Easy-Fit
Marbletrend Easy-Fit Polymarble Shower Base
SHOWER BASE INSTALLATION INSTRUCTIONS
A
Villaboard or
water resistant
wall lining
Tiles or wall
sheeting
Sealant
Mortar bed or Adhesive
B
Timber floor
Install base on mortar bed
or cement-based tile
adhesive
C
Concrete slab
Test water drainage to
waste
D
E
Smartpan/Smartwaste fitting -
lid/cover must remain on
Plumbers, please ensure a copy of the Installation
Instructions are left with the end user for future reference
A.
PRE-INSTALLATION NOTE
Check-in base
as required
B.
TIMBER FLOOR
1. Floor boards or sheet flooring must cover the en re underside of the base.
Bottom
Plate
2. Shower Base to be fixed to floor by spreading cement-based le adhesive on
120mm max.
3. Lay the shower base on the prepared bed and use a spirit level to adjust the
4.
C.
CONCRETE SLAB
1. Any boxed opening in the slab to accommodate the waste must not exceed
2. Shower Base to be fixed to floor by spreading cement-based le adhesive on
300 x 300mm max.
3. Lay the shower base on the prepared bed and use a spirit level to adjust the
4.
5. Backfill the opening in the slab with a 4:1 Washed Sand: Cement mix
D.
SMARTPAN/SMARTWASTE
It is recommended installa on prac ce to check the edge of the base into
the wall by the width of the ling flange in order to achieve a leak-free
junc on with the wall cladding material (see diagram 'A')
Cut a hole for waste no greater than 120 x 120mm.
Note: If renova ng, ensure the floor is structurally sound. Replace the floor
if necessary.
the floor using a 12mm notched trowel, or by use of silicone sealant.
Alterna vely, where the floor is not perfectly level, the base can be set into
a mortar bed - spread a 10mm thick mortar bed of 4:1 Washed Sand: Spread
the mortar over the whole area where base is to be installed then trowel off
level.
Do not use 'Liquid Nails' or similar rigid construc on-type adhesive to
install base.
base to ensure it is level along all sides and diagonally. This will allow the
base to drain properly as it has an inbuilt fall to the waste outlet.
At this point it is impera ve to check that water drains to the waste
outlet prior to lining the shower walls (see diagram 'D'). Failure to do so is
a breach of warranty.
300mm in width beneath the shower base.
the floor using a 12mm notched trowel, or by use of silicone sealant.
Alterna vely, where the floor is not perfectly level, the base can be set into
a mortar bed - spread a 10mm thick mortar bed of 4:1 Washed Sand: Spread
the mortar over the whole area where base is to be installed then trowel off
level.
Do not use 'Liquid Nails' or similar rigid construc on-type adhesive to
install base.
base to ensure it is level along all sides and diagonally. This will allow the
base to drain properly as it has an inbuilt fall to the waste outlet.
At this point it is impera ve to check that water drains to the waste
outlet prior to lining the shower walls (see diagram 'D'). Failure to do so is
a breach of warranty.
ensuring the mortar is packed ghtly around the waste outlet and all the
way back into the boxed sec on of the slab and up to the underside of the
base to give maximum support.
Note: Where required by regula on plas c pipe and fi�ngs may need to be
lagged prior to backfilling.
When the installa on uses these products as the waste collectors, ensure
that the lid/cover is fi�ed, to provide adequate support for the base (see
diagram 'E').
Installation Instructions
Page 1 of 2
Need help?
Do you have a question about the Easy-Fit and is the answer not in the manual?
Questions and answers