spring washers.
  • Page 3 Remove the yellow thumbscrews, flip up the computer cradle and mount the computer bracket on the support plate using 4 pcs #10-32x1/4" button-head screws. Fig. 3 Put back the yellow thumbscrews.
  • Page 4 Fig. 4 Plug in the switch cable in the six-pin connector, as shown on Fig. 4. Dock the computer and adjust the height and angle of the computer docking station. Tighten the four screws at that position.
  • Page 5 3. THREAD BREAK DETECTOR Position the thread break detector on the top of the arm, so the hole in the bracket is about 7" (178mm) from the rear edge of the head and the whole adhesive pad is beyond the separation line (see Fig. 5). Mark the position of the edge of the bracket. Fig.
  • Page 6 4. Y-MOTOR Mount the Y-motor on the front left wheel support as Fig. 6 shows. Set the drive and sensor wheels in the middle of the outer surface of the plastic rail and tighten the two bolts, but do not overtighten them. Fig.
  • Page 7 NOTE: On the SuperMotor-V3 make sure that the motor bracket is leveled. The top of the head of the sensor bracket limiting screw should be at least 1/8” (3 mm) to 2/10” (5 mm) elevated above the aluminum block to provide proper movement range for the sensor.
  • Page 8 5. X-MOTOR Remove the cover from the X-motor and put it on the bracket. Place the white spacer hook under the limiting screw as Fig. 8 shows. On the front of the right carriage rail, at about 5-1/2” from the front edge, push up the aluminum mounting block so the bottom of the slot is pressed against the bottom of the rail.
  • Page 9 Fig. 9 Adjust the X-motor’s position using the four-screw cluster on the bracket, so both the drive roller and the sensor wheel run securely on the plastic insert, as shown on Fig. 9. There should be a 1/16" gap (about one credit card thickness) between the drive roller and the track when all the screws are fully tightened.
  • Page 10 In order to stop the plastic insert from moving inside the aluminum track, bolt down both ends with the included #6-32 X ¼” screws. Drill and tap holes at ¾” from each edge of the insert and secure it with the screws. Fig.
  • Page 11 Move the machine all the way to the right (viewed from the back). Stop where the Y- motor is at a safe distance from the bars on the side of the table. Clean the top of the rail next to the carriage wheel on the right thoroughly with alcohol. Remove the protective foil and mount one of the rubber strips on the top of the rail.
  • Page 12: Junction Box

    6. JUNCTION BOX Mount the junction box in the existing holes on the rear crossbar of the carriage, using two ¼”-20 X ½” screws, as shown on Fig. 12. Arrange the wires and the stitch regulator cable as shown. Fig. 12...
  • Page 13: Installation Of Cables

    7. INSTALLATION OF CABLES Plug in the X-motor cable and secure it on the side of the carriage rail with a cable clamp. Run the Y-motor cable at the right side of the machine (viewed from the back), under the control box, along the side of the lower arm. Hold the cable with one adhesive cable clamp as Fig.
  • Page 14 Clean their locations with alcohol and place adhesive cable clamps under the upper arm as Fig. 14 shows. Insert the computer cable in the clamps. Fig. 14...
  • Page 15 Connect the computer power and communication connectors to the docking station as Fig.15 shows. Plug in the thread break detector cable. Fig. 15...
  • Page 16 Remove the protective cover from the power supply connector. Connect the power cable to the power supply: BLACK wire to the negative terminal, the wire with the in-line diode to the positive terminal. Fig. 16 Put back the protective cover. For strain relief, tie the cable to the hole on the side of the power supply with wire tie.
  • Page 17 Fig.17...
  • Page 18 Mount the power supply on one of the middle legs of the table using 14" wire ties, as Fig. 18 shows. Fig. 18...
  • Page 19 Tie the cables to the posts on both motors as Fig. 19 shows. Fig. 19...
  • Page 20 Put the plastic covers on the motors. Pull up the cable in the slot at the side of the cover as Fig. 20 shows. Fig. 20...
  • Page 21: Computer Setup

    8. COMPUTER SETUP Turn on the computer. When the booting completes, the motors will be engaged with the tracks. Select and quit Manual Mode repeatedly to see if the motors are sufficiently disengaged all along the tracks and make the necessary height adjustments.
  • Page 22 COPY THE LOGS AND POST THE logs.tar.gz FILE TO THE SUPPORT PAGE OF www.intelliquilter.com.