Testing And Troubleshooting - Monogram 15900-013 Assembly

Table of Contents

Advertisement

1. Testing
A. Place complete toilet assembly over sink or drain opening. Arrange with toilet drain
valve opening above sink or drain.
B. Connect 28 VDC Power to the toilet. See the wiring diagram (Figure 101) for
connection.
C. Connect a variable pressure water source to the water inlet fitting.
D. Rinse Test
(1)
Introduce the water source at 60 psi(g) to the tank. Check and ensure that
solenoid valve is open.
(2)
Observe pump spray nozzle for free rotation and adequate rinsing of the toilet
tank.
(3)
Remove the water source and disconnect the power source.
(4)
Check and ensure that the solenoid valve is closed. Check for leaks around the
inlet fitting, antisiphon valve and pump exterior.
E. Motor Pump and Timer Test
(1)
Connect the pump and timer to a regulated power supply that conforms to
specified voltage and current requirements.
(2)
Depress pushbutton switch and note toilet function. Cycle duration shall be 10
+ 2 seconds. The swirl pattern should be consistent and vigorous, washing the
complete inner surface of the bowl.
(3)
Repeat flush cycle 3 to 4 times.
(4)
Measure current surge and running current drain (5 amps nominal).
(5)
Inspect for leaks around inlet tube and antisiphon valve.
(6)
Drain toilet.
Monogram Systems
COMPONENT MAINTENANCE MANUAL
BASIC PN 15900

TESTING AND TROUBLESHOOTING

38-31-09
Page 101
May 17/02