Page 2
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Warnings: Please excuse from specification alternations without notice; It is required to comply with the local law, regulations or the permission From local government before installing WTGS;。 。 。 。 Only under no wind weather should carry out the installation, maintenance And dismantling of WTGS;。...
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 1 Abstract The wind turbine generator system is the equipments which could produce electricity by the rotating of blades. The function of the controller is to rectify the output and protect the generator under severe environment.
Page 6
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd from house or areas people gathering. It should be avoided to have trees or buildings nearby to affect the wind speed or wind direction. It is forbidden to install the wind turbine generator on soft lands, uneven ground or areas where the ground can be easily influenced by the climates.
Page 7
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Note:From R1 to R5 is the connector of dump loader. 4.3 Diagram for generator URL: www.f-n.cn...
Page 8
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 4.4 Assembly generator 1. Connect the cable to the bottom of generator, and then make the cable go through the pole center. For E1KW/E2KW/E3KW: Terminal No.1 and No.2 connect with temperature; Terminal No.3, No.4 and No.5 connect with wind generator power cable.
Page 9
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Generat Generat Generat Wire Tempera Tempera Brake Brake or lead or lead or lead (+) (-) ture ture wire wire wire control control (+) (-) 2. Connect the generator with the pole by screw; 3. Blades (1)The flange has been assembled on the motor shaft before delivery...
Page 10
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd not tight the screw before assembling all blades. For finding balance, please make a same distance for every apex, and then tighten the screw. (as below) 。 Note: L1=L2=L3(with tolerance ±5mm) 。 Tighten the screw after finding balance.
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 6. Please connect cable from the tower to the controller. Note, controller should be firstly connect with battery 5. Installation of guy cable tower 5.1Foundation sizing Please install the generator only under no wind weather.
Page 12
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Model Guy cable Guy cable Guy cable Guy cable tower tower tower tower Foundatio Radius( m) Center 0.6*0.6*0 0.6*0.6*0.8 0.9*0.9*1.2 foundation( m) Edge foundation 0.5*0.5*0 0.6*0.6*0.7 0.8*0.8*0.9 ( m) 5.2 For making basement Dig the basement according to the designed size. Then put the anchor in the basement.
Page 13
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 3kw, there needs to be three screw tooth hole forwards to the front side. Placing the concrete after making the basement ready(C25) ,as below, Put the edge anchor into the edge basement, and please check the distance between the hook of basement and the center, including the basic level of basement, and then placing concrete.
Page 14
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd For the 3kw and 5kw, it would need two guy cables for installation, and the picture of edge basements is as below, Notes: To keep the balance of the tension between each cable, the height of the basement need to be same with the base of the tower.
Page 15
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 5.3 Assemble the tower 【2kw and below 2kw】Put the tower into the base, and insert the pins in to the hole for it with screwing the pin shaft nut. As below, 【3KW to 5KW】 Connect the two section of subsidiary pole together, and insert it into the main tower, as below, URL: www.f-n.cn...
Page 16
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Connect 4 pieces of steel wire to the end of the subsidiary pole, and then connect the steel wire which corresponding to the edge basement with the U-shape spend orchid, as below, URL: www.f-n.cn...
Page 17
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd The steel which corresponding to the front basement need to connect with the chain block, as below, Erect the subsidiary pole, and fix the steel wire to the edge basement, as below, URL: www.f-n.cn...
Page 18
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Aim the pin hole of tower to the basement, and insert the pin with smearing grease, as below URL: www.f-n.cn...
Page 19
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Connect each section of the pole by screw as below, 2. To connect the steel wire after connecting the tower as below picture. For safety, you could twine the tower with the steel wire for a circle before fixing the wire with the fixture.
Page 20
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 4. Put the tower on a wooden yoke, height of 1m to 1.5m, as below, 5. Generator installation ( In the manual for generator part) You could erect the tower with a winch, tractor and crane. Please note, when using a winch and tractor, there need to be a yoke for generator below 2kw, including 2kw.
Page 21
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 7. 【3KW and above 3KW】 Please installing the bolts to the three hole at the bottom of the tower after the erecting of the tower. 8. To check the length of 4 pieces of steel wire, and fix it with fixture.
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd down the generator slowly to the yoke. 【If using a tractor or winch】 First, release the steel wire of the basement, and then connect the steel wire to tractor or winch according to the installing manner by reversing it. Finally, lay down the tower on the yoke slowly.
Page 23
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd Parallel connecting is to connect the battery anode with anode, cathode with cathode as below, ※ ※ ※ ※ Please check the notification, using instruction and maintenance with BATTERY INSTRUCTION. URL: www.f-n.cn...
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 7 Wiring diagram 7.1 OFF GRID( ( ( ( Picture as below) ) ) ) Please make sure that the output voltage, voltage of battery and the input voltage of battery should be same. Do not misconnect the end of battery, which would burn the generator, battery and inverter out.
Page 25
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 7.2 ON-GRID( ( ( ( Picture as below) ) ) ) Every model of E-series could be applied for on-grid system with the permission of local government, and on-gird inverter and on-grid controller should be purchased by your own part.
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 8. Maintenance Please check and maintain the generator at a certain time as the environment for generator might be very scurviness. Please lay down the tower before storm coming in case of any trouble. Maintenance plan:...
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd 9. Trouble shooting Why the Electrical equipment failure after connecting with the system? ○ Please check the remaining power the battery, and the electrical equipment would not work if the power is not enough. If the power is enough, please check if the connection between battery and inverter is correct.
Page 28
Yangzhou Shenzhou Wind-driven Generator Co.,Ltd capacity of battery without professional suggestion because it would put the battery always in the state of lacking power. NOTES: Please contact with our engineer by e-mail or mobile if you can ‘not solve the problem.
Need help?
Do you have a question about the E Series and is the answer not in the manual?
Questions and answers