ACTIVITY: - Realization of the hole or the exca- vation, for upper box housing of the Atlantech Lux foundation, to be car- ried out by hydraulic auger and bits in the first case, and by excavator buck- et in the second case.
Page 3
PLATE mo- del, outside the slot for the greater spacing of the PLATE model). - Placing the Atlantech Lux PLATE founda- tion inside the pre-hole or the excavation carried out in step 1. The screwing takes...
Page 4
- Insertion of the perforated plastic cap to close the Atlantech box in the center of the plate. - Passage of the wiring from inside the box through the hole of the plastic cap.
Page 5
- Passage of the cables inside the ligh- ting pole through the hole under the pole plate. - Driving the lighting pole on the bolts of the Atlantech Lux Plate foundation leaning on the nuts/washers set up in step 3. - Positioning of the washers and dou- ble nuts on the bolts to safely check the verticality of the pole.
Page 6
TECHNICAL NOTES FOR INSTALLERS - The Atlantech box must, under all circumstances, be buried for at least half of its height (for example in the PLATE 200-220 and PLATE 270-300 models the height of the box is 80cm, the buried part must be at least 40cm ).