UTICA BOILERS UCS-380 Installation, Operation & Maintenance Manual page 23

Condensing gas fired floor or wall mounted boiler
Table of Contents

Advertisement

• Mark dimension from above on outer aluminum intake
vent. Measure length of waste material, and transfer
dimension to inner grey flue pipe.
• Remove waste from both vents (flue and air). Verify cut
ends are square and free from burrs. Insert flue back into
intake air vent and pass them through hole in wall.
• Check all measurements before cutting. Clearance to
combustible materials is zero when using concentric vent
system.
• After installing venting use calibrated analyzer to verify
there is no recirculation of combustion.
• Ensure minimum downward slope of 2 in (50mm ) for
every 3 ft (1.0m) of flue length toward the boiler.
• Ensure termination is positioned with slots at the bottom.
B.
Concentric Vent Support
• All venting must be supported every 4 ft (1.3 m) using
steel strapping or equivalent. See Figure 6.4.
C.
Flue Options
• Standard horizontal termination is suitable only for
horizontal applications.
• Maximum permissible equivalent flue lengths are:
• Concentric venting = 21 ft (6.4m)
• Any "in line" elbows in flue system must be taken into
consideration.
Elbow
45°
90°
The first elbow in horizontal run is NOT included in any
equivalent length calculations
6 - COMBUSTION AIR AND VENT PIPING
Total Length Reduction
1' 8" (0.5 m)
3' 4" (1.0 m)
FIGURE 6-4 - Steel Strapping or Equivalent