    Before You Begin Orenco works hard to make your installation as easy as possible. Our pump packages are totally integrated and can be installed in most tanks in a matter of hours. All components are designed to fit together well, with a minimum of field cuts.
  • Page 3: Standard On-Lot Components

    Be sure you have the necessary risers, lids, lid screws, riser-to-tank adapters, adhesives, waterproof wire nuts, and other components required to complete the installation. All of these can be found in Orenco’s Product Catalog, which is available from your local distributor, from Orenco, and online at www.orenco.com/products.
  • Page 4: Installation Overview

    – For installing the mounting plate assembly, see NIN-HDA-1, HDA-Style Discharge Assembly Installation Instructions. • To install grommets in access risers and attach the risers to Orenco tank adapters, see NIN-RLA-RR-1, PVC Access Riser Installation Instructions.
  • Page 5: Step 3: Test Tank And Adapter Seams For Watertightness

    Biotube ProPak and LOS Pump Package Installation Manual Installation Steps Step 2. Install Tank Adapters and Risers, cont. Key Points: • Watertight seams and penetrations are critical for proper performance. • Before installing the risers, make sure that: – All risers are the correct height. Recommended riser height is 2in (50mm) above final grade.
  • Page 6: Step 5: Connect Pump Discharge To Transport/Service Line

    Biotube ProPak and LOS Pump Package Installation Manual Installation Steps Step 4. Install Biotube Pump Package, cont. Step 4b: Install the pump and discharge assembly for 4in (100mm) submersible effluent pumps. • For HV-style discharge plumbing, see NIN-HV-1, Pump and Discharge Plumbing Installation Instructions.
  • Page 7: Step 7: Test Pump Voltage And Amperage

    • Use watertight wire connectors to avoid electrical shorts and other issues. • Seal the conduit at the control panel and at the splice box with UL-listed sealing foam, putty, silicone sealant, or an Orenco conduit seal kit. Step 7. Test Pump Voltage and Amperage Perform an operational test on the pump.
  • Page 8: Step 8: Test Float Switches And Control Panel

    Biotube ProPak and LOS Pump Package Installation Manual Installation Steps Step 8. Test Float Switches and Control Panel • If you’re using a generator for pump operation, contact your dealer to make sure it can supply sufficient starting amperage to the pump(s).
  • Page 9 Biotube ProPak and LOS Pump Package Installation Manual Installation Steps Step 8. Test Float Switches and Control Panel, cont. Timed-Dose: “YG,R” or “YG,R,W” Float Switch Assemblies (S1PT or S1PTRO Control Panels) • Place the “Timer On/Off” and the “Redundant Off/Low-Level Alarm” (if included) switches in the “up”...
  • Page 10: Step 9: Complete The Installation

    Biotube ProPak and LOS Pump Package Installation Manual Installation Steps Step 8. Test Float Switches and Control Panel, cont. Step 8c: Snap the float switch assembly back into the bracket. Tee level • Make sure the float switches can move freely up and down without with bracket interference from each other or contact with the vault wall.
  • Page 11 Biotube ProPak and LOS Pump Package Installation Manual Orenco Systems ® • 800-348-9843 • +1 541-459-4449 • www.orenco.com NIM-EPS-1 Rev. 6 © 10/21 Page 11...
  • Page 12 Installation Manual Biotube ProPak & ® ™ LOS Pump Package ™ 1-800-348-9843 NIM-EPS-1 +1 541-459-4449 Rev. 6 © 10/21 www.orenco.com Orenco Systems ®...