All installations and services must be performed by qualified service personnel.
design-certified to be resistant to the action of the LP gases should be used on all
threaded joints.
The burner is setup to be piped to the gas supply through the left-hand side of the
furnace. For service purposes, it is recommended the gas union be located inside the
furnace.
A drip leg must be used on both propane and natural gas installations immediately
upstream of the furnace in order to trap oil, condensate, and other impurities which
might otherwise lodge in the gas valve, or plug the main burner orifice. A drip leg shall
be provided at the outlet of the gas meter when there is excessive condensation
between the gas meter and the furnace.
Failure to install drip leg(s) may void the manufacturer's limited warranty on the
furnace.
For natural gas, the maximum supply pressure is 14.0 in. W.G. and the minimum
supply pressure, for purposes of input adjustment, is 5.5 in. W.G.
For propane gas, the maximum supply pressure is 14.0 in. W.G. and the minimum
supply pressure, for purposes of input adjustment, is 11.0 in. W.G.
I. ELECTRICAL WIRING
When testing electrical equipment, always follow standard electrical
:
procedures and precautions.
All electrical wiring must be installed in strict accordance with local ordinances and
codes. In the absence of local ordinances and codes, all electrical wiring must conform
to the requirements of the National Electric Code, ANSI/NFPA 70-1999, or latest
edition.
1. Electrical Branch Supply Circuit
Route all electrical wiring to the left side of the furnace. The power supply circuit to
the furnace must be installed and grounded in accordance with the provisions of the
National Electrical Code, ANSI/NFPA-70-1999, or latest edition, and all local codes
having jurisdiction.
2. Connection Of Power Supply Wires
a. Remove the cover from junction box.
b. Insert 115 VAC wires through the strain relief bushing (or conduit connection as
applicable) on the left side of the furnace junction box.
c. Connect the "hot" wire to the black wire
.