Do you have a question about the CP600 and is the answer not in the manual?
Questions and answers
Алексей
April 23, 2025
Вестерн ср600 при включении в ручном режиме, после двух минутной работы отключается. После запуска опять работает 2 минуты и отключается, что делать как найти неисправность
1 comments:
Mr. Anderson
May 12, 2025
The Western CP600 may turn off after two minutes of operation in manual mode due to the Auto Restart option not being active in Hand (manual) mode. In manual mode, the timer pulse is not applied to the Start circuit, so the machine remains off after a power loss or interruption.
This answer is automatically generated
Алексей
April 23, 2025
Поливная машина в ручном управлении отключается через 2 минуты, потом опять запускаешь и опять через 2 минуты остонавливается, что делать как исправить неисправность
1 comments:
Mr. Anderson
May 12, 2025
To fix the issue of the Western CP600 irrigation machine shutting off after 2 minutes of manual operation, follow these steps:
1. Check Electrical Power: Ensure the main disconnect lever on the main control panel is fully turned on. Verify that all tower disconnect switches are also on.
2. Inspect Lockout/Tagout: Make sure the system is not accidentally locked out. Verify no lockout devices are engaged on the main disconnect or automatic valves.
3. Check for Water Supply: Confirm that all automatic valves are engaged properly and the system is filled with water. If the pivot unexpectedly drains, it may shut down.
4. Inspect Machine Alignment: Improper alignment can trigger shutdowns. Ensure the pivot has a slight leading bow and is aligned as described—start at the pivot and adjust towers accordingly.
5. Look for Pinch Points or Obstructions: Make sure there are no mechanical obstructions or pinch points that could cause the system to stop.
6. Verify All Bolts: Check that all bolts are properly tightened as part of initial startup checks.
If the issue persists after these checks, further electrical or mechanical troubleshooting may be needed.
WARNING: KEEP HANDS AND OBJECTS AWAY FROM MECHANICALLY MOVING PARTS. FAILURE TO DO SO COULD RESULT IN SERIOUS INJURY OR POSSIBLE DEATH. WARNING: STAY CLEAR OF HEAVY MATERIAL BEING LIFTED ABOVE. WARNING: DO NOT CLIMB ON OR JUMP OFF MACHINE. CP600 Pivot Operation Manual...
Page 8
CAUTION: Hard hat and steel toe work boots recommended when assembling equip- ment Lock Out / Tag Out Manufacturer recommends locking the main power disconnect before servicing or troubleshooting electrical components. See Winterization see manufacturers specifications Section 9-24. Note: Manufacture’s general comment, recommendation or instruction. CP600 Pivot Operation Manual...
Section 4 Panel Operation. WARNING MAKE SURE POWER IS DISCONNECTED AT THE MAIN SERVICE PANEL BEFORE PERFORMING ANY ELECTRICAL SERVICE TO THE MACHINE OR BEFORE OPENING THE INNER DOOR OF THE MASTER CON TROL PANEL. CP600 Pivot Operation Manual...
Section 1-6 Machine Alignment Your Western Center Pivot irrigation system should be run with a slight leading bow (center tow- ers ahead of pivot and end tower) in both directions. A correctly aligned machine will have an equal bow when operated in either direction. DO NOT let the machine run with a large leading bow in one direction and a lagging bow in the other.
Page 12
Operation, Safety & Maintenance Section 1-8 Machine Alignment Rotation Forward = Clockwise GOOD Total Bow For System is About One Tire Width Desired Too Much Crooked Trailing Leading Bow Figure 1-8. CP600 Pivot Operation Manual...
• TIRES: Check tire inflation (use low pressure tire gauge). Western Corporation inflates all new tires to a higher pressure for truck loading requirements. Set tire pressure so side wall has slight flex.
Page 15
ELECTRICAL: Check function of automatic switching devices such as Auto Reverse, Auto • Stop and End Gun (lube as required). CONTROL: Check junction box cam and bushings. Turn cam back and forth several • times to ensure there is no binding. CP600 Pivot Operation Manual...
The final drive wheel gearbox, center drive gear motor and the worm gear center drive require pre-season maintenance. Please refer to the following service information for the above items. If you should have any questions, please call your Western Dealer or Customer Service Represen- tative.
Page 17
8. Replace drain plug and refill gearbox through top fill hole to the proper operating level (top of worm gear) as shown below. After one or two hours the oil should be re-checked. Air may be trapped in the gearbox during initial filling. Top off with oil as needed. Figure 1-13. CP600 Pivot Operation Manual...
Page 18
4. Input & output shaft seals should be inspected for excessive leaks and re placed if necessary. 5. Expansion chamber vent holes should be kept clean. Note: Failure to maintain gearboxes as specified will void the gearbox warranty. CP600 Pivot Operation Manual...
Page 19
3. The two (2) drain holes located under the motor can must be kept clear to allow for drain age of accumulated moisture inside the motor if required. Do not Western or remove plug. 4. The two (2) drain holes located under the end bell must be kept clear to allow drainage of accumulated moisture inside of the junction box.
Page 20
3. Input & output shaft seals should be inspected for excessive leaks and replaced if neces sary. 4. Motor drain holes must be kept clear to allow moisture to drain. 5. Expansion chamber vent holes. Figure 1-16. CP600 Pivot Operation Manual...
Page 21
6. Replace drain plug and refill gearbox through top side fill hole to proper operating level (mid worm gear). Refer to gearbox oil specification. After one or two hours the oil should be re- checked. Air may be trapped in the gearbox during initial filling. Top off with oil as needed. CP600 Pivot Operation Manual...
Page 22
3. Input and output shaft seals should be inspected for excessive leaks and should be re placed if necessary. A. Driveline Coupler Maintenance 1. Drive line couplers should be inspected periodically for loose bolts and worn rubber inserts. Worn inserts should be replaced. Figure 1-18. CP600 Pivot Operation Manual...
This standard covers the lockout/tagout procedures you must use when servicing your Western pivot. The intent of Western corporation’s pivot lockout/tagout standard is to protect you or your workers anytime the pivot requires servicing. Before any worker performs maintenance on the piv- ot where unexpected energizing, start up release stored energy could occur and cause injury, the pivot must be isolated and rendered inoperative.
Page 24
Section 1-20 Lockout/Tagout Procedures Your Western pivot requires 480 volt 60 cycle, 3-phase electric power to operate sufficient charge. There is also 110-volt control power throughout the system. Other potential haz- ards include any injected fertilizers and pesticides, and water under pressure.
Page 25
They must be legible. (If you employ migrant workers, the tags should also be bilingual.) • They must not be removed, bypassed, or ignored. • They must be sturdy enough to withstand the elements and be securely attached. CP600 Pivot Operation Manual...
Page 26
Operate the energy isolating devices to restore energy to the pivot. 3. When possible, test run the machine to ensure proper operation. 4. If additional maintenance or service is required, shut down all systems and follow the lockout/tagout procedure again. CP600 Pivot Operation Manual...
4. Turn on air supply. Stand to front or rear of tire when you add air to tire. 5. After tire is at correct pressure, shut off air supply. Release chuck. (See Tire Pressure chart in Specification section.) CP600 Pivot Operation Manual...
6. Protect moving parts and bearing surfaces against rust and corrosion by greasing all fittings. 7. Sufficient oil should be drained from the center and wheel gearboxes to remove water and con- taminants. Refill with manufacturers specified lubricant. CP600 Pivot Operation Manual...
Page 30
Lube and Oil Charts Note: The charts listed above are intended to be used as a quick reference. Review the sections that pertain to the equipment being serviced or the indi- vidual manufacturers warranty for specific details. CP600 Pivot Operation Manual...
General Information Section 2-2 Span Tower Weights and Dimensions Note: For Low Profile Machines, subtract 126lbs or 157.15kg For High Profile Machines, add 280lbs or 127.01kg CP600 Pivot Operation Manual...
Page 43
General Information Section 2-3 Span Tower Weights and Dimensions CP600 Pivot Operation Manual...
. Allow adequate clearance for obstacles . The system passes over to ensure there is no contact if the machine creates wheel ruts during operation . The system may become closer to the ground as it operates . CP600 Pivot Operation Manual...
(as shown) or compression on an ascending slope . Exceeding the slope limitations set forth could create excessive tension and compressive forces in both spans, and especially the pivot point . Figure 3-4b.- High Centering Danger CP600 Pivot Operation Manual...
Page 86
. Note: The transverse slope for the given span length is not to exceed 30% . Must not be more than twice the transverse slope limit and must not exceed 30% . CP600 Pivot Operation Manual...
Page 87
. In this situation, both slopes should be calculated and added together to determine whether or not slope limitations have been exceeded . For example, if the ascending slope was calculated at 7%, and the descending slope 6%, the overall slope would be 13% . CP600 Pivot Operation Manual...
OR POSSIBLE DEATH. The power supply for your Western pivot can be provided by either the electric utility company or by an engine driven generator . The system requires 480 volts, 60 cycle, 3 phase electric power for operation .
Getting Started Section 3-8 Ground Rod Placement Figure 3-8. WARNING: DO NOT OPERATE MACHINE WITHOUT A PROPER EARTH GROUND. REFER- ENCE SECTION 6-3. CP600 Pivot Operation Manual...
Page 91
Getting Started Section 3-9 Ground Rod Placement Figure 3-9. WARNING: DO NOT OPERATE MACHINE WITHOUT A PROPER EARTH GROUND. REFER- ENCE SECTION 6-3. CP600 Pivot Operation Manual...
The concrete pivot pad is the first item of construction. If possible, the concrete work should be done prior to delivery of the machine . Enough time should be allotted to ensure proper curing of the concrete pad . CP600 Pivot Operation Manual...
Getting Started Section 3-13 High Profile Pivot Pad (Concrete) Pad requires approximately 13.2 cubic yards of concrete. CP600 Pivot Operation Manual...
USE CHAIN WITH A PROOF LOAD OF AT LEAST 24 .000 LBS {1/2” GRADE 8} . CONSULT CHAIN MANUFACTURER . THREAD REBAR THROUGH END LINK DETAIL A PAD REQUIRES APPROXIMATELY SCALE 1 : 25 6 .7 CUBIC YARDS OF CONCRETE Figure 3-13. CP600 Pivot Operation Manual...
1- Regular flat screwdriver. CAUTION: Lifting with chain or cable can cause damage to coated surfaces. Note: Since Western Corporation recommends all wiring be completed by a professional electrician, tools involving the electrical hook-up are not included. CP600 Pivot Operation Manual...
3. Hour Meter: Clocks amount of hours pivot is used. 4. Main Disconnect- Disconnects all incoming power from the machine. Note: Panel door will not open unless the Main Disconnect is in the “OFF” position. 5. Operation Indicator Lights: Indicates operations currently in use. CP600 Pivot Operation Manual...
Page 101
USE OVERRIDE UNLESS MACHINE IS IN COMPLETE VIEW. 12. Safety Override: The machine shutdown feature may be overridden by pressing the safety override button and turning the Stop, Run, Start switch to “START”. 13. iControlRemote See Section 1-6 for proper machine alignment. CP600 Pivot Operation Manual...
3. Move selector on panel door to “Fwd” position. 4. Set the Percent Timer on the panel door to desired application rate. NOTE: Reference Sections..for desired results. CP600 Pivot Operation Manual...
Page 103
6. Move Stop-Run-Start switch on panel door to Start to energize safety and latch circuit. 7. Check the lights on the front of the control panel door. The following lights should be ON: RUNNING, FORWARD, SAFETY, END TOWER CP600 Pivot Operation Manual...
3. Move selector on panel door to “Rev” position. 4. Set the Percent Timer on the panel door to desired application rate. NOTE: Reference Sections..for desired results. CP600 Pivot Operation Manual...
Page 105
6. Move Stop-Run-Start switch on panel door to Start to energize safety and latch circuit. 7. Check the lights on the front of the control panel door. The following lights should be ON: RUNNING, REVERSE, SAFETY, END TOWER CP600 Pivot Operation Manual...
Auto Reverse / Auto Off Option The CP600 Auto Reverse / Off option is designed for both End Tower and Pivot Point op- eration. It uses the direction wires in the span cable to send a momentary pulse signal to the main control panel.
Page 107
Panel Operation Section 4-9 Auto Reverse / Auto Off Option CP600 Pivot Operation Manual...
Place the selector switch in the position shown below to prevent the machine from automatically restarting after a power failure Auto Restart On: Place the selector switch in the position shown below to allow the machine to automatically restart- ing after a power failure CP600 Pivot Operation Manual...
Please refer to the iControl Remote documentation for more information regarding proper operation of that option. To enable or disable remote control of your pivot, simply move the selector switch between Panel (disabled) and iControl Remote (enabled). CP600 Pivot Operation Manual...
The machine Safety shutdown feature may be overridden by moving the Direction switch to For- ward or Reverse, pressing the Safety Override button and turning the Stop-Run-Start switch to “Start.” This will force the End Tower to move in the desired direction. CP600 Pivot Operation Manual...
Section 4-13 Disconnect Switch STOPPING YOUR MACHINE IN AN EMERGENCY The CP600 is equipped with a disconnect switch at each tower. An On/ Off switch is located on the underside of each tower junction box, see Figure 4-12a. and Figure 4-12b. Turning this switch to the “OFF”...
Section 5-2 A Word About Proper Grounding Due to the wet environment of irrigation equipment, it is very important that your Western CP600 Center Pivot Irrigation System be properly grounded . The NEC (National Electric Code) requires a grounded conductor of a grounded utility system to extend to every piece of equipment served . This means that for a three-phase electrical system, three power wires and one ground wire are required between your main ser- vice entrance disconnect and the pivot panel .
Electrical Section 5-3 Standard Panel Span Cable Connections SPAN CABLE SIDE PANEL SIDE Note: Field Wiring-Use Copper or Aluminum conductors for at least 60° C. Recommended screw tightening torque is 4.4 lb-in (0.5 Nm). CP600 Pivot Operation Manual...
WARNING! MAKE SURE WIRES CLEAR BRUSH POSTS WHEN MACHINE ROTATES In From Control Panel Note: See WARNING! regarding proper ground brush wiring Section 5-23. Out to Tower No. 1 Collector Ring WARNING! DO NOT CONNECT #6 WIRE TO #9 WIRE. CP600 Pivot Operation Manual...
Note: Wire color in Span Cable is subject to change without notice. Reference will be made here on out to yel/red wire. Depending upon purchase date, your Span Cable may be equipped with tan; yellow/red replaces tan. CP600 Pivot Operation Manual...
Need help?
Do you have a question about the CP600 and is the answer not in the manual?
Questions and answers
Вестерн ср600 при включении в ручном режиме, после двух минутной работы отключается. После запуска опять работает 2 минуты и отключается, что делать как найти неисправность
The Western CP600 may turn off after two minutes of operation in manual mode due to the Auto Restart option not being active in Hand (manual) mode. In manual mode, the timer pulse is not applied to the Start circuit, so the machine remains off after a power loss or interruption.
This answer is automatically generated
Поливная машина в ручном управлении отключается через 2 минуты, потом опять запускаешь и опять через 2 минуты остонавливается, что делать как исправить неисправность
To fix the issue of the Western CP600 irrigation machine shutting off after 2 minutes of manual operation, follow these steps:
1. Check Electrical Power: Ensure the main disconnect lever on the main control panel is fully turned on. Verify that all tower disconnect switches are also on.
2. Inspect Lockout/Tagout: Make sure the system is not accidentally locked out. Verify no lockout devices are engaged on the main disconnect or automatic valves.
3. Check for Water Supply: Confirm that all automatic valves are engaged properly and the system is filled with water. If the pivot unexpectedly drains, it may shut down.
4. Inspect Machine Alignment: Improper alignment can trigger shutdowns. Ensure the pivot has a slight leading bow and is aligned as described—start at the pivot and adjust towers accordingly.
5. Look for Pinch Points or Obstructions: Make sure there are no mechanical obstructions or pinch points that could cause the system to stop.
6. Verify All Bolts: Check that all bolts are properly tightened as part of initial startup checks.
If the issue persists after these checks, further electrical or mechanical troubleshooting may be needed.
This answer is automatically generated