Download Print this page

Schier GB-1000-L Installation Manual page 4

100 gpm great basin indoor/outdoor grease interceptor

Advertisement

1
Test Tank for Water Tightness
1a
Cap both connection points with 6" flexible PVC caps.
1c
2
Excavate Burial Pit
18"
Excavate hole at least 18" larger than interceptor on all sides and 12" deeper than tank bottom. Lay a level bed of
well-packed, crushed aggregate (approximately 3/4" size rock or sand, with no fines) in the base of hole.
page 4 of 9
Have a Leak?
Call customer care at 913-951-3300
Hours 8am-5pm CST, M-F
18"
12"
1b
Remove covers. For base unit testing fill with water to
just above the highest connection.
Inspect unit, connections and gaskets for leaks. Check
water level at specific time intervals per local code.
Fill Line
12" or more
Schier | GB-1000-L Installation Guide

Advertisement