General
These instructions apply to the following catalog numbers:
• Circuit breaker modules AMC6EB, AMC4EB,
AMC6EL, AMC6EBS, AMC4EBS, and AMC4SE
• Circuit breaker frames TEB, TED, THED, TEL,
SEDA, SEHA, SELA, and SEPA
Installation
1. Phase balancing for two-pole devices on three-phase
systems. To balance the panelboard load, remove the
screws on the appropriate bus clip, reposition the bus
clip as shown in Figure 1, then install and tighten the
screws to 27–32 in-lb.
Figure 1. Repositioning the bus clip to balance the load.
2. Prepare the module. Remove the protective caps or
insulating tape only from the tops of the stud posts to
which the circuit breaker is to be attached, as shown
in Figure 2. Fasten the filler supports, as shown in
Figure 3, with #10-32 x
to 15–20 in-lb.
Spectra Series™ Power Panelboards
Circuit Breakers and Modules
.
A & C Phase
As Received
A & B Phase
B & C Phase
3
/
" hex-head screws tightened
4
GEH5625 Installation Instructions
Protective Cap
or Insulating
Tape
Do
Figure 2. Removing the cap or tape from the stud posts of the
3
#10-32 x
/
"
4
Hex-Head
Screw
Figure 3. Attaching the filler breaker module.
3. Install the circuit breaker. Remove the lug cover, if
present. Place the
posts, as shown in Figure 4. Secure the breaker to the
module with #10-32 screw and washer assemblies and
3
#8-32 x 2
/
" screws with cup washers. After all screws
4
are in place, tighten the #10-32 screws to 27–32 in-lb
and the #8-32 screws to 15–20 in-lb. Replace the lug
cover, if present.
Stud Post
breaker module.
Filler
Support
side of the breaker over the stud
ON
R04