  • Page 1 Installation and commissioning instructions MDC0014-02 For Mixergy PV switch...
  • Page 2: About This Module

    About this module The Mixergy PV switch is an intermediary relay device which allows for external 3rd party PV diverters to be integrated with the Mixergy cylinder and share use of the primary immersion. Under idle conditions, control of the immersion is given to the PV diverter.
  • Page 3: Table Of Contents

    Contents About this module Technical data Contents Included items Installation: general guidelines Installation: mechanical Installation: electrical Installation: commissioning Troubleshooting Replacement parts...
  • Page 4: Included Items

    Included items • MAS0086-01 PV ready switch box complete • MEL0049 2m pump cable extension • 2x MME0077 Screw No 8 x 13mm Self Drilling • 2x MME0152 Plastic spacer • Installation guide Installation: general guidelines ENSURE ALL ELECTRICAL SUPPLIES ARE SWITCHED OFF BEFORE MAKING ANY CONNECTION TO THE UNIT.
  • Page 5: Installation: Mechanical

    2. Mount the PV switch either to the side wall of the cylinder (using the included self-drilling screws) or to a nearby wall (using the included plastic spacers). 3. Remove the cover/cap on the primary immersion heater. Disconnect the Mixergy controller’s immersion supply cable from the immersion’s terminals. 3 (SLIM)
  • Page 6: Installation: Electrical

    Installation: electrical 4. Wire the Mixergy controller’s immersion supply cable into the terminals MXL(L), MXN(N), GND(E) on the PV switch. This cable can be extended using minimum 1.5mm2 CSA 3-core H05V2V2-F flex if required. 5. Wire the external diverter’s immersion supply cable into the ter- minals PVL(L), PVN(N), GND(E) on the PV switch.
  • Page 7 Installation: electrical 7. Remove the Mixergy cylinder controller's top cover by unscrewing the screws shown below and pulling the cover away. 8. Unplug the pump from the cylinder controller. 9. Plug the pump cable into either pump port on the PV switch.
  • Page 8: Installation: Commissioning

    3. Set the PV diverter to bypass/boost and check that the immersion is heating via the diverter. 4. Set the Mixergy controller heat source to electric and boost using the gauge, observe that the bypass/boost function of the diverter is switched off and the cylinder continues to heat via. the Mixergy controller supply.
  • Page 9: Replacement Parts

    Replacement parts Do not attempt to repair or replace any parts of the Mixergy cylinder unless you are a trained operative. If you suspect a fault or a replacement part is needed, please contact Mixergy directly. Part description Part no.
  • Page 10 01865 884 343 Mixergy Ltd, 2 Canal View, Wharf Farm, Eynsham Road, Cassington, Oxfordshire OX29 4DB T: 01865 884 343 | www.mixergy.co.uk MIXERGY INSTALLATION AND COMMISSIONING GUIDE MDC0014-02...