SeaHawk LDZB6 Quick Start Guide

Thank you for purchasing a SeaHawk LDZB6 zone leak detection circuit board. This
guide outlines device installation and configuration.
If you need further assistance, please contact RLE Technologies via our website -
rletech.com or call us at 800-518-1519.
v2.1
(05/2012)
© Raymond & Lae Engineering, Inc. 2011. All rights reserved. RLE® is a registered trademark and Seahawk™, Falcon™, and Raptor™ are trademarks
of Raymond & Lae Engineering, Inc. The products sold by Raymond & Lae Engineering, Inc. are subject to the limited warranty, limited liability, and
other terms and conditions of sale set forth at http://rletech.com/RLE-Terms-and-Conditions.html.

Supplies for Installation

Available from RLE, sold separately
Circuit board enclosure
24 VDC power supply
Leader cable for each zone
SeaHawk sensing cable - up to 500 feet (152.4m) per zone
End-of-line terminator (EOL) for each zone
Available from Other Vendors
Electrostatic discharge (ESD) protection

Mount the Device

The LDZB6 does not come with an enclosure or mounting hardware. Use the four
provided holes, one in each corner of the circuit board, to secure the board in a
suitable enclosure. Mount the enclosure in the desired location.

Connect the Power and Modbus Relay Output

The LDZB6 requires a 9 – 24 VDC power supply. To avoid product damage or
personal injury, wire power to the slots labeled +DC and –DC in the appropriate
terminal blocks. If you are using just one LDZB6, use the two left-most pinouts
on TB7. If you are using multiple LDZB6s, use TB7 (input) and TB8 (output) to
create a daisy-chained power connection. Establish all wiring connections, including
power, Modbus, and sensing cable, before you activate the board's power supply.
The LDZB6 is not intended to be used as a stand-alone device. It communicates
to a controller via Modbus. If you are installing one LDZB6, use the three right-
most pinouts on TB7 to connect to an EIA-485 network. If you are installing more
than one LDZB6, use the pinouts on TB7 (input) and TB8 (output) to create a
daisy-chained connection. A grounded shield contact is provided for connection to
shielded cable. If the shield contact is used, verify the power connector is properly
grounded and there is no voltage potential between units on the Modbus network.

Install the Sensing Cable

Leader cable is used to connect sensing cable to the LDZB6, since sensing cable
cannot connect directly to the board. Each zone must have its own leader cable,
sensing cable, and end-of-line terminator (EOL).
1. Insert the four stripped wires of the leader cable into the appropriate slots in
the labeled terminal block at the top of the LDZB6:
White wire: insert into pinout labeled W
Black wire: insert into pinout labeled B
Green wire: insert into pinout labeled G
Red wire: insert into pinout labeled R
2. Unscrew the EOL from the end of the leader cable.
3. Attach the first length of sensing cable to the leader cable.
4. Route the sensing cable according to your cable layout diagram.
5. Secure the EOL to the unoccupied end of the sensing cable.

DIP Switches

The LDZB6 has two sets of DIP switches.
Sw1 is used to configure the baud rate and
termination setting. SW2 is used to set the
Modbus address.
DIP Switches - Push the numbered switch up to turn it on;
DIP Switch 1, switches 1 through 8
Set the baud rate for the EIA-485 Port
1 = Off
2 = Off
Modbus 9600 baud
1 = Off
2 = On
Modbus 1200 baud
1 = On
2 = Off
Modbus 19200 baud
1 = On
2 = On
Modbus 38400 baud
Unused Switches
DIP Switches 3 - 7
Currently Unused
EIA-485 Termination Settings
8 = Off
8 = On
EIA-485 Termination - Turn this on if you are only using one LDZB6,
or if the device is the last unit in a daisy chain.
DIP Switch 2 is used to set the address of the Modbus device, which should be a
number between 1 and 254. Adjust the individual switches until their sum equals
the Modbus address. If you are daisy-chaining together multiple LDZB6s, each
board must have its own unique Modbus address. Switch values are as follows:
Example: Modbus address 34
Example: Modbus address 226

LED Indicators

The LDZB6 contains a series of LEDs. The diagram on the back of this page
highlights their locations.
• Heartbeat LED HB - green - blinks - Board is operating normally
• Status LED TX - green - blinks - Board is communicating via Modbus
• Status LED RX - green - blinks - Modbus activity is detected for this board or
another board in the daisy-chain
• Alarm LEDs, one labeled for each zone - red - lights - Alarm condition, either
leak or cable fault, is detected in the zone.

Modbus Registers

The LDZB6 uses its EIA-485 port to communicate via Modbus. The LDZB6 is
configured to act as a slave device on a common network and is a slave only device
– it will never initiate a communications sequence.
Modbus register assignments are as follows:
Register Number Description
Holding Registers
40001
40002 - 40012
40013
40014
40015
40016
40017
40018
Input Registers
30001
Bit
push the switch down to turn it off.
00
01
02
03
04
05
06
07
30002
30003
30004
30005
30006
30007
30008 -30009
30010
30011
Default Value
Leak threshold
60 mA (Range: 25 - 250 mA)
not used
0
Real-time clock days
x
not used
0
Real-time clock hours
x
Real-time clock minutes
x
Real-time clock days
x
Leak delay
5 second (Range: 5 - 999 seconds)
Leak status bitmap
0 - 15
Description
Bit
Description
1 = Zone 1 leak
08
1 = Zone 1 cable break
1 = Zone 2 leak
09
1 = Zone 2 cable break
1 = Zone 3 leak
10
1 = Zone 3 cable break
1 = Zone 4 leak
11
1 = Zone 4 cable break
1 = Zone 5 leak
12
1 = Zone 5 cable break
1 = Zone 6 leak
13
1 = Zone 6 cable break
not used
14
not used
not used
15
not used
Zone 1 leak current
x
Zone 2 leak current
x
Zone 3 leak current
x
Zone 4 leak current
x
Zone 5 leak current
x
Zone 6 leak current
x
not used
x
Firmware version
2xx
Number of zones
6

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SeaHawk LDZB6 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for RLE Technologies SeaHawk LDZB6

  • Page 1 Real-time clock minutes 40017 Real-time clock days DIP Switches Thank you for purchasing a SeaHawk LDZB6 zone leak detection circuit board. This 40018 Leak delay 5 second (Range: 5 - 999 seconds) The LDZB6 has two sets of DIP switches.
  • Page 2 Zone 2 Zone 1 Zone 6 Zone 5 Zone 4 Zone 3 Be sure the leader cable is wired W-B-G-R W-B-G-R W-B-G-R W-B-G-R W-B-G-R W-B-G-R into the correct pinouts. Mounting Holes - One in each corner Set the Baud Rate (switches 1 and 2) and Termination Resistor (switch 8) Modbus Status LEDs TX - Blinks when the board is...

Table of Contents