GG-6 MULTI-CHANNEL GAS DETECTION CONTROL PANEL Installation and Operation Manual...
Page 2
GG-6 Warning Use this product only in the manner described in this manual. If the equipment is used in a manner not specified by Calibration Technologies, the protection provided by the equipment may be impaired. This equipment should be installed by qualified personnel.
Version 2.00 adds time-weighted averaging features to the operating system. The TWA (8 hour) and STEL (15 minute) functions can be enabled through The GG-6 is a six-channel control panel designed to accept industry standard the menu, along with their corresponding alarm setpoints and relay output 4/20 mA input signals.
For GG-XM expansion module installations, mount the units inline from left Locating the GG-6 to right, as shown in the drawing below. The important consideration when installing GG-6 control panel is that it Maximum mounting distance between enclosures is approximately 10 must be easily accessible for operating personnel.
GG-6 Control panel. • Be sure to land the shield conductors of the sensor cables at the shield • 115 VAC, 3A, 50/60 HZ (100-120 VAC).
Page 7
• Length of cable should not exceed 1,500 feet. Analog Output Wiring: (for optional GG-6-AOB) • The analog output is 4/20 mA signal for monitoring by plant PLC or other analog input equipment. It is powered by the GG-6. • Use 2-conductor shielded cable compatible with receiving equipment.
Before applying power, make a final check of all wiring for continuity, shorts, STEL and TWA Reset: Upon power-up, after saving changes to the GG-6 grounds, etc. It is usually best to disconnect external alarms and other...
GG-6 LCD Operator Interface Alternate System Display Screens Key Functions: Below is a list of the common key functions used for the LCD operations: Expansion Modules Below are three alternate system display screens, depending on the number MENU to enter main menu of expansion modules that are selected in the configuration menu.
GG-6 Configuring the Control Panel Navigating the Menu Preparation System Display Screen The key to accurate and timely programming After system power-up, the normal operating is defining the configuration parameters screen will be displayed. It provides at-a- ahead of time. Included with the control...
GG-6 Channel View (cont.) Cal Mode If the STEL-TWA function is set to Active, the Calibration mode allows for sensor calibration real-time value is displayed, along with the time- and maintenance by holding the relays in their weighted average values for the 15 minute short normal state, preventing unwanted alarms.
Down arrow key to advance programming changes to the system. Enter the to next screen. password (last 4 digits of CTI toll-free phone number) with the alphanumeric keys. Enter numbers 1 through 6 to enter CONFIG...
GG-6 Configure Sensor (cont.) To specify which sensor or group that will cause STEL-TWA setpoints and time weighted this action, press ENTER and use up or down averaging: Enabling this feature provides 15 arrow keys to select sensor or group. Press ENTER...
5) Configure System Relay Test The GG-6 is equipped to accommodate both local The relay test menu allows the relay outputs to be and remote mounted reset and silence switches tested individually for correct output functions.
GG-6 Maintenance All gas detection systems should be calibrated with certified calibration gas once every six months. At this interval, all alarm functions and outputs should be tested, verified and documented. If sensor span or zero cannot be adjusted, the sensor may be approaching its end of life and must be replaced.
CTI until receipt by the buyer of shipping instructions from CTI; and c) the right of CTI to require that the buyer provide proof of purchase such as the original invoice, bill of sale or packing slip to establish that the product is within the warranty period.
Need help?
Do you have a question about the GG-6 and is the answer not in the manual?