Download Print this page
Techno HD Series Setup Instructions

Techno HD Series Setup Instructions

Advertisement

Quick Links

I. TECHNO HD SETUP
The Techno HD Series Router is powered by 220 Volt AC. Unless specially requested,
the electronics require 3-phase power.
1.1
The Electronics are housed in the large Nema
enclosure as shown in Figure 1.1. When unpacking
the machine avoid twisting the cable carrier that
guides the cables to the motors.
Enclosure
Fig. 1.1
1.2
Open the
back of the
enclosure
(shown in
Fig 1.2)
with the key
provided.
Fig. 1.2
1.3
The electronics will now be visible
and identifiable and will be identical or
like depending on the model issued.
(shown in Fig. 1.3).
The terminals for the
220 volt connection is located at the
bottom of the box (shown in Fig.1.4).
1.4
Have a suitably qualified
person connect the 220V
to the terminals. Make sure
that all local electrical codes
are obeyed. For single
phase machine, connect
power to L1 and L3 only.
Fig. 1.4
www.technocnc.com
A
C
Fig. 1.3
D
L2
L1
HD SERIES Setup Instructions
Tel: 516-328-3970
Email: support@technocnc.com
1.5
Unpack the hand-
held controller
(shown in Fig 1.5)
and carefully
attach this to the
controller board.
(shown in Fig 1.6).
A -Controller Board
B -Stepper Driver
C -24 Volt PSU
D -220 Volt In
B
L3
HTT06031110
Fig. 1.5
1.6
Guide the cable through the hole
on the side of the enclosure and
attach the hand-held controller to
the DB 15 terminal.
(shown in Fig. 1.6).
Fig. 1.6
1.7
If the machine has a vacuum
hold down pump, there is a
matching connector that will
plug into the controller box
(shown in Fig.1.7).
Vacuum Starter
Connection
Fig. 1.7

Advertisement

loading

Summary of Contents for Techno HD Series

  • Page 1 Tel: 516-328-3970 Email: support@technocnc.com I. TECHNO HD SETUP The Techno HD Series Router is powered by 220 Volt AC. Unless specially requested, the electronics require 3-phase power. The Electronics are housed in the large Nema enclosure as shown in Figure 1.1. When unpacking...
  • Page 2 HTT06031110 www.technocnc.com HD SERIES Setup Instructions Tel: 516-328-3970 Email: support@technocnc.com WARNING: Direction of Pump Rotation is critical. Briefly start Pump and check rotation (arrow on casing). Exchange phases if rotation is incorrect. IF YOU RUN THE PUMP/BLOWER CONTINUOUSLY IN THE WRONG DIRECTION, THE VANES WILL BE DAMAGED.