  • Page 1 CBS ArcSafe® RSA-80A (For Westinghouse DB-25) CBS ArcSafe, Inc. 2616 Sirius Road Denton, TX 76208 (940) 382-4411 www.cbsarcsafe.com...
  • Page 2: Installation

    RSA. These items may need to be removed or repositioned for proper RSA installation. Step 2: Next, if it is not already, manually jog the RSA-80A handle adapter to center of its travel to correspond with the “home” position of the Westinghouse DB-25 breaker. See the following image showing the correct handle adapter orientation for installation.
  • Page 3 CLOSE/TRIP handle of the breaker and position the RSA so that the magnets are sitting flush against the surface of the door. See image below for details. Step 4: Next, secure the RSA-80A into place by rotating the handles of each of the two twist- lock magnets 180° clockwise.
  • Page 4 Step 2: Another adjustment which may need to be made is the location of the RSA-80A motor assembly. Adjusting the motor assembly may be necessary in the event that a magnet or other component on the RSA interferes with a component on the breaker or door.
  • Page 5 Step 3: The height of the RSA-80A motor assembly may also be adjusted to account for varying depths of doors or breaker CLOSE/TRIP switches. See the following image for details (This procedure will have to be performed on both sides of the actuator).
  • Page 6 Step 3: Verify the unit is properly installed on the switchgear and connected to the RSO-IIID as previously described. Step 4: Turn the switch on the RSA-80A motor control box to the corresponding operation to be performed (Either Close or Trip).
  • Page 7 RSA-80A Installation and Operation Page | 7...
  • Page 8 Federal, State, Local, and In-house safety regulations and procedures. Attention should be given to distance, angle, and personal protective equipment (PPE). Page | 8 RSA-80A Installation and Operation...